AANDAL ENCLAVE is a plotted residential development in Mahabubnagar, Mahabubnagar Mandal, Mahabubnagar District. The registered promoter is SV TANVI REALTORS AND DEVELOPERS. The layout covers 3 Acer 8.83 Gts 15589 Sq. Yds and comprises 23 residential plots; buildings and floors are not disclosed. It is registered under TG-RERA P01400007165, and the promoter’s Form B declaration states completion by 09/03/2024.

More from Sv Tanvi Realtors And Developers · 3 projects →

01What we found

Period endedTG-RERA registration ran to 9 Mar 2024 - check its extension on TG-RERA
12documents on file - each fact links to its page
0court cases on this project's land in the court records searched
11items to check - 6 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

ItemRecord
Registered project nameAANDAL ENCLAVE RERA record
Project typePlotted residential development / tentative layout RERA filing
Phase / registered portionNew project; registration record identifies the layout project. No separate phase description is disclosed. RERA record Approvals record
TG-RERA registrationP01400007165 Approvals record
Registration validity23/10/2023 to 09/03/2024; the supplied certificate says it is not extended. This is registration validity, not a statement that the layout is complete. Approvals record
Registered promoterSV TANVI REALTORS AND DEVELOPERS (also rendered “Sv Tanvi Realtors And Developers” in the certificate) RERA record Corporate record
RERA statusRegistration certificate issued; the supplied record lists the registration period above. Current registration status beyond that period is not established by the supplied evidence. Approvals record

Land and geographic identity

ItemRecord
LocalityMahabubnagar; the approval identifies MAHABUBNAGAR SHIVAR and PALAKONDA SHIVAR. RERA record
Revenue villagesMahabubnagar Revenue Village is stated in the layout-approval extraction; the title records also identify Christianpally Village and Palakonda Village. The evidence does not reconcile these village labels into one consistent parcel-by-parcel mapping.
MandalMahabubnagar Mandal in the layout-approval extraction.
District / PINMahabubnagar District; 509001 in the project record and registration certificate. RERA record
Survey numbers and subdivisions142/P OF MAHABUBNAGAR SHIVAR and 283/P OF PALAKONDA SHIVAR; the tentative layout approval lists 142/P and 283/P. RERA filing
Site extentLayout approval states 3 Acer 8.83 Gts 15589 Sq. Yds. RERA land details report 13,033.83 sq.m total area, 993.58 sq.m affected area, and 12,040.25 sq.m net area. RERA filing
BoundariesNorth: Sy No 142 and 283; South: Mahabubnagar to Bhoothpur Road and Sy No 142 by P; East: Sy No 283 and 283 by Part; West: Sy No 142 and Sy No 142 by P. RERA filing

Development identity

ItemRecord
Sanctioning authorityMahaboobnagar Municipality / Municipal Corporation; the RERA record lists DTCP as the authority name. Approvals record
Principal approvalTentative Layout Plan 0056/LO/3063/2022, approved 09 March 2022; application 005742/LO/DTCP/3063/0080/2021. Approvals record
Layout scale23 plots, as stated in the approval extraction.
Approved built-up area8606.36 sq.m appears in the RERA project fields; for this plotted development, the supplied evidence does not explain its precise scope. RERA filing
Buildings, floors and parking levelsNot disclosed in the supplied project record. This is a plotted layout rather than a documented apartment-building scheme. RERA filing
Common parkingApproval area statement records 0% common parking space.

Offering and status

ItemRecord
Unit type and countResidential plots; approval extraction states 23 No’s.
Plot-size rangeSoftware-read plot schedule: 125.52–1168.94 sq.m (150.1–1398.0 sq.yd); drawing-derived measurements, not a RERA-filed unit schedule. Layout record
Booked / available countsNot established in the supplied evidence. RERA filing Layout record
Construction stageRERA header records 80% completeness; the supplied material does not establish this as an independently verified site inspection. RERA record
Completion deadlinePromoter’s Form B declaration states completion by 09/03/2024.
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied documents; this is a plotted layout, and the supplied record does not establish final layout release. Document index

The project story

AANDAL ENCLAVE is a 23-plot residential layout recorded under TG-RERA registration P01400007165. The project land is identified by survey subdivisions 142/P OF MAHABUBNAGAR SHIVAR and 283/P OF PALAKONDA SHIVAR. The approval extraction describes the layout location as Mahabubnagar Revenue Village, Mahabubnagar Mandal, while title documents also refer to Christianpally and Palakonda villages.

