S.V.SAMRUDDHI - B
SAMRUDDHI INFRA · Rangareddy · RERA P02400000099
S.V.SAMRUDDHI - B is a residential apartment project in Saroornagar, Saroornagar Mandal, Ranga Reddy District, developed by the registered promoter SAMRUDDHI INFRA. It is on a land area of 748.32 sq. m and comprises one building, Building - A, approved as Stilt + 5, with 15 3BHK homes. The project is registered under TG-RERA number P02400000099, with a proposed completion date of 30/11/2021.
More from Samruddhi Infra · 2 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | S.V.SAMRUDDHI - B RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | Phase designation is not separately stated; registration is for S.V.SAMRUDDHI - B RERA record |
| TG-RERA registration number | P02400000099 RERA record |
| Registration validity | 21/12/2018 to 30/11/2021; certificate records no extension |
| Registered promoter | SAMRUDDHI INFRA RERA record |
| RERA status | The supplied certificate records the registration period above. Current registration status is not established by the supplied record. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Saroornagar; locality is also recorded as SAROORNAGAR RERA record RERA filing |
| Mandal | Saroornagar RERA record RERA filing |
| District | Ranga Reddy RERA record RERA filing |
| PIN | 500035 RERA record RERA filing |
| Project survey number(s) | Survey No. 33; no project subdivision is stated in the supplied RERA record RERA filing Land records |
| Site description | 1-128 (OLD), 1-146 (NEW) SCHEDULE-B RERA filing |
| Registered site area | 748.32 sq. m RERA filing |
| Total / net area and road-affected area | Filed and sanctioned records state total/site area 748.32 sq. m, net area 748.32 sq. m, and road-affected area 0. RERA filing |
| Boundaries as filed | East: REMAINIG PORTION OF H NO 1-128; West: EXISTING HOUSE; North: NEIGHBOURS HOUSE; South: 30 FT WIDE ROAD RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) Approvals record |
| Principal building approval | Building Permit Order 2/C5/14736/2018, approved 11 September, 2018; file number 2/C5/11738/2018 Approvals record |
| Approved building | Building - A, residential, Stilt + 5 |
| Approved built-up area | RERA filing records 1816.89 sq. m; the GHMC permit extraction separately lists residential upper floors as 1,816.90 and stilt as 349.13. RERA filing |
| Building / block count | 1 building/unit in the RERA project record RERA filing RERA unit table |
| Approved versus RERA-declared homes | GHMC permit extraction does not state a unit count. RERA fields record 1 total building unit and 1 proposed building unit; the unit schedule lists 15 homes. RERA filing RERA unit table |
| Parking levels | GHMC permit describes cellar area as 0.00 m² and requires approved stilt parking to be used for vehicle parking. The supplied record does not give a parking-space count. |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configuration | 3BHK, 15 units RERA unit table |
| RERA-filed saleable area | 133.3 sq. m RERA unit table |
| Portal booking snapshot | 0 booked; 15 available as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative. RERA unit table |
| Construction stage | No independently verified site-progress record is supplied. The RERA amenities schedule records 0% for its listed progress items; that is not an independent site inspection. RERA amenities |
| Completion date | Promoter-declared proposed completion: 30/11/2021 RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. GHMC’s permit requires an Occupancy Certificate before occupation. Document index |
2. The project story
S.V.SAMRUDDHI - B is a registered residential apartment development on the filed 748.32 sq. m site in Survey No. 33, Saroornagar. The RERA record identifies one building, while the GHMC building permit identifies Building - A as a Stilt + 5 residential building. The registered unit schedule lists 15 3BHK apartments. RERA record RERA filing RERA unit table
The promoter’s proposed completion date in the RERA record is 30/11/2021. The supplied evidence does not establish the actual construction stage or independently confirm completion. Nor does it include an occupancy/completion certificate; the permit states that an Occupancy Certificate is required before the building is occupied. RERA record RERA amenities Document index
3. Master plan, architecture & building design
The GHMC building permit records Building - A, residential, Stilt + 5, on a site area of 748.32 m² and a net area of 748.32 m². It lists the residential upper floors as 1,816.90 and the stilt as 349.13; the project RERA fields record approved built-up area as 1816.89 sq. m. The permit extraction also states a building height of 15 m. RERA filing
