Akshaya Nivas
AKSHAYA HOMES · Rangareddy · RERA P02400011024
AKSHAYA NIVAS is a residential apartment project in Yella reddy Colony, Hayathnagar mandal, Ranga Reddy district. The registered promoter is AKSHAYA HOMES. The project covers 308.38 sq. m. and comprises one residential building with 1 Stilt + 5 Floors and 10 2BHK apartments, each with a RERA-filed saleable area of 49.7 sq. m. (535 sq. ft.). It is registered under TG-RERA number P02400011024, with a proposed completion date of 14/03/2029.
More from Akshaya Homes · 2 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | TG-RERA record |
|---|---|
| Registered project | AKSHAYA NIVAS |
| Project type | Residential apartment project |
| Phase / registered portion | No phase designation disclosed in the registration record; the registered site is identified by Survey No. 101 and the stated plot portions. |
| TG-RERA registration | P02400011024 |
| Registration validity | 14/11/2025 to 14/11/2028, unless extended by the Authority. This is the registration period, not a statement of construction completion or occupancy. |
| Registered promoter | AKSHAYA HOMES |
| RERA status in supplied record | Registered; certificate captured 10/09/2026. |
RERA record Approvals record
Land and geographic identity
| Item | Recorded identity |
|---|---|
| Locality | Yella reddy Colony; the GHMC permit identifies YELLAREDDY COLONY PHASE-2 and BAGH HAYATHNAGAR. |
| Revenue village | RERA certificate: Yella reddy Colony. GHMC permit and title documents: Bagh Hayathnagar. |
| Mandal / district / PIN | Hayathnagar / Ranga Reddy / 500073 |
| Survey number and plot portions | Survey No. 101; 68 NORTH PART, 69 SOUTH PART, 69 AND 70 PART. No survey subdivision is specified in the supplied record. |
| Site extent | 308.38 sq. m. total and net plot area in the GHMC permit; RERA land record also reports 308.38 sq. m. |
| Boundaries in RERA land record | North: Plot No. 70 Part; South: Plot No. 68 Southern Part; East: Plot Nos. 34, 35 and 36; West: 30 ft wide road. |
RERA record RERA filing Land records
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building permit | 1798/GHMC/SWBP/LBN2/2025, approved 14/11/2025; GHMC file no. 008825/GHMC/04091/SWBP/LBN2/2025. |
| Building count and configuration | One residential building: 1 Stilt + 5 Floors. |
| Building height | GHMC plan extraction records 17.95 m proposed height from ground level and 15 m excluding stilt. |
| Approved built-up area | 854.55 sq. m. total proposed BUA excluding parking; 1,025.46 sq. m. total proposed BUA including parking. These are distinct plan-record figures. |
| Parking shown in approval extraction | Five car-parking spaces; 170.91 sq. m. parking area, including a stilt parking floor. |
| Units | 10 dwelling units in the GHMC permit and 10 units in the TG-RERA filing. |
Approvals record
Offering and status
| Item | Record |
|---|---|
| Unit type | 2BHK apartments |
| RERA-filed saleable area | 49.7 sq. m. per unit (535 sq. ft. in the normalized unit record); 10 units. |
| Booked / available | 0 booked and 10 available in the TG-RERA portal snapshot supplied; no snapshot as-of date is provided, so counts are indicative. |
| Construction stage | Current construction progress is not established by the supplied evidence. The project is described as new; the GHMC permit sets construction commencement and completion deadlines. |
| Completion dates | GHMC permit: construction to be completed before 14/11/2028. Form B completion undertaking: 14/11/2028. The project header separately records a proposed completion date of 14/03/2029; the supplied record does not explain that date. |
| Occupancy certificate | No occupancy certificate is supplied. GHMC requires an occupancy certificate before occupation; the record does not establish that one has been issued for the building. |
RERA unit table RERA unit details RERA record
2. The project story
AKSHAYA NIVAS is a 10-apartment residential project registered with TG-RERA on Survey No. 101 in the Yella reddy Colony / Bagh Hayathnagar area of Hayathnagar mandal, Ranga Reddy district. The sanctioned scheme is one building, with a stilt level and five upper floors, on a recorded site of 308.38 sq. m. The approved building permit identifies the plot portions as 68 NORTH PART, 69 SOUTH PART, and 69 AND 70 PART. RERA record Land records
The offer recorded in the RERA filing is 10 2BHK units. The portal snapshot lists all 10 as available, but gives no as-of date. The documents establish a permit and a promoter completion undertaking; they do not establish current construction progress or completed/occupied portions. No occupancy certificate is supplied. RERA unit table RERA unit details
3. Master plan, architecture & building design
The GHMC building permit covers one residential building on a 308.38 sq. m. plot. Its plan extraction records 170.91 sq. m. proposed coverage area (55.00%), 128.9 sq. m. vacant plot area, 854.55 sq. m. proposed BUA excluding parking, and 1,025.46 sq. m. proposed BUA including parking. The same extraction separately records 854.55 sq. m. as total net BUA and 1,038.74 sq. m. as proposed building BUA; the supplied record does not reconcile these differently labelled figures.