The tentative layout plan allocates land to plots, roads, open space, social infrastructure and utilities. It also records plots 23, 22, 21 and 20 as mortgaged to the municipality in connection with layout-development conditions. The approval requires infrastructure and amenity works and specifies that the tentative approval itself is not proof of land title.

The project record reports 80% completeness, but the supplied material does not state the date or method for that percentage or provide independent site verification. The promoter’s Form B sets 09/03/2024 as the completion date. Registration validity also ended on that date, but registration validity, the promoter’s completion undertaking and physical completion are separate matters; the supplied documents do not establish final layout release or a completion certificate. RERA record

Master plan, architecture & building design

The approved plan is a tentative layout plan, not a building or apartment floor plan. Its area statement gives a layout extent of 3 Acer 8.83 Gts 15589 Sq. Yds and allocates 2 Acer 5.07 Gts 10293 Sq. Yds (71.48%) to plotted area, 0 Acer 16.66 Gts 2015 Sq. Yds (14%) to roads, 0 Acer 12.39 Gts 1499 Sq. Yds (10.41%) to open space (park), 0 Acer 3.23 Gts 391 Sq. Yds (2.71%) to social infrastructure, and 0 Acer 1.66 Gts 201 Sq. Yds (1.4%) to utilities. The same area statement lists 0 Acer 13.09 Gts 1583 Sq. Yds (15.34%) as mortgage area from plots 23, 22, 21 and 20.

The layout drawing’s plot schedule was software-read as 23 plots. The supplied drawing-derived record says the plot areas sum to the plotted area in the drawing’s area statement, but advises verification against the drawing. No building count, floor configuration, building footprint, residential/commercial building mix or apartment phase organization is evidenced. Layout record

Homes, configurations & floor plans

The offering evidenced in the approved layout is plots, not apartments. The plot schedule was software-read from the drawing and is not a RERA-filed unit schedule. The floor-plan processing record shows two layout sheets and no apartment floor plans measured. Layout record Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Residential plots23 (approval extraction)Not establishedNot establishedNot disclosed as a RERA unit scheduleNot applicableNot supplied

The drawing-derived plot areas range from 125.52 sq.m (150.1 sq.yd) to 1168.94 sq.m (1398.0 sq.yd), with a median of 208.66 sq.m (249.6 sq.yd). These are software-measured plot figures; the supplied record says the plot count and sizes should be checked against the drawing. Layout record

Parking & vehicle circulation

The tentative layout area statement records 0 Acer 0 Gts 0 Sq. Yds (0%) for common parking space. The approval separately identifies plots 23, 22, 21 and 20 as mortgaged to the municipality; it does not establish parking spaces, parking allocation to purchasers, or exclusive parking rights.

The approval requires layout roads to be formed and opened for accessibility to neighbouring sites, and records road area as 0 Acer 16.66 Gts 2015 Sq. Yds (14%). The supplied evidence does not state road widths, vehicle entry/exit arrangements, visitor parking, accessible parking, EV facilities or pedestrian/vehicle separation.

Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Park / open space0 Acer 12.39 Gts 1499 Sq. Yds (10.41%) of the layoutTentative layout approvalReserved in the approved area statement; completion or handover is not established.
Roads0 Acer 16.66 Gts 2015 Sq. Yds (14%)Tentative layout approvalRequired layout infrastructure; completion is not independently verified.
Social infrastructure site0 Acer 3.23 Gts 391 Sq. Yds (2.71%)Tentative layout approvalReserved site; no particular facility or delivery status is identified.
Utilities site0 Acer 1.66 Gts 201 Sq. Yds (1.4%)Tentative layout approvalReserved site; the approval lists utility uses, but completion is not established.
Green strip / parkRERA amenity record marks this item available, with 50% shownRERA amenitiesRERA-reported progress indicator; not independent verification of completion.
Community buildingsNo size or facility description suppliedRERA amenitiesAmenity record shows 0%.
Common parking space0 Acer 0 Gts 0 Sq. Yds (0%) in the approval area statementApproved area statement; no common parking space is allocated there.

The approval requires works including avenue planting, fencing of open spaces, rainwater-harvesting pits and street lighting. These are approval conditions, not evidence that the works have been completed.

Utilities, building services & safety

The tentative approval requires provision of a protected water supply and sewerage-disposal system, construction of drains and channelization of nalas for storm-water runoff, rainwater-harvesting pits, street lighting and electricity facilities. It also identifies a water reservoir, septic tank / sewerage treatment plant, electric transformer and solid-waste management among utility provisions. These are approval requirements or stated utility uses; the supplied documents do not establish capacities or independent completion.