The available drawing record is identified as a building-plan/layout-plan document, but it is not extracted here into reliable floor-by-floor details. The evidence supplied therefore does not establish the building footprint, number of flats per floor, lift or stair arrangement, entrances, internal circulation, or landscaped/open-space dimensions. Document index
The permit lists a 0.00 m² cellar and requires the approved stilt/cellar parking areas to remain for vehicle parking. The RERA-filed area figures above are not identified as carpet area; the separately measured drawing carpet figures are addressed below. RERA unit table Floor plans
4. Homes, configurations & floor plans
The TG-RERA unit schedule lists 15 3BHK homes, each with a filed saleable area of 133.3 sq. m. Its latest supplied portal snapshot shows 0 booked and 15 available, but no snapshot date is provided. RERA unit table
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 15 | 0 | 15 | 133.3 sq. m | 76.1–97.7 sq. m; median 92.6 sq. m | 31% |
Carpet measurements are software-measured from the supplied floor-plan drawing geometry, are marked as needing review, and are not RERA-filed areas. The RERA saleable area is a separate filed figure; the supplied measurement notes explain that saleable area includes the home’s share of common areas, so it should not be treated as carpet area. Floor plans RERA unit details
The measured typical-floor 3BHK example shows living/dining, kitchen, three bedrooms, toilets and balconies. For the measured example, the listed dimensions include living/dining 5.38 × 6.31 m, kitchen 2.00 × 4.15 m, and bedrooms 3.35 × 3.36 m, 3.09 × 3.36 m and 3.35 × 3.75 m. These are drawing-derived measurements, not RERA area disclosures. RERA unit details
5. Parking & vehicle circulation
The GHMC permit describes a Stilt + 5 building, lists cellar area as 0.00 m², and requires the approved stilt/cellar parking areas to be used exclusively for vehicle parking. It does not provide a count of car or two-wheeler spaces in the supplied extraction.
The RERA unit schedule marks the 3BHK units as mortgaged, but the supplied record does not provide a unit-wise parking allocation or establish exclusive parking rights. The number of resident, visitor or accessible spaces, and the arrangements for ramps, vehicle entry/exit, internal driveways, pedestrian separation or EV charging, are not established by the supplied evidence. RERA unit table
6. Amenities, recreation & open spaces
The RERA amenities schedule lists the following facilities and services. Its progress entries are recorded as 0% for all listed items; water supply, sewerage and rainwater harvesting are marked “YES” in the schedule. These are RERA-recorded declarations, not independent confirmation of installation or operation. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip / Tot Lot / Park | GHMC permit also requires a tot-lot to be fenced and maintained as greenery; no area is stated. | RERA amenities | Amenities schedule: 0%; no independent completion verification supplied. |
| Community Buildings | Listed; no size or further description supplied. | RERA amenities | 0%; no independent completion verification supplied. |
| Internal Roads & Footpaths | Listed; no dimensions supplied. | RERA amenities | 0%; no independent completion verification supplied. |
| Street Lighting | Listed; no further detail supplied. | RERA amenities | 0%; no independent completion verification supplied. |
No clubhouse, indoor recreation or sports facility is identified in the supplied RERA amenities schedule. RERA amenities
7. Utilities, building services & safety
The RERA amenities schedule marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP) and Water Conservation, Rain water Harvesting as “YES”; it does not specify water source, storage or treatment capacity, sewage-treatment capacity, reuse arrangements, or drainage design. The schedule records 0% progress for these listed items. RERA amenities
GHMC’s permit requires a rainwater-harvesting structure (percolation pit), space for a transformer, a garbage house, and execution of sanitation, plumbing, fire-safety, lift and electrical services under qualified technical supervision. It does not establish from the supplied documents that these works are complete or provide equipment capacities or specifications.
The permit also states that structural safety and fire-safety requirements are the responsibility of the owner, builder/developer, architect and site engineer, and that an Occupancy Certificate is compulsory before occupation. The supplied material does not document completed fire systems, escape-stair specifications, lifts, backup power, CCTV, access control or accessible circulation.
