Sri Manikanta Town Ship
GANGAREDDY · Nizamabad · RERA P03100005954
SRI MANIKANTA TOWN SHIP is a plotted development located at BORGAON (P)SHIVAR MUGPAL MANDAL ,NUDA, MUPKAL (NEW), Nizamabad district. The registered promoter is Gangareddy Govind Gari. The site extent is 9865.84 sq. m and the layout comprises 30 plots; plot sizes are 122.59–224.86 sq. m. The TG-RERA registration number is P03100005954, and the promoter’s Form-B undertaking states completion by 27/01/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SRI MANIKANTA TOWN SHIP |
| Project type | Plotted development / 30-plot layout RERA record |
| Phase or registered portion | Phase not separately identified; registration covers the project on the survey numbers listed below |
| TG-RERA registration | P03100005954 |
| Registration validity | Certificate states validity from 01/04/2023 to 27/01/2026; it records a two-year period. No extension is recorded in the supplied certificate. Registration validity is separate from the completion undertaking below. |
| Registered promoter | Gangareddy Govind Gari; the filed Form-B declaration names GOVIND GARI GANGAREDDY as promoter. |
| RERA status | Certificate records registration granted under section 5. Current status after the certificate’s stated expiry is not established by the supplied record. |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / address as filed | BORGAON (P)SHIVAR MUGPAL MANDAL,NUDA RERA filing |
| Revenue village | RERA filing identifies Nuda; the draft layout approval identifies Borgoan. The supplied records do not reconcile the revenue-village identity. RERA filing |
| Mandal | MUPKAL (NEW) RERA filing |
| District | Nizamabad RERA filing |
| PIN | 503230 RERA filing |
| Project survey numbers and subdivisions | 221/A, 221/AA, 221/E, 221/EE, 221/AE, 221/I, 222/A/1, 222/A/2 |
| Registered site extent | 9865.84 sq. m (also stated as Ac. 2.44 gts) RERA filing |
| Net / total area | RERA filing gives total area 9865.84 sq. m, affected area 0, and net area 9865.84 sq. m. RERA filing |
| Boundaries as filed | East: ROAD; West, North and South: OTHERS LAND. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority / principal approval | Draft technical layout pattern approval communicated by Nizamabad Urban Development Authority (NUDA), approval number Draft - TLP.NO.3146/Borgoan P/2020/0064 UDA, dated 28 January, 2021. |
| Plan / letter reference | 3146/BORGOAN P/2020/0064; letter reference Lr.Roc.No.3146/Borgoan P/2020/0064. RERA filing |
| Plots | Approval document states 30 plots; the layout drawing’s schedule was software-read as 30 plots. Layout record |
| Land-use areas in drawing | Plotted area 4957.67 sq. m; road area 3562.66 sq. m; park/open space 741.36 sq. m; social infrastructure 251.81 sq. m. These are drawing-derived figures; the drawing’s printed percentages are reproduced in the Master plan section. Layout record |
| Approved built-up area | RERA filing lists 4957.67 sq. m as “Approved Built up Area”; the supplied evidence does not further define that field for this plotted layout. RERA filing |
| Buildings / floor configuration | Not disclosed; the project is recorded as a plotted layout, not a multi-storey building development. RERA record |
| Mortgage area | RERA filing records 773.24 sq. m. The draft approval describes a 15% plotted-area mortgage to NUDA as security for development works and conditions. RERA filing |
Offering and status
| Item | Project record |
|---|---|
| Offering | Plots; the approval document specifies 30 plots. |
| Plot size range | Software-measured from the layout drawing: 122.59–224.86 sq. m (146.6–268.9 sq. yd); median 166.36 sq. m (199.0 sq. yd). Verify against the drawing before relying on an individual plot measurement. Layout record |
| Booked / available counts | Not disclosed in the supplied project data. |
| Construction / development stage | No verified current site-progress evidence supplied. The approval document requires development works; amenity progress fields are recorded as 0%, which does not establish site-wide physical progress. RERA amenities |
| Completion date | Promoter’s Form-B undertaking states completion by 27/01/2026. This is a declared completion date, not a verified completion finding. |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. For this plotted-layout project, the supplied records do not establish whether any relevant completion certificate has since been issued. |
2. The project story
SRI MANIKANTA TOWN SHIP is registered as a plotted development in the Borgaon/Mugpal–Mupkal area of Nizamabad district. The project record covers eight survey numbers and subdivisions and identifies a 30-plot layout. The site is shown as 9865.84 sq. m in the RERA filing, with roads, a park/open-space area and social infrastructure identified in the layout’s area statement. RERA record RERA filing Layout record
The layout approval document describes a draft technical layout pattern approval and sets out development conditions, including completion of specified works and a mortgage in favour of NUDA. The supplied material does not establish the present physical completion of those works or the release of any mortgaged plots. The promoter declared a completion date of 27/01/2026; no current progress report or completion/occupancy certificate is included here.