The RERA amenity record marks water supply, sewerage (including chambers, lines, septic tank and STP), storm-water drains, water conservation/rainwater harvesting, street lighting, and electrical meter room/sub-station/receiving station as available, each with 50% shown. The same record lists treatment and disposal of sewage and sullage, solid-waste management, energy management and fire protection/fire-safety requirements at 0%. The supplied record does not define the measurement date or independently verify these progress indicators. RERA amenities

No building lift, backup-power, fire-system capacity, security/CCTV or accessibility details are supplied. Document index RERA amenities

Location, access & connectivity

The project’s registered location is Mahabubnagar, PIN 509001, with survey identifiers 142/P OF MAHABUBNAGAR SHIVAR and 283/P OF PALAKONDA SHIVAR. The tentative layout approval describes the land as in Mahabubnagar Revenue Village and Mahabubnagar Mandal, and gives the southern boundary as Mahabubnagar to Bhoothpur Road. RERA record

The supplied location record identifies Financial District (Nanakramguda), 1.2 km from the recorded cadastral parcel centroid; this is a recorded distance, not a travel-time estimate. The project evidence does not provide public-transport details or verified distances to other landmarks. Location record

Developer & development status

The registered promoter is SV TANVI REALTORS AND DEVELOPERS, identified in the project record as a partnership with GSTIN 36AEAFS5999E1ZL. The project’s registered promoter office is recorded on the RERA certificate as Village: Madhapur, Mandal: Serilingampally, District: Ranga Reddy, Pin: 500081. The project record separately gives an address at Raghuma Towers, Madhapur, Mahabubnagar, Mahabubnagar, Mahabubnagar, 509001. Corporate record

The Form B declaration, made by KUMBHAM SRINIVAS REDDY as authorized representative, identifies Smt. S. ANDALAMMA as landowner, refers to Development Agreement-cum-General Power of Attorney Doc. No. 9250/2023, declares the land free from encumbrances and undertakes completion by 09/03/2024. These are promoter declarations in the filed affidavit.

The RERA header reports 80% completeness; the supplied material does not establish an independently verified construction stage. No revised completion date or phase-specific completion status is supplied. RERA record

Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01400007165, issued 23/10/2023; valid through 09/03/2024
Scope and evidenceCertificate for AANDAL ENCLAVE; includes registration conditions, including the separate-account condition.
Tentative layout approval
Identifier / date0056/LO/3063/2022, approved 09 March 2022
Scope and evidenceMahaboobnagar Municipality / Municipal Corporation; 23-plot layout. Application 005742/LO/DTCP/3063/0080/2021.
Municipal mortgage deed
Identifier / date2909/2022, dated 04 March 2022
Scope and evidenceApproval record identifies plots 23, 22, 21 and 20, with mortgage area 0 Acer 13.09 Gts 1583 Sq. Yds.
Development Agreement-cum-General Power of Attorney
Identifier / date9250/2023, dated 16 August 2023
Scope and evidenceFiled title document for the landowner/developer arrangement; it concerns development rights for the stated layout land.
Gift Deed
Identifier / date9249 of 2023, dated 16 August 2023
Scope and evidenceFiled document concerning designated layout land gifted to the municipality for public use.
Land-conversion orders
Identifier / dateProceedings 2100969254 and 2100963839, dated 22.10.2021; 23.10.2021
Scope and evidenceFiled NALA conversion-order references.
Title search report
Identifier / dateDated 16.09.2023
Scope and evidenceAdvocate B. Satish Kumar’s filed title-search report.
Form B declaration
Identifier / dateDeclaration date extracted as “1) ay or Octaber 2023”
Scope and evidencePromoter affidavit identifies the landowner, development agreement reference and completion undertaking.

The supplied files do not include a final layout-release document or completion certificate. The layout approval is expressly described as tentative.

Frequently asked questions

Is AANDAL ENCLAVE registered with Telangana RERA?

Yes. AANDAL ENCLAVE is registered with the Telangana Real Estate Regulatory Authority as P01400007165; the registration status is New Project.

Who is the developer of AANDAL ENCLAVE?

The promoter named in the RERA registration is SV TANVI REALTORS AND DEVELOPERS.

Where is AANDAL ENCLAVE located?

AANDAL ENCLAVE is in Mahabubnagar, Telangana (509001).

When will AANDAL ENCLAVE be completed?

The promoter's proposed date of completion filed with RERA is 09/03/2024. This is the promoter's declaration, not a guarantee.

More projects in Mahabubnagar