Sign in

Gmb Towers

VADDIRAJ INFRACON · Hanamkonda · RERA P00300004398

GMB TOWERS is a residential apartment project in HUNTER ROAD, Khazipet Mandal, Warangal Urban. It is being developed by the registered promoter VADDIRAJ INFRACON on a site of 6881.84 sq.m, with one residential building of Stilt + 5 Upper Floors and 111 homes: 58 2BHK units and 53 3BHK units. The project is registered under TG-RERA number P00300004398, and its proposed completion date is 30/03/2028.

More from Vaddiraj Infracon · 2 projects →

01What we found

RegisteredTG-RERA - valid till 30 Nov 2027
18documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameGMB TOWERS RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionNot separately identified in the supplied record. The registration concerns GMB TOWERS; phase-wise scope is not disclosed. RERA record
TG-RERA registrationP00300004398, granted under section 5; valid from 11/04/2022 to 30/11/2027. Registration validity is distinct from the project’s stated completion date.
Registered promoterVADDIRAJ INFRACON
RERA statusRegistered; the certificate records a five-year validity period and does not record an extension.

Land and geographic identity

FieldRecord
LocalityHUNTER ROAD RERA record RERA filing
Revenue villageShayampet Jagir Revenue Village is identified in the title documents. The RERA land fields do not disclose a village. Land records
MandalKhazipet Mandal is stated in a title document; the RERA project fields do not disclose a mandal.
DistrictWarangal Urban RERA record RERA filing
PIN506001 in the project identity fields; the registration certificate lists 506001 for the project and records the promoter office PIN as 506002. RERA record
Project survey numbers153/A, 153/B and 153/C RERA record Land records
Registered / sanctioned site extent6881.84 sq.m; sanctioned net area is also 6881.84 sq.m, with road-affected area recorded as 0.00 sq.m. Land records
BoundariesEast: 40 FEET WIDE ROAD; West: LAND OF BOLENA TIRUPATHI GOUD AND OTHERS; North: LAND OF SRIPATHI RAO AND OTHERS; South: PLOTS OF OTHERS. Land records

Development identity

FieldRecord
Sanctioning authorityGreater Warangal Municipal Corporation (GWMC), Town Planning Section Approvals record
Principal building permitApproval number 3001i/;31454/W32/2021; file number TP/647/2021-G1; approved 14/12/2021. Approvals record
RERA-filed plan approval numberHO/Gl/E-120967 /2021 RERA record Approvals record
Approved built-up areaResidential area 15714.90 m². The record separately gives stilt parking area of 3649.30 m²; these figures are not interchangeable.
Building count and configurationOne residential building; sanctioned configuration: Stilt + 5 Upper Floors. RERA filing
Height14.80 m as recorded in the building permit extraction.
Units111 total units in the RERA-derived unit record; the project fields record one building unit. The supplied building-permit extract does not state an approved apartment count. RERA unit table RERA filing

Offering and status

FieldRecord
Configurations2BHK: 58 units; 3BHK: 53 units. RERA unit table RERA unit details
RERA-filed saleable area2BHK: 32.71 sqm; 3BHK: 54.97–77.85 sqm. RERA unit table RERA unit details
Booked / availablePortal-derived record shows 0 booked, 111 available (58 2BHK and 53 3BHK). The booking record has no as-of date and is indicative. RERA unit table RERA unit details
Construction stageNot established by the supplied evidence. The registration and filed documents do not provide a verified current site-progress assessment. Document index
Completion datesPromoter’s Form B undertaking: 30/11/2027. The building-permit extract separately records completion before 13 0· 11"2027; that extracted text is not fully legible. The project header states 30/03/2028 as proposed completion. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied documents. The building permit says an Occupancy Certificate is compulsory before occupation. The evidence does not establish whether any part of the building has received one.

