Chaitanya Emerald
SRI CHAITANYARAM BUILDERS · Medchal-Malkajgiri · RERA P02200005187
CHAITANYA EMERALD is a residential apartment project in Hyder Nagar, Kukatpally mandal, Medchal-Malkajgiri district, developed by registered promoter SRI CHAITANYARAM BUILDERS. It is on 376.04 sq. m and comprises one building with 1 Stilt + 5 upper floors and 10 apartments: five 2BHK and five 3BHK. The TG-RERA registration number is P02200005187, and the proposed completion date is 27/06/2025.
More from Sri Chaitanyaram Builders · 16 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name | CHAITANYA EMERALD RERA record |
| Project type / phase | Residential apartment project; the registration identifies one registered project, but does not state a phase number or a separately named phase. RERA record |
| TG-RERA registration | P02200005187, issued 13/10/2022; certificate states validity from 13/10/2022 to 27/06/2025, subject to extension by the Authority. The supplied certificate records no extension; current registration status is not established by this certificate. RERA record |
| Registered promoter | SRI CHAITANYARAM BUILDERS RERA record Corporate record |
| RERA status | The filing identifies the project as “New Project.” Registration validity and the promoter’s proposed completion date are separate matters; the certificate’s stated validity ended 27/06/2025. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Hydernagar / Hyder Nagar RERA record |
| Revenue village | Hyder Nagar; the filed building-permit extraction identifies HYDERNAGAR. RERA record RERA filing |
| Mandal / district / PIN | Kukatpally / Medchal-Malkajgiri / 500072 RERA record |
| Project survey numbers | 148 TO 155, M.C.K. BLOCK NO. 2 in the project land filing; the RERA certificate lists 148 TO 155. RERA filing Land records |
| Plot identity | Plots 685 & 686 (EASTERN PART) RERA filing |
| Registered site extent | 376.04 sq. m; the filed building permit records plot area and net plot area as 376.04 sq. m, with road-affected and nala-affected area each 0.0 sq. m. RERA filing |
| Boundaries (RERA filing) | East: Plot Nos 684 and 685; West: Western Part of Plot No 686; North: Plots No 642 and 643 and 644; South: 30 Feet Wide Road. RERA filing |
| Parcel reference | A cadastral record is available for survey 148, described as a whole-survey record; this is not a parcel-level verification of the full project land description. Cadastral map |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) Approvals record |
| Principal building permit | 2045/GHMC/KPL/2022-BP, approved 27 June, 2022; file no. 005960/GHMC/2990/KPL2/2022-BP. Approvals record |
| Approved built-up area | 1,100.40 sq. m RERA filing |
| Building count | One building is recorded in the project filing. RERA filing |
| Sanctioned configuration | 1 Stilt + 5 upper floors; permit extraction also records building height 14.99 (unit not specified in the extracted field). |
| Parking provision recorded in permit | Total Parking Area 220.1; the extraction does not state the number of vehicle spaces. |
| Units | The project filing records 10 units across 2BHK and 3BHK configurations; the project information states one building unit. RERA unit table RERA unit details RERA filing |
Offering and status
| Item | Project record |
|---|---|
| Configurations | 2BHK and 3BHK apartments RERA unit table RERA unit details |
| RERA-filed saleable areas | 2BHK: 113.8 sq. m; 3BHK: 148.64 sq. m RERA unit table RERA unit details |
| Booked / available | Portal figures show 0 booked and 5 available for each configuration (10 available in total). These are indicative portal figures; no as-of date is supplied. RERA unit table RERA unit details |
| Proposed completion | 27/06/2025 in the project header and 27th June 2025 in the promoter’s Form B declaration. RERA record |
| Construction stage | No independently verified construction-stage evidence or site-progress measurement is supplied. The RERA amenities record shows 0% for its listed progress fields. RERA amenities |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project records. The GHMC permit makes an occupancy certificate compulsory before occupation. Document index |
2. The project story
CHAITANYA EMERALD is registered as a residential apartment project on the filed site in Hyder Nagar, Kukatpally mandal, Medchal-Malkajgiri district. The site is identified by the project filing as survey 148 TO 155, M.C.K. BLOCK NO. 2, on 376.04 sq. m, and by plots 685 & 686 (EASTERN PART). RERA record Land records
The GHMC permit describes one residential building with 1 Stilt + 5 upper floors. The RERA filing offers five 2BHK and five 3BHK apartments. The promoter’s filed Form B undertakes completion by 27 June 2025; the supplied evidence does not establish current physical progress or that the project has been completed. RERA unit details
The permit requires an occupancy certificate before occupation. No occupancy certificate is present in the supplied records, so completion and occupancy-certified status are not established here. Document index
3. Master plan, architecture & building design
The GHMC building permit approves a residential building on a 376.04 sq. m plot, with 1,100.40 sq. m recorded as residential built-up area and 220.1 recorded as stilt area. The permit specifies 1 Stilt + 5 upper floors and a building height of 14.99 (the extracted field does not state a unit). These are permit-recorded figures; the supplied material does not separately identify FSI-counted area, carpet area of the building, building footprint, or floor-by-floor apartment arrangement.