8. Location, access & connectivity
The registered location is Saroornagar, Saroornagar Mandal, Ranga Reddy District, Telangana, PIN 500035. The filed site boundaries identify a 30 FT WIDE ROAD to the south. The GHMC permit also refers to an 18 mt. road condition; no route or approach-road map is included in the supplied project record. RERA record RERA filing RERA filing
The supplied location data lists these nearby reference points and distances; it does not specify how the distances were measured or establish travel times: Location record
| Reference point | Listed distance |
|---|---|
| Andhra Bank Zonal Office | 0.3 km |
| Kamineni Hospital | 0.3 km |
| Rajeev Gandhi Nagar bus station | 0.4 km |
| Children Traffic Park | 0.5 km |
| Unnamed school | 0.5 km |
| Firstcry.com | 1.1 km |
| Victoria Memorial Metro | 1.2 km |
| iON Digital Zone, iDZ L.B. Nagar | 1.7 km |
| Sri Chaitanya Junior College | 1.9 km |
9. Developer & development status
The registered promoter is SAMRUDDHI INFRA, identified in the RERA record as a Partnership. The named partner is GARLAPATI SRINIVASULU and the authorized signatory is MANCHANA KRISHNAIAH. The supplied record does not provide a verified corporate identifier or a separate registered-office address beyond the promoter address recorded in the project filing. RERA record RERA filing Corporate record Parties record
The RERA filing gives 30/11/2021 as the proposed completion date. The supplied evidence contains no independently verified construction update and no occupancy/completion certificate; the building’s current physical completion and occupation status therefore remain unestablished in this Overview. RERA record RERA amenities Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form “C” certificate for S.V.SAMRUDDHI - B, registration P02400000099, issued 21/12/2018, valid to 30/11/2021; no extension is recorded in the supplied certificate. |
| GHMC building permit | Building Permit Order 2/C5/14736/2018, file 2/C5/11738/2018, dated 11 September, 2018, for Building - A at Bapu Nagar, Survey No. 33. |
| Plan drawing | A building-plan/layout-plan document is listed as document 9787; detailed drawing-derived building features are not established in the supplied extraction. |
| Promoter declaration | Form B affidavit attributed to SAMRUDDHI INFRA; its signatory and date are illegible or incomplete in the supplied extraction, and it does not state the project registration number. |
| Occupancy / completion certificate | Not present among the supplied project documents. The GHMC permit requires an Occupancy Certificate before occupation. Document index |
The GHMC permit lists the related LRS number LRS/2071/ho/CR-EAST ZONE/2012. The supplied materials do not include a separate approved-layout lookup record.
1. Project at a glance
Project identity
Registered project name: S.V.SAMRUDDHI - B
Project type: Residential apartment project
Phase / registered portion: Phase designation is not separately stated; registration is for S.V.SAMRUDDHI - B
TG-RERA registration number: P02400000099
Registration validity: 21/12/2018 to 30/11/2021; certificate records no extension
Registered promoter: SAMRUDDHI INFRA
RERA status: The supplied certificate records the registration period above. Current registration status is not established by the supplied record.
Land and geographic identity
Locality / revenue village: Saroornagar; locality is also recorded as SAROORNAGAR
Mandal: Saroornagar
District: Ranga Reddy
PIN: 500035
Project survey number(s): Survey No. 33; no project subdivision is stated in the supplied RERA record
Site description: 1-128 (OLD), 1-146 (NEW) SCHEDULE-B
Registered site area: 748.32 sq. m
Total / net area and road-affected area: Filed and sanctioned records state total/site area 748.32 sq. m, net area 748.32 sq. m, and road-affected area 0.
Boundaries as filed: East: REMAINIG PORTION OF H NO 1-128; West: EXISTING HOUSE; North: NEIGHBOURS HOUSE; South: 30 FT WIDE ROAD
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: Building Permit Order 2/C5/14736/2018, approved 11 September, 2018; file number 2/C5/11738/2018
Approved building: Building - A, residential, Stilt + 5
Approved built-up area: RERA filing records 1816.89 sq. m; the GHMC permit extraction separately lists residential upper floors as 1,816.90 and stilt as 349.13.
Building / block count: 1 building/unit in the RERA project record
Approved versus RERA-declared homes: GHMC permit extraction does not state a unit count. RERA fields record 1 total building unit and 1 proposed building unit; the unit schedule lists 15 homes.