2. The project story

GMB TOWERS is recorded with TG-RERA as a residential apartment project on land identified by survey numbers 153/A, 153/B and 153/C, in the HUNTER ROAD locality of Warangal Urban. Title material identifies the revenue location as Shayampet Jagir Revenue Village and refers to Khazipet Mandal. The project site is recorded as 6881.84 sq.m. RERA record Land records

The building permit allows one residential building of Stilt + 5 Upper Floors. The RERA-derived unit record lists 111 apartments: 58 two-bedroom and 53 three-bedroom units. The supplied evidence does not establish the present construction stage or independently verify the promoter’s completion undertaking. No occupancy or completion certificate is provided, so completion and occupation status cannot be confirmed from this record. RERA unit table

3. Master plan, architecture & building design

The filed building permit describes one residential building on a sanctioned site area of 6881.84 sq.m, with 15714.90 m² recorded as residential area and 3649.30 m² as stilt parking area. The sanctioned configuration is Stilt + 5 Upper Floors, with a recorded height of 14.80 m. The permit lists setbacks of Front 6.00 m, Rear 6.04 m, Side 6.00 m and Side 6.06 m.

The building-permit conditions call for a tot-lot to be fenced and maintained as greenery, a rainwater-harvesting percolation pit, transformer space, and a garbage house. The permit extract does not provide a building footprint, floor-by-floor apartment schedule, lifts, stairs, detailed circulation plan, or a breakdown of residential and common-area floor space.

Two floor-plan drawings are recorded, but both are pending scanning and none has been software-measured. No drawing-based carpet or room measurements are available. The RERA saleable area figures in the unit record are reported separately in the next section; the record does not supply carpet area. Floor plans RERA unit table

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK (filed as DOUBLE BEDROOM)5805832.71 sqmNot measuredNot supplied
3BHK (filed as TRIPLE / TRIPLE BEDROOM)5305354.97–77.85 sqmNot measuredNot supplied

RERA unit table RERA unit details

The saleable-area figures are RERA-filed figures, not drawing-based carpet measurements. No carpet-area measurements, room dimensions, balcony or utility areas, or configuration-specific floor arrangements are available in the supplied drawing record. Although two floor-plan drawings are listed, both are scans pending measurement; the booking and availability figures have no recorded as-of date. Floor plans RERA unit table

5. Parking & vehicle circulation

The building permit records 3649.30 m² of stilt parking area and requires the cellar and stilts approved for parking to be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied extract does not state a car or two-wheeler space count, visitor or accessible parking provision, or the allocation of parking spaces to individual units.

The permit lists road widths of 4.5mts. and 7.62m, and requires a service road wherever required. The supplied documents do not describe ramps, internal driveway design, pedestrian separation, mechanical parking, or EV charging. A parking area recorded in a permit does not by itself establish exclusive unit-level parking rights.

6. Amenities, recreation & open spaces

The RERA-filed amenity record lists the following facilities. It records zero progress for each item; the supplied data does not give a date for that progress snapshot or independently verify completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal Roads & FootpathsSize not statedRERA amenities0%; not independently verified
Water SupplyMarked “YES”; details not statedRERA amenities0%; not independently verified
Sewerage (Chamber, Lines, Septic Tank, STP)Marked “YES”; components/capacities not specifiedRERA amenities0%; not independently verified
Storm Water DrainsDetails not statedRERA amenities0%; not independently verified
Green Strip / TOT LOT / ParkMarked “YES”; size not statedRERA amenities0%; not independently verified
Street LightingDetails not statedRERA amenities0%; not independently verified
Community BuildingsMarked “YES”; type and size not statedRERA amenities0%; not independently verified
Treatment and Disposal of Sewage and Sullage WaterDetails not statedRERA amenities0%; not independently verified
Solid Waste Management and DisposalDetails not statedRERA amenities0%; not independently verified
Water Conservation / Rainwater HarvestingDetails not stated; permit requires a rainwater-harvesting percolation pitRERA amenities0%; not independently verified
Energy managementDetails not statedRERA amenities0%; not independently verified
Fire Protection and Fire Safety RequirementsDetails not statedRERA amenities0%; not independently verified
Electrical Meter Room / Sub-Station / Receiving StationDetails not stated; permit requires transformer spaceRERA amenities0%; not independently verified
Aggregate area of recreational Open SpaceMarked “YES”; area not statedRERA amenities0%; not independently verified

Categories: The project record identifies a tot-lot/green strip and community buildings, but does not specify clubhouse or indoor-recreation facilities, sports facilities, or the type of community buildings. The building permit requires the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate. RERA amenities