The sanctioned floor configuration is 1 Stilt + 5 Floors. The plan extraction lists 170.91 sq. m. for the stilt and each of the first through fifth floors, with the fifth floor marked “TDR,” and 13.28 sq. m. at terrace level. The GHMC permit records a height of 15.0 m, while the plan extraction records 17.95 m from ground level and 15 m excluding stilt.
The approval extraction shows 10 dwelling units and a 9.0 m building road width. It also records a vacant plot area and a “Tot Lot” of 0 sq. m. in the permit extraction; no drawing-derived details are supplied for landscaping layout, flat distribution by floor, lifts, stairs, or internal circulation.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 49.7 sq. m. (535 sq. ft.) | Not available | Not supplied |
RERA unit table RERA unit details
The 49.7 sq. m. figure is the RERA-filed saleable area. The supplied floor-plan review reports that drawings were processed, but no 2BHK flat design was measured; therefore no software-measured carpet area or room dimensions can be reported. Carpet area and saleable area are not interchangeable: the supplied measurement note describes saleable area as including a share of common areas, while the project record provides no unit-level carpet-area or loading figure. RERA unit details Floor plans RERA unit table
5. Parking & vehicle circulation
The approval-plan extraction records five car-parking spaces, a 170.91 sq. m. net parking area, and a stilt parking floor. The GHMC permit also records 170.91 sq. m. total parking area and requires approved cellar/stilt parking to be used exclusively for parking. The supplied evidence does not identify resident, visitor or accessible-space allocations, parking ownership or allotment to particular apartments, two-wheeler counts, ramps, or vehicle-entry arrangements.
GHMC’s permit includes a condition that parking places are to have electric-vehicle charging infrastructure under the applicable requirements; the documents do not establish that charging equipment has been installed.
6. Amenities, recreation & open spaces
The RERA amenities record lists proposed project infrastructure and facilities with progress shown as 0% where reported. The permit separately identifies certain site provisions. Neither record establishes that these facilities are complete or independently verified.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot lot / green strip / park | No size supplied; GHMC permit extraction records Tot Lot area as 0 sq. m. and separately requires greenery and fencing of the tot lot. | RERA amenities | RERA amenities progress 0%; completion not verified. |
| Rainwater harvesting | Four rainwater-harvesting pits recorded in the GHMC permit; plan extraction also lists rainwater harvesting. | Required/recorded provision; installation not verified. | |
| Internal roads and footpaths | Listed in RERA amenities. | RERA amenities | Progress 0%; completion not verified. |
| Street lighting | Listed in RERA amenities. | RERA amenities | Progress 0%; completion not verified. |
| Community buildings | Listed in RERA amenities; no size or specific facility is stated. | RERA amenities | Progress 0%; completion not verified. |
The supplied evidence contains no project-specific TG-RERA amenity list for a clubhouse or indoor recreation facility. Vendor-listed facilities are not treated here as sanctioned or delivered project amenities. RERA amenities
7. Utilities, building services & safety
The RERA amenities record lists water supply, sewerage (including chamber, lines, septic tank and STP), storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station. Progress is reported as 0% where shown, and no capacities or completion evidence are supplied. RERA amenities
The GHMC plan extraction lists a sump, septic provision, rainwater-harvesting structure, transformer space and garbage house; the permit records four rainwater-harvesting pits and requires a transformer space and garbage house. The documents do not establish installed water sources, storage capacity, treatment capacity, electrical supply or backup arrangements.
The permit requires fire-safety provisions and an occupancy Fire NOC before an occupancy certificate; it also requires compliance with structural-safety and means-of-escape conditions. It records EV charging infrastructure as a requirement for parking places. These are permit conditions, not evidence that the systems, clearances or equipment have been completed. No lift count or capacity, accessible circulation details, CCTV/security arrangements, or waste-segregation system is established by the supplied project-specific evidence.