Parking levels: GHMC permit describes cellar area as 0.00 m² and requires approved stilt parking to be used for vehicle parking. The supplied record does not give a parking-space count.
Offering and status
RERA-filed configuration: 3BHK, 15 units
RERA-filed saleable area: 133.3 sq. m
Portal booking snapshot: 0 booked; 15 available as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative.
Construction stage: No independently verified site-progress record is supplied. The RERA amenities schedule records 0% for its listed progress items; that is not an independent site inspection.
Completion date: Promoter-declared proposed completion: 30/11/2021
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. GHMC’s permit requires an Occupancy Certificate before occupation.
2. The project story
S.V.SAMRUDDHI - B is a registered residential apartment development on the filed 748.32 sq. m site in Survey No. 33, Saroornagar. The RERA record identifies one building, while the GHMC building permit identifies Building - A as a Stilt + 5 residential building. The registered unit schedule lists 15 3BHK apartments.
The promoter’s proposed completion date in the RERA record is 30/11/2021. The supplied evidence does not establish the actual construction stage or independently confirm completion. Nor does it include an occupancy/completion certificate; the permit states that an Occupancy Certificate is required before the building is occupied.
3. Master plan, architecture & building design
The GHMC building permit records Building - A, residential, Stilt + 5, on a site area of 748.32 m² and a net area of 748.32 m². It lists the residential upper floors as 1,816.90 and the stilt as 349.13; the project RERA fields record approved built-up area as 1816.89 sq. m. The permit extraction also states a building height of 15 m.
The available drawing record is identified as a building-plan/layout-plan document, but it is not extracted here into reliable floor-by-floor details. The evidence supplied therefore does not establish the building footprint, number of flats per floor, lift or stair arrangement, entrances, internal circulation, or landscaped/open-space dimensions.
The permit lists a 0.00 m² cellar and requires the approved stilt/cellar parking areas to remain for vehicle parking. The RERA-filed area figures above are not identified as carpet area; the separately measured drawing carpet figures are addressed below.
4. Homes, configurations & floor plans
The TG-RERA unit schedule lists 15 3BHK homes, each with a filed saleable area of 133.3 sq. m. Its latest supplied portal snapshot shows 0 booked and 15 available, but no snapshot date is provided.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 15 | 0 | 15 | 133.3 sq. m | 76.1–97.7 sq. m; median 92.6 sq. m | 31% |
Carpet measurements are software-measured from the supplied floor-plan drawing geometry, are marked as needing review, and are not RERA-filed areas. The RERA saleable area is a separate filed figure; the supplied measurement notes explain that saleable area includes the home’s share of common areas, so it should not be treated as carpet area.
The measured typical-floor 3BHK example shows living/dining, kitchen, three bedrooms, toilets and balconies. For the measured example, the listed dimensions include living/dining 5.38 × 6.31 m, kitchen 2.00 × 4.15 m, and bedrooms 3.35 × 3.36 m, 3.09 × 3.36 m and 3.35 × 3.75 m. These are drawing-derived measurements, not RERA area disclosures.
5. Parking & vehicle circulation
The GHMC permit describes a Stilt + 5 building, lists cellar area as 0.00 m², and requires the approved stilt/cellar parking areas to be used exclusively for vehicle parking. It does not provide a count of car or two-wheeler spaces in the supplied extraction.
The RERA unit schedule marks the 3BHK units as mortgaged, but the supplied record does not provide a unit-wise parking allocation or establish exclusive parking rights. The number of resident, visitor or accessible spaces, and the arrangements for ramps, vehicle entry/exit, internal driveways, pedestrian separation or EV charging, are not established by the supplied evidence.
6. Amenities, recreation & open spaces
The RERA amenities schedule lists the following facilities and services. Its progress entries are recorded as 0% for all listed items; water supply, sewerage and rainwater harvesting are marked “YES” in the schedule. These are RERA-recorded declarations, not independent confirmation of installation or operation.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip / Tot Lot / Park | GHMC permit also requires a tot-lot to be fenced and maintained as greenery; no area is stated. | Amenities schedule: 0%; no independent completion verification supplied. | |
| Community Buildings | Listed; no size or further description supplied. | 0%; no independent completion verification supplied. | |
| Internal Roads & Footpaths | Listed; no dimensions supplied. | 0%; no independent completion verification supplied. | |
| Street Lighting | Listed; no further detail supplied. | 0%; no independent completion verification supplied. |
No clubhouse, indoor recreation or sports facility is identified in the supplied RERA amenities schedule.