The permit also records a Total Parking Area of 220.1 and five rainwater-harvesting pits. The RERA building-count field records one building. The supplied plan information does not establish the number of flats per floor, lifts or stairs, internal circulation details, or measured open-space area. RERA filing
The RERA filing identifies the project land as 148 TO 155, M.C.K. BLOCK NO. 2, at plots 685 & 686 (EASTERN PART). The GHMC permit records 0.0 sq. m road-affected area and 0.0 sq. m nala-affected area. RERA filing
4. Homes, configurations & floor plans
The TG-RERA filing records 10 apartments, comprising five 2BHK units and five 3BHK units. Portal booking and availability figures are indicative and carry no supplied as-of date. RERA saleable area is distinct from carpet area: saleable area may include the home’s proportionate share of common areas, while carpet area is the internal usable area. No software-measured carpet areas are available from the supplied floor-plan records. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 113.8 sq. m | Not measured in supplied drawing data | Not supplied |
| 3BHK | 5 | 0 | 5 | 148.64 sq. m | Not measured in supplied drawing data | Not supplied |
The floor-plan record states that two drawings are present, but neither has measured flats; no room dimensions or typical-floor arrangement can therefore be reported from the supplied drawing measurements. Floor plans
5. Parking & vehicle circulation
The GHMC permit records Total Parking Area 220.1 and states that the approved cellar and stilt spaces are to be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction describes the building as 1 Stilt + 5 upper floors but does not provide a count of car or two-wheeler spaces, visitor or accessible spaces, or parking allocation by apartment.
A promoter-listed amenity source mentions reserved parking, visitor parking and covered car parking; these are vendor-listed claims, not a count or a legally documented allocation in the supplied RERA material. No parking-space ownership or unit-specific allocation is established here. Promoter website
6. Amenities, recreation & open spaces
| Description / size | Permit requires the tot-lot to be fenced and maintained as greenery before an occupancy certificate; no area or capacity is supplied. |
|---|---|
| Declared progress / verified status | Permit condition; delivery not independently verified. |
| Description / size | Five rainwater-harvesting pits recorded in the permit; a percolation pit is required. |
|---|---|
| Declared progress / verified status | Permit-recorded provision; completion not verified. |
| Description / size | Space for a transformer is required on site. |
|---|---|
| Declared progress / verified status | Permit condition; completion not verified. |
| Description / size | Required within the premises by the permit. |
|---|---|
| Declared progress / verified status | Permit condition; completion not verified. |
| Description / size | Listed in vendor-provided amenity material; no sizes or capacities supplied. |
|---|---|
| Evidence source | Promoter website |
| Declared progress / verified status | Vendor-listed; not established as sanctioned or delivered. |
The RERA amenities record lists items including internal roads and footpaths, water supply, sewerage, storm-water drains, community buildings, sewage treatment/disposal, solid-waste management, energy management, fire protection, electrical meter room/sub-station and recreational open space. Its progress fields show 0%; the record does not provide facility sizes or independent completion verification. RERA amenities
7. Utilities, building services & safety
- Water: Water supply appears in the RERA amenities record. The GHMC permit states that public water connections will be provided only on production of an occupancy certificate. No source, storage capacity or treatment details are supplied. RERA amenities
- Sewerage and drainage: Sewerage, sewage/sullage treatment and storm-water drains appear in the RERA amenities record; progress is recorded as 0%. No STP capacity or reuse arrangements are supplied. RERA amenities
- Rainwater: The permit records five rainwater-harvesting pits and requires a rainwater-harvesting structure (percolation pit). Completion is not verified.