3. Master plan, architecture & building design
This is a plotted layout rather than a documented apartment or multi-storey building scheme. The layout drawing contains one sheet and a schedule read by software as 30 plots; the project evidence states all 30 plot sizes were extracted, with the caveat that measurements should be checked against the drawing. Layout record
| Layout land use | Area | Printed percentage on drawing |
|---|---|---|
| Plotted area | 4957.67 sq. m | 50.57% |
| Roads | 3562.66 sq. m | 36.34% |
| Parks / open space | 741.36 sq. m | 7.56% |
| Social infrastructure | 251.81 sq. m | 2.57% |
| Amenities | 0.00 sq. m | 0.00% |
The drawing-derived land-use percentages are those printed on the layout; the supplied area record also calculates percentages using the drawing’s stated land-use base of 9513.5 sq. m. The overall registered site extent is separately recorded as 9865.84 sq. m. Layout record RERA filing
The approval document refers to roads 18 mts and above and lists proposed layout infrastructure such as storm-water drains, underground drainage lines, a common septic tank/STP, internal water-supply pipelines, an overhead tank, transformer, avenue plantation, park development and rainwater-harvesting pits. These are approval-document descriptions, not evidence that the works are complete.
4. Homes, configurations & floor plans
The registered offering is plots, not flats. No RERA-filed plot-by-plot saleable-area schedule, booked inventory or availability count is supplied in the project data.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 30 (approval document and drawing schedule) | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not supplied |
The layout drawing’s plot schedule was software-read as 30 plots, with sizes ranging from 122.59 sq. m to 224.86 sq. m. The size bands read from the drawing are:
| Plot size band | Number of plots |
|---|---|
| 100–150 sq. yd (84–125 sq. m) | 2 |
| 150–200 sq. yd (125–167 sq. m) | 16 |
| 200–250 sq. yd (167–209 sq. m) | 10 |
| 250–300 sq. yd (209–251 sq. m) | 2 |
These are software-measured drawing-derived values, not RERA-filed saleable areas; verify any specific plot dimensions against the approved drawing and plot schedule. Layout record
5. Parking & vehicle circulation
The supplied records do not state a parking-space count, visitor or accessible parking provision, mechanical parking, EV charging, or plot-specific parking allocation. The layout approval identifies roads and road widths of 18 mts and above, but does not provide a detailed vehicle-circulation or driveway schedule in the supplied extraction. A road or parking mark on a drawing, if present, would not by itself establish an exclusive allocation to a purchaser. Layout record
6. Amenities, recreation & open spaces
The project record lists layout-level infrastructure and community/open-space items. The amenity register marks several items “YES,” but shows 0% progress for the listed items; this does not independently verify completion.
| Description / size | Layout roads; approval document refers to road widths 18 mts and above. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed “YES”; 0% recorded. Completion not independently verified. |
| Description / size | 741.36 sq. m; drawing prints 7.56%. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Park development listed in approval conditions; completion not verified. |
| Description / size | 251.81 sq. m; drawing prints 2.57%. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Listed in the approval document; delivery/status not verified. |
| Description / size | Internal water-supply pipelines and overhead tank are listed in the approval document. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed “YES”; 0% recorded. Completion not independently verified. |
| Description / size | Underground drainage lines and common septic tank/STP are listed. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed “YES”; 0% recorded. Completion not independently verified. |
| Description / size | Storm-water drains are listed. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed “YES”; 0% recorded. Completion not independently verified. |
| Description / size | Rainwater-harvesting pits are listed. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Listed “YES”; 0% recorded. Completion not independently verified. |
| Description / size | Listed as a layout development item. |
|---|---|
| Declared progress / verified status | Completion not verified. |
| Description / size | Transformer and utility provision are listed; the layout area statement records 0 sq. m for amenities and a utility line with no separate stated area in the supplied extraction. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Electrical meter room/sub-station/receiving station listed “YES”; 0% recorded. Completion not independently verified. |
No clubhouse, indoor recreation facility or sports facility is established in the supplied project record.