7. Utilities, building services & safety
The RERA amenities schedule marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP) and Water Conservation, Rain water Harvesting as “YES”; it does not specify water source, storage or treatment capacity, sewage-treatment capacity, reuse arrangements, or drainage design. The schedule records 0% progress for these listed items.
GHMC’s permit requires a rainwater-harvesting structure (percolation pit), space for a transformer, a garbage house, and execution of sanitation, plumbing, fire-safety, lift and electrical services under qualified technical supervision. It does not establish from the supplied documents that these works are complete or provide equipment capacities or specifications.
The permit also states that structural safety and fire-safety requirements are the responsibility of the owner, builder/developer, architect and site engineer, and that an Occupancy Certificate is compulsory before occupation. The supplied material does not document completed fire systems, escape-stair specifications, lifts, backup power, CCTV, access control or accessible circulation.
8. Location, access & connectivity
The registered location is Saroornagar, Saroornagar Mandal, Ranga Reddy District, Telangana, PIN 500035. The filed site boundaries identify a 30 FT WIDE ROAD to the south. The GHMC permit also refers to an 18 mt. road condition; no route or approach-road map is included in the supplied project record.
The supplied location data lists these nearby reference points and distances; it does not specify how the distances were measured or establish travel times:
Andhra Bank Zonal Office: 0.3 km
Kamineni Hospital: 0.3 km
Rajeev Gandhi Nagar bus station: 0.4 km
Children Traffic Park: 0.5 km
Unnamed school: 0.5 km
Firstcry.com: 1.1 km
Victoria Memorial Metro: 1.2 km
iON Digital Zone, iDZ L.B. Nagar: 1.7 km
Sri Chaitanya Junior College: 1.9 km
9. Developer & development status
The registered promoter is SAMRUDDHI INFRA, identified in the RERA record as a Partnership. The named partner is GARLAPATI SRINIVASULU and the authorized signatory is MANCHANA KRISHNAIAH. The supplied record does not provide a verified corporate identifier or a separate registered-office address beyond the promoter address recorded in the project filing.
The RERA filing gives 30/11/2021 as the proposed completion date. The supplied evidence contains no independently verified construction update and no occupancy/completion certificate; the building’s current physical completion and occupation status therefore remain unestablished in this Overview.
10. Approvals, official records & documents
TG-RERA registration: Form “C” certificate for S.V.SAMRUDDHI - B, registration P02400000099, issued 21/12/2018, valid to 30/11/2021; no extension is recorded in the supplied certificate.
GHMC building permit: Building Permit Order 2/C5/14736/2018, file 2/C5/11738/2018, dated 11 September, 2018, for Building - A at Bapu Nagar, Survey No. 33.
Plan drawing: A building-plan/layout-plan document is listed as document 9787; detailed drawing-derived building features are not established in the supplied extraction.
Promoter declaration: Form B affidavit attributed to SAMRUDDHI INFRA; its signatory and date are illegible or incomplete in the supplied extraction, and it does not state the project registration number.
Occupancy / completion certificate: Not present among the supplied project documents. The GHMC permit requires an Occupancy Certificate before occupation.
The GHMC permit lists the related LRS number LRS/2071/ho/CR-EAST ZONE/2012. The supplied materials do not include a separate approved-layout lookup record.
Frequently asked questions
Is S.V.SAMRUDDHI - B registered with Telangana RERA?
Yes. S.V.SAMRUDDHI - B is registered with the Telangana Real Estate Regulatory Authority as P02400000099; the registration status is New Project.
Who is the developer of S.V.SAMRUDDHI - B?
The promoter named in the RERA registration is SAMRUDDHI INFRA.
Where is S.V.SAMRUDDHI - B located?
S.V.SAMRUDDHI - B is in SAROORNAGAR, Rangareddy, Telangana (500035).
When will S.V.SAMRUDDHI - B be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2021. This is the promoter's declaration, not a guarantee.