- Electrical: The permit requires space for a transformer. An electrical meter room/sub-station/receiving station is listed in the RERA amenities record. Supply capacity and backup arrangements are not stated in the project filing. RERA amenities
- Lifts and building services: The permit requires services including plumbing, fire safety, lifts and electrical installations to be executed under qualified technical supervision. Lift count and capacity are not supplied.
- Fire and life safety: The permit assigns responsibility for structural safety and means-of-escape safety and requires fire-fighting installations as stipulated in the National Building Code of India, 2016. It states that an Occupancy FIRE NOC is to be obtained before the occupancy certificate. No issued fire NOC or occupancy certificate is included in the supplied records.
- Waste: The permit requires a garbage house within the premises; solid-waste management and disposal also appear in the RERA amenities record, with 0% shown in its progress field. RERA amenities
- Safety conditions: The permit requires tree planting along the periphery and in front of the premises, maintenance of a greenery strip, and specified clearances from high- and low-tension electrical lines. These are permit conditions, not evidence of completed works.
8. Location, access & connectivity
The project’s official location is Hyder Nagar (also rendered as Hydernagar), Kukatpally mandal, Medchal-Malkajgiri district, Telangana, PIN 500072. The filed building permit identifies the site as HYDER NAGAR (Circle 14A), and the RERA certificate identifies Hyder Nagar, Kukatpally. RERA record
The project location record provides a cadastral parcel centroid at 17.48831674126732, 78.37630469650277 and lists HITEC City at 5.0 km. This is the supplied recorded distance; no travel time or route is provided. Location record Cadastral map
The permit records a 30 Feet Wide Road on the southern boundary and also refers to an 18 mt. road width in its conditions. RERA filing
9. Developer & development status
The registered promoter is SRI CHAITANYARAM BUILDERS, identified in the project record as a partnership. Its supplied GSTIN is 36ADHFS3993A1ZY. The RERA filing lists the promoter address as Plot No. 84, Venkataramana Colony, Gopal Nagar Co-Operative House Building Society Limited, Hydernagar, Kukatpally, Medchal-Malkajgiri, Telangana, PIN 500072. Corporate record Parties record RERA filing RERA filing
The RERA certificate shows a separate promoter-office address as Village: Mandal: District: Ranga Reddy, PIN 500049. No official contact number, email address or website is supplied in the project evidence.
The promoter’s Form B, signed by its stated authorized signatory, declares legal title and that the land is free from encumbrances, and undertakes completion by 27 June 2025. These are promoter declarations. The supplied records do not establish current construction progress, completion, or an occupancy certificate.
10. Approvals, official records & documents
| Identifier / date | P02200005187; issued 13/10/2022 |
|---|---|
| What the supplied record establishes | Form C registration for CHAITANYA EMERALD, with stated validity to 27/06/2025 unless extended. No extension is recorded on the supplied certificate. |
| Identifier / date | 2045/GHMC/KPL/2022-BP; 27 June, 2022 |
|---|---|
| What the supplied record establishes | Conditional building permission for a residential building of 1 Stilt + 5 upper floors on a 376.04 sq. m plot. The permit requires an occupancy certificate before occupation. |
| Identifier / date | 005960/GHMC/2990/KPL2/2022-BP |
|---|---|
| What the supplied record establishes | File number appearing in the filed permit extraction. |
| Identifier / date | August 2022 (day not specified) |
|---|---|
| What the supplied record establishes | Promoter declaration of title, no encumbrances and proposed completion by 27 June 2025. |
| Identifier / date | Document 255993 |
|---|---|
| What the supplied record establishes | RERA filing lists a request for a layout approval letter or stamped layout plan, or a declaration/equivalent document if not applicable; the supplied record is not extracted, so its contents cannot be confirmed. Document index |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No issued certificate is established by the documents provided. The GHMC permit requires an occupancy certificate before occupation. Document index |
The project evidence also identifies an encumbrance statement, title-report documents, a draft allotment letter and a partially filled agreement-for-sale form among the filed records; their detailed title and legal implications are addressed in the relevant report sections. Document index
1. Project at a glance
Project identity
Registered name: CHAITANYA EMERALD
Project type / phase: Residential apartment project; the registration identifies one registered project, but does not state a phase number or a separately named phase.