8. Location, access & connectivity
The registered location is Yella reddy Colony, Hayathnagar, Ranga Reddy, PIN 500073. The building permit identifies Bagh Hayathnagar and Yellareddy Colony Phase-2; the site is in GHMC limits. The RERA land record gives the west boundary as a 30 ft wide road, and the plan extraction records a 9.0 m building road width. RERA record Land records
The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 1.9 km away. This is a recorded approximate distance, not a travel-time estimate. No other independently sourced distances or public-transport details are supplied. Location record
9. Developer & development status
The registered promoter is AKSHAYA HOMES, recorded in the RERA filing as a partnership. Its GSTIN is 36ACJFA2372C1ZP. VAKITI RAMACHANDRA REDDY is identified as authorized signatory; the supplied partnership deed extract describes him as managing partner. The partnership deed is dated 21/03/2025. The promoter address in the project record is Vasavi Colony, Yella Reddy Colony Phase-2, Bagh Hayathnagar, Hayathnagar, Ranga Reddy, 500073. An email address, telephone number and official promoter website are not supplied. Corporate record Parties record
The GHMC permit identifies the applicant as Sri MADDI PRABHAKAR REDDY and the developer as V. RAMACHANDRA REDDY. The registered development agreement-cum-GPA is described in the project record as an area-share arrangement between landowner Maddi Prabhakar Reddy and Akshaya Homes; it is not a conveyance of land title. Parties record
The project’s TG-RERA registration is valid through 14/11/2028 unless extended. The RERA Form B undertaking gives a completion period ending 14/11/2028; the GHMC permit also states construction is to be completed before 14/11/2028. No construction-progress figure or occupancy certificate is supplied.
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C for AKSHAYA NIVAS, registration P02400011024, valid 14/11/2025–14/11/2028 unless extended. |
| Principal building permit | GHMC Building Permit Order 1798/GHMC/SWBP/LBN2/2025, dated 14/11/2025; file no. 008825/GHMC/04091/SWBP/LBN2/2025. |
| Building-plan record | Plan extraction for a residential building of 1 Stilt + 5 Floors, 10 dwelling units, on Survey No. 101. |
| Title and development documents filed | Title-report and sale-deed documents 624573, 624574, and 719047; Development Agreement-Cum-GPA document 624570. Document index |
| Promoter declarations and registration filing | Form B declaration 624725; registration certificate REGCERT-78133. Document index |
| Occupancy / completion certificate | No issued OC or completion certificate appears in the supplied record. The GHMC permit requires an OC before occupation. |
The permit records LRS numbers LRS/7815/CR-3/EAST ZONE/2012 and LRS/17829/CR-3/EASTZONE/2010, and references mortgage deed no. 5791/2025. These are identifiers appearing in the filed approval record; their scope and implications are not assessed in this Overview.
1. Project at a glance
Project identity
Registered project: AKSHAYA NIVAS
Project type: Residential apartment project
Phase / registered portion: No phase designation disclosed in the registration record; the registered site is identified by Survey No. 101 and the stated plot portions.
TG-RERA registration: P02400011024
Registration validity: 14/11/2025 to 14/11/2028, unless extended by the Authority. This is the registration period, not a statement of construction completion or occupancy.
Registered promoter: AKSHAYA HOMES
RERA status in supplied record: Registered; certificate captured 10/09/2026.
Land and geographic identity
Locality: Yella reddy Colony; the GHMC permit identifies YELLAREDDY COLONY PHASE-2 and BAGH HAYATHNAGAR.
Revenue village: RERA certificate: Yella reddy Colony. GHMC permit and title documents: Bagh Hayathnagar.
Mandal / district / PIN: Hayathnagar / Ranga Reddy / 500073
Survey number and plot portions: Survey No. 101; 68 NORTH PART, 69 SOUTH PART, 69 AND 70 PART. No survey subdivision is specified in the supplied record.
Site extent: 308.38 sq. m. total and net plot area in the GHMC permit; RERA land record also reports 308.38 sq. m.
Boundaries in RERA land record: North: Plot No. 70 Part; South: Plot No. 68 Southern Part; East: Plot Nos. 34, 35 and 36; West: 30 ft wide road.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building permit: 1798/GHMC/SWBP/LBN2/2025, approved 14/11/2025; GHMC file no. 008825/GHMC/04091/SWBP/LBN2/2025.
Building count and configuration: One residential building: 1 Stilt + 5 Floors.
Building height: GHMC plan extraction records 17.95 m proposed height from ground level and 15 m excluding stilt.
Approved built-up area: 854.55 sq. m. total proposed BUA excluding parking; 1,025.46 sq. m. total proposed BUA including parking. These are distinct plan-record figures.
Parking shown in approval extraction: Five car-parking spaces; 170.91 sq. m. parking area, including a stilt parking floor.
