CONCRETE AVASA is a residential apartment project in Nagole, Uppal Mandal, Medchal-Malkajgiri district, developed by registered promoter CONCRETE INFRA PROJECTS INDIA LLP. The project covers 14600.42 m² and comprises four residential blocks and a clubhouse; the residential blocks are approved as 1Stilt + 5, with A-1 also having 1Cellar, and the clubhouse as 1Ground + 2. The RERA filing records 270 homes: 175 2BHK and 95 3BHK units. Its TG-RERA registration is P02200001445, and the proposed completion date recorded in the RERA filing is 30/09/2022.
More from Concrete Infra Projects India LLP · 7 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | CONCRETE AVASA |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | Phase or separately registered portion not identified in the supplied record. RERA record |
| TG-RERA registration | P02200001445; Form C records registration from 25/11/2019 to 30/09/2022. The certificate lists a two-year validity and says extension would be subject to Authority approval; the supplied certificate records no extension. Registration validity is distinct from the completion deadline and occupancy-certificate status. |
| Registered promoter | CONCRETE INFRA PROJECTS INDIA LLP, an LLP. Corporate record |
| RERA-record status | The filing labels the project “New Project.” The supplied record does not establish a current registration status beyond the certificate’s stated validity period. RERA filing |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Nagole / Nagole RERA record |
| Mandal / district / PIN | Uppal / Medchal-Malkajgiri / 500068 RERA record |
| Project survey numbers | SY. NO. 56 AND 61; the registration certificate lists SY. NO. 56 and 61. No subdivision is specified in the project identity. RERA record |
| Site extent | GHMC permit: 14600.42 m² site area; 765.35 m² road-affected area; 13835.06 m² net area. The RERA filing records 14600.42 m² total area, 765.35 m² affected area, and 13835.07 m² net area. RERA filing |
| Boundaries in RERA filing | East: ROAD WIDTH 9; west: VACANT LAND; north: ROAD WIDHT 12; south: VACANT LAND. RERA filing |
| GHMC permit road reference | The permit extract also refers to 18 mt. road widths. |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building permit | Permit 1/C3/12445/2019, approved 16 August, 2019; file no. 1/HO/16042/2017. Approvals record |
| Approved built-up area | The RERA filing records approved built-up area of 35180.85 m². The permit extract separately states “Proposed Covered builtup area 2,848,120.00”; the supplied extract does not identify the unit for that figure. RERA filing |
| Building count and uses | Permit extract identifies four residential blocks—A-1, B-1, C-1 and D-1—and a clubhouse building. |
| Sanctioned floors and heights | B-1, C-1 and D-1: 1Stilt + 5, each 14.95 m; A-1: 1Cellar + 1Stilt + 5, 14.4 m; CLUB HOUSE-1: 1Ground + 2, 9.45 m. |
| Parking levels | GHMC permit extract says cellar and stilts approved for parking, and requires those areas to be used exclusively for vehicle parking. A parking-space count is not supplied. |
| Unit count | RERA filing records 270 units across 4 buildings. The supplied GHMC extract identifies five permitted blocks including the clubhouse, but does not provide an approved dwelling-unit count. RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configurations | 2BHK: 175 units; 3BHK: 95 units. RERA unit table |
| RERA-filed saleable area | 2BHK: 18.8 m²; 3BHK: 117.93 m². These are the figures recorded in the supplied RERA unit data. RERA unit table |
| Booked / available | The portal-derived counts show 0 booked / 175 available for 2BHK and 0 booked / 95 available for 3BHK; the record has no as-of date, so these counts are indicative rather than a current inventory confirmation. RERA unit table |
| Completion dates | Promoter’s Form B undertaking: 30/09/2022. RERA project information: 30/09/2022 at registration. GHMC permit extract states construction to be completed before 16 August, 2025. These are completion deadlines, not registration-validity dates. RERA filing |
| Construction stage | The supplied record includes a declared RERA completeness figure of 80%, but no site inspection or independent construction-progress verification is supplied. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. GHMC’s permit conditions require an occupancy certificate before occupation. The certificate’s absence from this evidence pack does not establish whether one has since been issued. Document index |