TG-RERA registration: P02200005187, issued 13/10/2022; certificate states validity from 13/10/2022 to 27/06/2025, subject to extension by the Authority. The supplied certificate records no extension; current registration status is not established by this certificate.
Registered promoter: SRI CHAITANYARAM BUILDERS
RERA status: The filing identifies the project as “New Project.” Registration validity and the promoter’s proposed completion date are separate matters; the certificate’s stated validity ended 27/06/2025.
Land and geographic identity
Locality: Hydernagar / Hyder Nagar
Revenue village: Hyder Nagar; the filed building-permit extraction identifies HYDERNAGAR.
Mandal / district / PIN: Kukatpally / Medchal-Malkajgiri / 500072
Project survey numbers: 148 TO 155, M.C.K. BLOCK NO. 2 in the project land filing; the RERA certificate lists 148 TO 155.
Plot identity: Plots 685 & 686 (EASTERN PART)
Registered site extent: 376.04 sq. m; the filed building permit records plot area and net plot area as 376.04 sq. m, with road-affected and nala-affected area each 0.0 sq. m.
Boundaries (RERA filing): East: Plot Nos 684 and 685; West: Western Part of Plot No 686; North: Plots No 642 and 643 and 644; South: 30 Feet Wide Road.
Parcel reference: A cadastral record is available for survey 148, described as a whole-survey record; this is not a parcel-level verification of the full project land description.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building permit: 2045/GHMC/KPL/2022-BP, approved 27 June, 2022; file no. 005960/GHMC/2990/KPL2/2022-BP.
Approved built-up area: 1,100.40 sq. m
Building count: One building is recorded in the project filing.
Sanctioned configuration: 1 Stilt + 5 upper floors; permit extraction also records building height 14.99 (unit not specified in the extracted field).
Parking provision recorded in permit: Total Parking Area 220.1; the extraction does not state the number of vehicle spaces.
Units: The project filing records 10 units across 2BHK and 3BHK configurations; the project information states one building unit.
Offering and status
Configurations: 2BHK and 3BHK apartments
RERA-filed saleable areas: 2BHK: 113.8 sq. m; 3BHK: 148.64 sq. m
Booked / available: Portal figures show 0 booked and 5 available for each configuration (10 available in total). These are indicative portal figures; no as-of date is supplied.
Proposed completion: 27/06/2025 in the project header and 27th June 2025 in the promoter’s Form B declaration.
Construction stage: No independently verified construction-stage evidence or site-progress measurement is supplied. The RERA amenities record shows 0% for its listed progress fields.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project records. The GHMC permit makes an occupancy certificate compulsory before occupation.
2. The project story
CHAITANYA EMERALD is registered as a residential apartment project on the filed site in Hyder Nagar, Kukatpally mandal, Medchal-Malkajgiri district. The site is identified by the project filing as survey 148 TO 155, M.C.K. BLOCK NO. 2, on 376.04 sq. m, and by plots 685 & 686 (EASTERN PART).
The GHMC permit describes one residential building with 1 Stilt + 5 upper floors. The RERA filing offers five 2BHK and five 3BHK apartments. The promoter’s filed Form B undertakes completion by 27 June 2025; the supplied evidence does not establish current physical progress or that the project has been completed.
The permit requires an occupancy certificate before occupation. No occupancy certificate is present in the supplied records, so completion and occupancy-certified status are not established here.