Units: 10 dwelling units in the GHMC permit and 10 units in the TG-RERA filing.
Offering and status
Unit type: 2BHK apartments
RERA-filed saleable area: 49.7 sq. m. per unit (535 sq. ft. in the normalized unit record); 10 units.
Booked / available: 0 booked and 10 available in the TG-RERA portal snapshot supplied; no snapshot as-of date is provided, so counts are indicative.
Construction stage: Current construction progress is not established by the supplied evidence. The project is described as new; the GHMC permit sets construction commencement and completion deadlines.
Completion dates: GHMC permit: construction to be completed before 14/11/2028. Form B completion undertaking: 14/11/2028. The project header separately records a proposed completion date of 14/03/2029; the supplied record does not explain that date.
Occupancy certificate: No occupancy certificate is supplied. GHMC requires an occupancy certificate before occupation; the record does not establish that one has been issued for the building.
2. The project story
AKSHAYA NIVAS is a 10-apartment residential project registered with TG-RERA on Survey No. 101 in the Yella reddy Colony / Bagh Hayathnagar area of Hayathnagar mandal, Ranga Reddy district. The sanctioned scheme is one building, with a stilt level and five upper floors, on a recorded site of 308.38 sq. m. The approved building permit identifies the plot portions as 68 NORTH PART, 69 SOUTH PART, and 69 AND 70 PART.
The offer recorded in the RERA filing is 10 2BHK units. The portal snapshot lists all 10 as available, but gives no as-of date. The documents establish a permit and a promoter completion undertaking; they do not establish current construction progress or completed/occupied portions. No occupancy certificate is supplied.
3. Master plan, architecture & building design
The GHMC building permit covers one residential building on a 308.38 sq. m. plot. Its plan extraction records 170.91 sq. m. proposed coverage area (55.00%), 128.9 sq. m. vacant plot area, 854.55 sq. m. proposed BUA excluding parking, and 1,025.46 sq. m. proposed BUA including parking. The same extraction separately records 854.55 sq. m. as total net BUA and 1,038.74 sq. m. as proposed building BUA; the supplied record does not reconcile these differently labelled figures.
The sanctioned floor configuration is 1 Stilt + 5 Floors. The plan extraction lists 170.91 sq. m. for the stilt and each of the first through fifth floors, with the fifth floor marked “TDR,” and 13.28 sq. m. at terrace level. The GHMC permit records a height of 15.0 m, while the plan extraction records 17.95 m from ground level and 15 m excluding stilt.
The approval extraction shows 10 dwelling units and a 9.0 m building road width. It also records a vacant plot area and a “Tot Lot” of 0 sq. m. in the permit extraction; no drawing-derived details are supplied for landscaping layout, flat distribution by floor, lifts, stairs, or internal circulation.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 49.7 sq. m. (535 sq. ft.) | Not available | Not supplied |
The 49.7 sq. m. figure is the RERA-filed saleable area. The supplied floor-plan review reports that drawings were processed, but no 2BHK flat design was measured; therefore no software-measured carpet area or room dimensions can be reported. Carpet area and saleable area are not interchangeable: the supplied measurement note describes saleable area as including a share of common areas, while the project record provides no unit-level carpet-area or loading figure.
5. Parking & vehicle circulation
The approval-plan extraction records five car-parking spaces, a 170.91 sq. m. net parking area, and a stilt parking floor. The GHMC permit also records 170.91 sq. m. total parking area and requires approved cellar/stilt parking to be used exclusively for parking. The supplied evidence does not identify resident, visitor or accessible-space allocations, parking ownership or allotment to particular apartments, two-wheeler counts, ramps, or vehicle-entry arrangements.
GHMC’s permit includes a condition that parking places are to have electric-vehicle charging infrastructure under the applicable requirements; the documents do not establish that charging equipment has been installed.
6. Amenities, recreation & open spaces
The RERA amenities record lists proposed project infrastructure and facilities with progress shown as 0% where reported. The permit separately identifies certain site provisions. Neither record establishes that these facilities are complete or independently verified.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot lot / green strip / park | No size supplied; GHMC permit extraction records Tot Lot area as 0 sq. m. and separately requires greenery and fencing of the tot lot. | RERA amenities progress 0%; completion not verified. | |
| Rainwater harvesting | Four rainwater-harvesting pits recorded in the GHMC permit; plan extraction also lists rainwater harvesting. | Required/recorded provision; installation not verified. | |
| Internal roads and footpaths | Listed in RERA amenities. | Progress 0%; completion not verified. | |
| Street lighting | Listed in RERA amenities. | Progress 0%; completion not verified. | |
| Community buildings | Listed in RERA amenities; no size or specific facility is stated. | Progress 0%; completion not verified. |
The supplied evidence contains no project-specific TG-RERA amenity list for a clubhouse or indoor recreation facility. Vendor-listed facilities are not treated here as sanctioned or delivered project amenities.