7. Utilities, building services & safety
The approval document lists internal water-supply pipelines, an overhead tank, underground drainage lines, a common septic tank/STP, storm-water drains and rainwater-harvesting pits. It also lists a transformer. These are proposed or approval-recorded layout works; capacities, water source, treatment specifications, power-backup arrangements and completion evidence are not supplied. RERA amenities
The amenity register includes solid-waste management, energy management, fire protection and fire-safety requirements, street lighting and sewage/sullage treatment and disposal, but the supplied records do not provide system specifications, capacities or verified completion status. As a plotted layout, apartment-building services such as lifts and escape stairs are not established or applicable from the available evidence. RERA amenities
8. Location, access & connectivity
The official project filing identifies the location as BORGAON (P)SHIVAR MUGPAL MANDAL,NUDA, MUPKAL (NEW) mandal, Nizamabad district, PIN 503230. The RERA record identifies the revenue village as Nuda, while the draft layout approval describes the village as Borgoan; the supplied records do not resolve that identification. RERA filing RERA filing
The site boundary entry identifies a road on the east and other land on the west, north and south. The location data supplies one connectivity reference: Financial District (Nanakramguda), 1.2 km. The supplied data does not describe the approach route or public-transport services. RERA filing Location record
9. Developer & development status
The TG-RERA registration certificate names the promoter as Gangareddy Govind Gari; the Form-B affidavit is signed by GOVIND GARI GANGAREDDY as promoter. The promoter’s legal entity type, corporate registration number and registered office are not established in the supplied material. Corporate record
The promoter declared that the project would be completed by 27/01/2026 and that project funds would be handled through the separate-account arrangement described in the affidavit. The supplied evidence does not include a current construction-progress report, verified physical inspection, or subsequent certificate confirming completion.
10. Approvals, official records & documents
| Record | Details in supplied evidence |
|---|---|
| TG-RERA registration certificate | Form C; registration P03100005954, granted under section 5; certificate states validity from 01/04/2023 to 27/01/2026. |
| Layout approval document | NUDA draft technical layout pattern approval; Draft - TLP.NO.3146/Borgoan P/2020/0064 UDA, dated 28 January, 2021; reference Lr.Roc.No.3146/Borgoan P/2020/0064. |
| Development-charges proceedings | ROC.No 1234/2016/P, dated 26-10-2018, listed in the layout approval document. |
| Promoter declaration | Form-B affidavit-cum-declaration by GOVIND GARI GANGAREDDY, including the declared title and encumbrance statements and completion undertaking. |
| Other approvals / certificates | No separate current completion or occupancy certificate is supplied. The approval document is described as a draft layout pattern approval; the supplied record does not include a later final layout-release certificate. |
1. Project at a glance
Project identity
Registered project name: SRI MANIKANTA TOWN SHIP
Project type: Plotted development / 30-plot layout
Phase or registered portion: Phase not separately identified; registration covers the project on the survey numbers listed below
TG-RERA registration: P03100005954
Registration validity: Certificate states validity from 01/04/2023 to 27/01/2026; it records a two-year period. No extension is recorded in the supplied certificate. Registration validity is separate from the completion undertaking below.
Registered promoter: Gangareddy Govind Gari; the filed Form-B declaration names GOVIND GARI GANGAREDDY as promoter.
RERA status: Certificate records registration granted under section 5. Current status after the certificate’s stated expiry is not established by the supplied record.
Land and geographic identity
Locality / address as filed: BORGAON (P)SHIVAR MUGPAL MANDAL,NUDA
Revenue village: RERA filing identifies Nuda; the draft layout approval identifies Borgoan. The supplied records do not reconcile the revenue-village identity.
Mandal: MUPKAL (NEW)
District: Nizamabad
PIN: 503230
Project survey numbers and subdivisions: 221/A, 221/AA, 221/E, 221/EE, 221/AE, 221/I, 222/A/1, 222/A/2
Registered site extent: 9865.84 sq. m (also stated as Ac. 2.44 gts)
Net / total area: RERA filing gives total area 9865.84 sq. m, affected area 0, and net area 9865.84 sq. m.
Boundaries as filed: East: ROAD; West, North and South: OTHERS LAND.
Development identity
Sanctioning authority / principal approval: Draft technical layout pattern approval communicated by Nizamabad Urban Development Authority (NUDA), approval number Draft - TLP.NO.3146/Borgoan P/2020/0064 UDA, dated 28 January, 2021.
Plan / letter reference: 3146/BORGOAN P/2020/0064; letter reference Lr.Roc.No.3146/Borgoan P/2020/0064.
Plots: Approval document states 30 plots; the layout drawing’s schedule was software-read as 30 plots.
Land-use areas in drawing: Plotted area 4957.67 sq. m; road area 3562.66 sq. m; park/open space 741.36 sq. m; social infrastructure 251.81 sq. m. These are drawing-derived figures; the drawing’s printed percentages are reproduced in the Master plan section.