3. Master plan, architecture & building design
The GHMC building permit approves a residential building on a 376.04 sq. m plot, with 1,100.40 sq. m recorded as residential built-up area and 220.1 recorded as stilt area. The permit specifies 1 Stilt + 5 upper floors and a building height of 14.99 (the extracted field does not state a unit). These are permit-recorded figures; the supplied material does not separately identify FSI-counted area, carpet area of the building, building footprint, or floor-by-floor apartment arrangement.
The permit also records a Total Parking Area of 220.1 and five rainwater-harvesting pits. The RERA building-count field records one building. The supplied plan information does not establish the number of flats per floor, lifts or stairs, internal circulation details, or measured open-space area.
The RERA filing identifies the project land as 148 TO 155, M.C.K. BLOCK NO. 2, at plots 685 & 686 (EASTERN PART). The GHMC permit records 0.0 sq. m road-affected area and 0.0 sq. m nala-affected area.
4. Homes, configurations & floor plans
The TG-RERA filing records 10 apartments, comprising five 2BHK units and five 3BHK units. Portal booking and availability figures are indicative and carry no supplied as-of date. RERA saleable area is distinct from carpet area: saleable area may include the home’s proportionate share of common areas, while carpet area is the internal usable area. No software-measured carpet areas are available from the supplied floor-plan records.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 113.8 sq. m | Not measured in supplied drawing data | Not supplied |
| 3BHK | 5 | 0 | 5 | 148.64 sq. m | Not measured in supplied drawing data | Not supplied |
The floor-plan record states that two drawings are present, but neither has measured flats; no room dimensions or typical-floor arrangement can therefore be reported from the supplied drawing measurements.
5. Parking & vehicle circulation
The GHMC permit records Total Parking Area 220.1 and states that the approved cellar and stilt spaces are to be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction describes the building as 1 Stilt + 5 upper floors but does not provide a count of car or two-wheeler spaces, visitor or accessible spaces, or parking allocation by apartment.
A promoter-listed amenity source mentions reserved parking, visitor parking and covered car parking; these are vendor-listed claims, not a count or a legally documented allocation in the supplied RERA material. No parking-space ownership or unit-specific allocation is established here.
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Permit requires the tot-lot to be fenced and maintained as greenery before an occupancy certificate; no area or capacity is supplied. | Permit condition; delivery not independently verified. | |
| Rainwater harvesting | Five rainwater-harvesting pits recorded in the permit; a percolation pit is required. | Permit-recorded provision; completion not verified. | |
| Transformer space | Space for a transformer is required on site. | Permit condition; completion not verified. | |
| Garbage house | Required within the premises by the permit. | Permit condition; completion not verified. | |
| Children’s play area, gym, clubhouse, swimming pool, jogging track, common garden and Wi-Fi | Listed in vendor-provided amenity material; no sizes or capacities supplied. | Vendor-listed; not established as sanctioned or delivered. |
The RERA amenities record lists items including internal roads and footpaths, water supply, sewerage, storm-water drains, community buildings, sewage treatment/disposal, solid-waste management, energy management, fire protection, electrical meter room/sub-station and recreational open space. Its progress fields show 0%; the record does not provide facility sizes or independent completion verification.
7. Utilities, building services & safety
- Water: Water supply appears in the RERA amenities record. The GHMC permit states that public water connections will be provided only on production of an occupancy certificate. No source, storage capacity or treatment details are supplied.
- Sewerage and drainage: Sewerage, sewage/sullage treatment and storm-water drains appear in the RERA amenities record; progress is recorded as 0%. No STP capacity or reuse arrangements are supplied.
- Rainwater: The permit records five rainwater-harvesting pits and requires a rainwater-harvesting structure (percolation pit). Completion is not verified.
- Electrical: The permit requires space for a transformer. An electrical meter room/sub-station/receiving station is listed in the RERA amenities record. Supply capacity and backup arrangements are not stated in the project filing.
- Lifts and building services: The permit requires services including plumbing, fire safety, lifts and electrical installations to be executed under qualified technical supervision. Lift count and capacity are not supplied.
- Fire and life safety: The permit assigns responsibility for structural safety and means-of-escape safety and requires fire-fighting installations as stipulated in the National Building Code of India, 2016. It states that an Occupancy FIRE NOC is to be obtained before the occupancy certificate. No issued fire NOC or occupancy certificate is included in the supplied records.