7. Utilities, building services & safety

The RERA-filed amenity list marks water supply and sewerage as available, but supplies no source, storage, treatment or capacity details. It also lists storm-water drainage, sewage and sullage treatment, solid-waste management, energy management, rainwater harvesting and electrical meter/substation/receiving facilities, each without technical specifications. These entries are filed amenity data, not evidence that the services are complete or operational. RERA amenities

The building permit requires a rainwater-harvesting percolation pit, space for a transformer and a garbage house. It states that structural and fire-safety requirements are the responsibility of the owner, builder/developer, architect and site engineer. The supplied permit extract and amenity record do not specify fire systems, escape-stair details, lifts, backup power, CCTV, access control, accessibility features, or system capacities. RERA amenities

8. Location, access & connectivity

The registered project locality is HUNTER ROAD, Warangal Urban, PIN 506001. The building-permit document identifies the site at Shyampet and the title record refers to Shayampet Jagir Revenue Village; the RERA land fields themselves leave village and mandal undisclosed. The site boundary record identifies a 40 FEET WIDE ROAD to the east. RERA record RERA filing Land records

The building-permit extract also records road widths of 4.5mts. and 7.62m and provides for a service road wherever required. The supplied data does not establish public-transport access, measured distances to landmarks, or travel times.

9. Developer & development status

The registered promoter is VADDIRAJ INFRACON, identified in the RERA project record as a partnership. The recorded GSTIN is 36AAVFV0356P1Z9. The promoter address is VADDIRAJ GANESH HOUSE, VADDIRAJ COLONY, KHAMMAM FLYOVER, HUNTER ROAD, Warangal Urban, 506001. The RERA record names SHYAMALA DEVI VADDIRAJ and GANESH VADDIRAJ as partners and VIKRAM VADDIRAJ as authorized signatory. No official telephone, email address or website is supplied in the project evidence. RERA filing Corporate record Parties record

In Form B, authorized signatory VIKRAM VADDIRAJ undertakes project completion by 30/11/2027. The project header separately records 30/03/2028 as proposed completion. These are recorded completion-date fields; the supplied evidence does not establish current construction progress or confirm completion. No phase-wise or tower-wise construction schedule is supplied. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP00300004398; issued 11/04/2022; valid to 30/11/2027
What the supplied record establishesRegistration of GMB TOWERS to Vaddiraj Infracon; certificate includes a separate-account condition.
GWMC building permit order
Identifier / dateApproval 3001i/;31454/W32/2021; file TP/647/2021-G1; approved 14/12/2021
What the supplied record establishesPermit for a residential building of Stilt + 5 Upper Floors on Sy.Nos. 153/A, 153/B and 153/C. The permit requires an Occupancy Certificate before occupation.
RERA-filed plan approval identifier
Identifier / dateHO/Gl/E-120967 /2021
What the supplied record establishesListed as the plan approval number in the project record; the supplied evidence does not include a separately extracted approval document under this identifier. RERA record Approvals record
Promoter’s Form B declaration
Identifier / dateDated 24/03/2022
What the supplied record establishesPromoter declaration, including the stated completion undertaking and project-fund declarations.
Title search report filed with TG-RERA
Identifier / dateDated 24-03-2022
What the supplied record establishesAdvocate’s report concerning 8234 sq.yards in Sy.Nos.153/A, 153/B and 153/C at Shyampet Jagir Revenue Village.
Occupancy / completion certificate
Identifier / dateNot supplied
What the supplied record establishesThe available record does not establish that an occupancy or completion certificate has been issued. Document index

The supplied evidence does not include a separately identifiable occupancy or completion certificate, or a complete extracted drawing set for review. The building permit and registration certificate are available project documents; this index does not establish the current status of construction or service delivery. Document index

Frequently asked questions

Is GMB TOWERS registered with Telangana RERA?

Yes. GMB TOWERS is registered with the Telangana Real Estate Regulatory Authority as P00300004398; the registration status is New Project.

Who is the developer of GMB TOWERS?

The promoter named in the RERA registration is VADDIRAJ INFRACON.

Where is GMB TOWERS located?

GMB TOWERS is in HUNTER ROAD, Hanamkonda, Telangana (506001).

When will GMB TOWERS be completed?

The promoter's proposed date of completion filed with RERA is 30/03/2028. This is the promoter's declaration, not a guarantee.

More projects in Hanamkonda