7. Utilities, building services & safety
The RERA amenities record lists water supply, sewerage (including chamber, lines, septic tank and STP), storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station. Progress is reported as 0% where shown, and no capacities or completion evidence are supplied.
The GHMC plan extraction lists a sump, septic provision, rainwater-harvesting structure, transformer space and garbage house; the permit records four rainwater-harvesting pits and requires a transformer space and garbage house. The documents do not establish installed water sources, storage capacity, treatment capacity, electrical supply or backup arrangements.
The permit requires fire-safety provisions and an occupancy Fire NOC before an occupancy certificate; it also requires compliance with structural-safety and means-of-escape conditions. It records EV charging infrastructure as a requirement for parking places. These are permit conditions, not evidence that the systems, clearances or equipment have been completed. No lift count or capacity, accessible circulation details, CCTV/security arrangements, or waste-segregation system is established by the supplied project-specific evidence.
8. Location, access & connectivity
The registered location is Yella reddy Colony, Hayathnagar, Ranga Reddy, PIN 500073. The building permit identifies Bagh Hayathnagar and Yellareddy Colony Phase-2; the site is in GHMC limits. The RERA land record gives the west boundary as a 30 ft wide road, and the plan extraction records a 9.0 m building road width.
The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 1.9 km away. This is a recorded approximate distance, not a travel-time estimate. No other independently sourced distances or public-transport details are supplied.
9. Developer & development status
The registered promoter is AKSHAYA HOMES, recorded in the RERA filing as a partnership. Its GSTIN is 36ACJFA2372C1ZP. VAKITI RAMACHANDRA REDDY is identified as authorized signatory; the supplied partnership deed extract describes him as managing partner. The partnership deed is dated 21/03/2025. The promoter address in the project record is Vasavi Colony, Yella Reddy Colony Phase-2, Bagh Hayathnagar, Hayathnagar, Ranga Reddy, 500073. An email address, telephone number and official promoter website are not supplied.
The GHMC permit identifies the applicant as Sri MADDI PRABHAKAR REDDY and the developer as V. RAMACHANDRA REDDY. The registered development agreement-cum-GPA is described in the project record as an area-share arrangement between landowner Maddi Prabhakar Reddy and Akshaya Homes; it is not a conveyance of land title.
The project’s TG-RERA registration is valid through 14/11/2028 unless extended. The RERA Form B undertaking gives a completion period ending 14/11/2028; the GHMC permit also states construction is to be completed before 14/11/2028. No construction-progress figure or occupancy certificate is supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C for AKSHAYA NIVAS, registration P02400011024, valid 14/11/2025–14/11/2028 unless extended.
Principal building permit: GHMC Building Permit Order 1798/GHMC/SWBP/LBN2/2025, dated 14/11/2025; file no. 008825/GHMC/04091/SWBP/LBN2/2025.
Building-plan record: Plan extraction for a residential building of 1 Stilt + 5 Floors, 10 dwelling units, on Survey No. 101.
Title and development documents filed: Title-report and sale-deed documents 624573, 624574, and 719047; Development Agreement-Cum-GPA document 624570.
Promoter declarations and registration filing: Form B declaration 624725; registration certificate REGCERT-78133.
Occupancy / completion certificate: No issued OC or completion certificate appears in the supplied record. The GHMC permit requires an OC before occupation.
The permit records LRS numbers LRS/7815/CR-3/EAST ZONE/2012 and LRS/17829/CR-3/EASTZONE/2010, and references mortgage deed no. 5791/2025. These are identifiers appearing in the filed approval record; their scope and implications are not assessed in this Overview.
Frequently asked questions
Is AKSHAYA NIVAS registered with Telangana RERA?
Yes. AKSHAYA NIVAS is registered with the Telangana Real Estate Regulatory Authority as P02400011024; the registration status is New Project.
Who is the developer of AKSHAYA NIVAS?
The promoter named in the RERA registration is AKSHAYA HOMES.
Where is AKSHAYA NIVAS located?
AKSHAYA NIVAS is in BAGH HAYATHNAGAR, Yella reddy Colony, Hayathnagar, Rangareddy, Telangana (500073).
When will AKSHAYA NIVAS be completed?
The promoter's proposed date of completion filed with RERA is 14/03/2029. This is the promoter's declaration, not a guarantee.