Approved built-up area: RERA filing lists 4957.67 sq. m as “Approved Built up Area”; the supplied evidence does not further define that field for this plotted layout.
Buildings / floor configuration: Not disclosed; the project is recorded as a plotted layout, not a multi-storey building development.
Mortgage area: RERA filing records 773.24 sq. m. The draft approval describes a 15% plotted-area mortgage to NUDA as security for development works and conditions.
Offering and status
Offering: Plots; the approval document specifies 30 plots.
Plot size range: Software-measured from the layout drawing: 122.59–224.86 sq. m (146.6–268.9 sq. yd); median 166.36 sq. m (199.0 sq. yd). Verify against the drawing before relying on an individual plot measurement.
Booked / available counts: Not disclosed in the supplied project data.
Construction / development stage: No verified current site-progress evidence supplied. The approval document requires development works; amenity progress fields are recorded as 0%, which does not establish site-wide physical progress.
Completion date: Promoter’s Form-B undertaking states completion by 27/01/2026. This is a declared completion date, not a verified completion finding.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. For this plotted-layout project, the supplied records do not establish whether any relevant completion certificate has since been issued.
2. The project story
SRI MANIKANTA TOWN SHIP is registered as a plotted development in the Borgaon/Mugpal–Mupkal area of Nizamabad district. The project record covers eight survey numbers and subdivisions and identifies a 30-plot layout. The site is shown as 9865.84 sq. m in the RERA filing, with roads, a park/open-space area and social infrastructure identified in the layout’s area statement.
The layout approval document describes a draft technical layout pattern approval and sets out development conditions, including completion of specified works and a mortgage in favour of NUDA. The supplied material does not establish the present physical completion of those works or the release of any mortgaged plots. The promoter declared a completion date of 27/01/2026; no current progress report or completion/occupancy certificate is included here.
3. Master plan, architecture & building design
This is a plotted layout rather than a documented apartment or multi-storey building scheme. The layout drawing contains one sheet and a schedule read by software as 30 plots; the project evidence states all 30 plot sizes were extracted, with the caveat that measurements should be checked against the drawing.
| Layout land use | Area | Printed percentage on drawing |
|---|---|---|
| Plotted area | 4957.67 sq. m | 50.57% |
| Roads | 3562.66 sq. m | 36.34% |
| Parks / open space | 741.36 sq. m | 7.56% |
| Social infrastructure | 251.81 sq. m | 2.57% |
| Amenities | 0.00 sq. m | 0.00% |
The drawing-derived land-use percentages are those printed on the layout; the supplied area record also calculates percentages using the drawing’s stated land-use base of 9513.5 sq. m. The overall registered site extent is separately recorded as 9865.84 sq. m.
The approval document refers to roads 18 mts and above and lists proposed layout infrastructure such as storm-water drains, underground drainage lines, a common septic tank/STP, internal water-supply pipelines, an overhead tank, transformer, avenue plantation, park development and rainwater-harvesting pits. These are approval-document descriptions, not evidence that the works are complete.
4. Homes, configurations & floor plans
The registered offering is plots, not flats. No RERA-filed plot-by-plot saleable-area schedule, booked inventory or availability count is supplied in the project data.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 30 (approval document and drawing schedule) | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not supplied |
The layout drawing’s plot schedule was software-read as 30 plots, with sizes ranging from 122.59 sq. m to 224.86 sq. m. The size bands read from the drawing are:
100–150 sq. yd (84–125 sq. m): 2
150–200 sq. yd (125–167 sq. m): 16
200–250 sq. yd (167–209 sq. m): 10
250–300 sq. yd (209–251 sq. m): 2
These are software-measured drawing-derived values, not RERA-filed saleable areas; verify any specific plot dimensions against the approved drawing and plot schedule.
5. Parking & vehicle circulation
The supplied records do not state a parking-space count, visitor or accessible parking provision, mechanical parking, EV charging, or plot-specific parking allocation. The layout approval identifies roads and road widths of 18 mts and above, but does not provide a detailed vehicle-circulation or driveway schedule in the supplied extraction. A road or parking mark on a drawing, if present, would not by itself establish an exclusive allocation to a purchaser.