- Waste: The permit requires a garbage house within the premises; solid-waste management and disposal also appear in the RERA amenities record, with 0% shown in its progress field.
- Safety conditions: The permit requires tree planting along the periphery and in front of the premises, maintenance of a greenery strip, and specified clearances from high- and low-tension electrical lines. These are permit conditions, not evidence of completed works.
8. Location, access & connectivity
The project’s official location is Hyder Nagar (also rendered as Hydernagar), Kukatpally mandal, Medchal-Malkajgiri district, Telangana, PIN 500072. The filed building permit identifies the site as HYDER NAGAR (Circle 14A), and the RERA certificate identifies Hyder Nagar, Kukatpally.
The project location record provides a cadastral parcel centroid at 17.48831674126732, 78.37630469650277 and lists HITEC City at 5.0 km. This is the supplied recorded distance; no travel time or route is provided.
The permit records a 30 Feet Wide Road on the southern boundary and also refers to an 18 mt. road width in its conditions.
9. Developer & development status
The registered promoter is SRI CHAITANYARAM BUILDERS, identified in the project record as a partnership. Its supplied GSTIN is 36ADHFS3993A1ZY. The RERA filing lists the promoter address as Plot No. 84, Venkataramana Colony, Gopal Nagar Co-Operative House Building Society Limited, Hydernagar, Kukatpally, Medchal-Malkajgiri, Telangana, PIN 500072.
The RERA certificate shows a separate promoter-office address as Village: Mandal: District: Ranga Reddy, PIN 500049. No official contact number, email address or website is supplied in the project evidence.
The promoter’s Form B, signed by its stated authorized signatory, declares legal title and that the land is free from encumbrances, and undertakes completion by 27 June 2025. These are promoter declarations. The supplied records do not establish current construction progress, completion, or an occupancy certificate.
10. Approvals, official records & documents
| Identifier / date | P02200005187; issued 13/10/2022 |
|---|---|
| What the supplied record establishes | Form C registration for CHAITANYA EMERALD, with stated validity to 27/06/2025 unless extended. No extension is recorded on the supplied certificate. |
| Identifier / date | 2045/GHMC/KPL/2022-BP; 27 June, 2022 |
|---|---|
| What the supplied record establishes | Conditional building permission for a residential building of 1 Stilt + 5 upper floors on a 376.04 sq. m plot. The permit requires an occupancy certificate before occupation. |
| Identifier / date | 005960/GHMC/2990/KPL2/2022-BP |
|---|---|
| What the supplied record establishes | File number appearing in the filed permit extraction. |
| Identifier / date | August 2022 (day not specified) |
|---|---|
| What the supplied record establishes | Promoter declaration of title, no encumbrances and proposed completion by 27 June 2025. |
| Identifier / date | Document 255993 |
|---|---|
| What the supplied record establishes | RERA filing lists a request for a layout approval letter or stamped layout plan, or a declaration/equivalent document if not applicable; the supplied record is not extracted, so its contents cannot be confirmed. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No issued certificate is established by the documents provided. The GHMC permit requires an occupancy certificate before occupation. |
The project evidence also identifies an encumbrance statement, title-report documents, a draft allotment letter and a partially filled agreement-for-sale form among the filed records; their detailed title and legal implications are addressed in the relevant report sections.
Frequently asked questions
Is CHAITANYA EMERALD registered with Telangana RERA?
Yes. CHAITANYA EMERALD is registered with the Telangana Real Estate Regulatory Authority as P02200005187; the registration status is New Project.
Who is the developer of CHAITANYA EMERALD?
The promoter named in the RERA registration is SRI CHAITANYARAM BUILDERS.
Where is CHAITANYA EMERALD located?
CHAITANYA EMERALD is in Hydernagar, Hyder Nagar, Kukatpally, Medchal-Malkajgiri, Telangana (500072).
When will CHAITANYA EMERALD be completed?
The promoter's proposed date of completion filed with RERA is 27/06/2025. This is the promoter's declaration, not a guarantee.
More projects in Hyder Nagar