6. Amenities, recreation & open spaces
The project record lists layout-level infrastructure and community/open-space items. The amenity register marks several items “YES,” but shows 0% progress for the listed items; this does not independently verify completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | Layout roads; approval document refers to road widths 18 mts and above. | Listed “YES”; 0% recorded. Completion not independently verified. | |
| Park / green open space | 741.36 sq. m; drawing prints 7.56%. | Park development listed in approval conditions; completion not verified. | |
| Social infrastructure | 251.81 sq. m; drawing prints 2.57%. | Listed in the approval document; delivery/status not verified. | |
| Water supply | Internal water-supply pipelines and overhead tank are listed in the approval document. | Listed “YES”; 0% recorded. Completion not independently verified. | |
| Sewerage / sewage treatment | Underground drainage lines and common septic tank/STP are listed. | Listed “YES”; 0% recorded. Completion not independently verified. | |
| Storm-water drainage | Storm-water drains are listed. | Listed “YES”; 0% recorded. Completion not independently verified. | |
| Rainwater harvesting | Rainwater-harvesting pits are listed. | Listed “YES”; 0% recorded. Completion not independently verified. | |
| Avenue plantation | Listed as a layout development item. | Completion not verified. | |
| Utility / transformer | Transformer and utility provision are listed; the layout area statement records 0 sq. m for amenities and a utility line with no separate stated area in the supplied extraction. | Electrical meter room/sub-station/receiving station listed “YES”; 0% recorded. Completion not independently verified. |
No clubhouse, indoor recreation facility or sports facility is established in the supplied project record.
7. Utilities, building services & safety
The approval document lists internal water-supply pipelines, an overhead tank, underground drainage lines, a common septic tank/STP, storm-water drains and rainwater-harvesting pits. It also lists a transformer. These are proposed or approval-recorded layout works; capacities, water source, treatment specifications, power-backup arrangements and completion evidence are not supplied.
The amenity register includes solid-waste management, energy management, fire protection and fire-safety requirements, street lighting and sewage/sullage treatment and disposal, but the supplied records do not provide system specifications, capacities or verified completion status. As a plotted layout, apartment-building services such as lifts and escape stairs are not established or applicable from the available evidence.
8. Location, access & connectivity
The official project filing identifies the location as BORGAON (P)SHIVAR MUGPAL MANDAL,NUDA, MUPKAL (NEW) mandal, Nizamabad district, PIN 503230. The RERA record identifies the revenue village as Nuda, while the draft layout approval describes the village as Borgoan; the supplied records do not resolve that identification.
The site boundary entry identifies a road on the east and other land on the west, north and south. The location data supplies one connectivity reference: Financial District (Nanakramguda), 1.2 km. The supplied data does not describe the approach route or public-transport services.
9. Developer & development status
The TG-RERA registration certificate names the promoter as Gangareddy Govind Gari; the Form-B affidavit is signed by GOVIND GARI GANGAREDDY as promoter. The promoter’s legal entity type, corporate registration number and registered office are not established in the supplied material.
The promoter declared that the project would be completed by 27/01/2026 and that project funds would be handled through the separate-account arrangement described in the affidavit. The supplied evidence does not include a current construction-progress report, verified physical inspection, or subsequent certificate confirming completion.
10. Approvals, official records & documents
TG-RERA registration certificate: Form C; registration P03100005954, granted under section 5; certificate states validity from 01/04/2023 to 27/01/2026.
Layout approval document: NUDA draft technical layout pattern approval; Draft - TLP.NO.3146/Borgoan P/2020/0064 UDA, dated 28 January, 2021; reference Lr.Roc.No.3146/Borgoan P/2020/0064.
Development-charges proceedings: ROC.No 1234/2016/P, dated 26-10-2018, listed in the layout approval document.
Promoter declaration: Form-B affidavit-cum-declaration by GOVIND GARI GANGAREDDY, including the declared title and encumbrance statements and completion undertaking.
Other approvals / certificates: No separate current completion or occupancy certificate is supplied. The approval document is described as a draft layout pattern approval; the supplied record does not include a later final layout-release certificate.
Frequently asked questions
Is SRI MANIKANTA TOWN SHIP registered with Telangana RERA?
Yes. SRI MANIKANTA TOWN SHIP is registered with the Telangana Real Estate Regulatory Authority as P03100005954; the registration status is New Project.
Who is the developer of SRI MANIKANTA TOWN SHIP?
The promoter named in the RERA registration is GANGAREDDY.
Where is SRI MANIKANTA TOWN SHIP located?
SRI MANIKANTA TOWN SHIP is in BORGAON (P)SHIVAR MUGPAL MANDAL ,NUDA, MUPKAL (NEW), Nizamabad, Telangana (503230).
When will SRI MANIKANTA TOWN SHIP be completed?
The promoter's proposed date of completion filed with RERA is 27/01/2026. This is the promoter's declaration, not a guarantee.
More projects in Mupkal