2. The project story
CONCRETE AVASA is recorded with TG-RERA as a residential apartment project in Nagole, Uppal Mandal, Medchal-Malkajgiri district, on Survey Nos. 56 and 61. The GHMC building permit extract describes four residential blocks and a separate clubhouse building, with the residential blocks approved as stilt-and-five-floor buildings, one of them also having a cellar. RERA record
The RERA filing describes an offering of 270 homes: 175 two-bedroom and 95 three-bedroom units. Its portal-derived booking figures show all 270 as available and none booked, but carry no as-of date. The filing also reports 80% completeness; this is a recorded progress figure, not independently verified site progress. No occupancy or completion certificate is included in the supplied documents, and the GHMC permit requires an occupancy certificate before occupation. RERA unit table RERA record
3. Master plan, architecture & building design
- The supplied GHMC permit extract describes four residential blocks plus CLUB HOUSE-1. Blocks B-1, C-1 and D-1 are each sanctioned as 1Stilt + 5, while A-1 is 1Cellar + 1Stilt + 5. The clubhouse is 1Ground + 2. The listed heights are 14.95 m for B-1, C-1 and D-1; 14.4 m for A-1; and 9.45 m for the clubhouse.
- The permit extract records a site area of 14600.42 m², road-affected area of 765.35 m², net area of 13835.06 m², and a 1410 m² tot-lot. The RERA filing separately records approved built-up area of 35180.85 m². No evidence supplied here specifies the FSI-counted area, gross built-up area, detailed building footprints, flats per floor, lift or stair arrangement, internal circulation, or phase-wise organization. RERA filing RERA filing
- The RERA-uploaded plan items are identified as documents 73106 and 73110, but the supplied record does not include their extracted architectural details. No layout approval details are available from the public lookup in the evidence pack. Document index HMDA
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 175 | 0 | 175 | 18.8 m² | Not measured from supplied drawings | Not supplied |
| 3BHK | 95 | 0 | 95 | 117.93 m² | 86.5–117.5 m², median 110.7 m²; software-measured from drawings, not a RERA disclosure | Not supplied |
RERA configuration and inventory figures come from the project filing; booking counts have no recorded as-of date. The 3BHK carpet-area range is a software measurement of approved floor-plan drawing geometry, based on 12 measured designs, and is flagged in the source as needing review. Carpet area describes the measured dwelling area; saleable area is a separate RERA-filed measure that includes the home’s share of common areas. No balcony, utility, or loading calculation is supplied that would support a further breakdown. RERA unit table RERA unit details Floor plans
The 3BHK drawing sample includes bedrooms, a guest room, living/dining, kitchen, toilets and a utility area. For example, drawing 73110, “FIRST FLOOR PLAN,” flat C-6, includes a 4.42 m² utility area; this is drawing-derived, not a RERA-filed unit specification. No 2BHK carpet measurement was established from the supplied drawings. RERA unit details
5. Parking & vehicle circulation
- The GHMC permit extract states that the cellar and stilt areas approved in the plan are to be used exclusively for vehicle parking, without partition walls or rolling shutters. It does not provide sanctioned parking-space counts, accessible or visitor-space numbers, mechanical-parking provision, ramp details, or a unit-wise parking allocation. A parking bay shown in a plan, by itself, would not establish exclusive ownership or allotment.
- The RERA filing records a 2617.39 m² mortgage area, but the supplied material does not specify its parking allocation or relationship to individual units. The RERA unit data marks both configurations as mortgaged. RERA filing RERA unit table
6. Amenities, recreation & open spaces
The RERA amenity schedule records 15 items. Each item with an explicit “YES” is shown as available in the schedule; all listed progress percentages are 0%, so this record does not establish completed or independently verified delivery. The GHMC permit separately specifies a tot-lot and site provisions for trees, transformer space and a garbage house. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Clubhouse | Club house listed; permit identifies CLUB HOUSE-1 as 1Ground + 2, height 9.45 m. | RERA amenities | RERA schedule: YES, 0%; completion not independently verified. |
| Internal roads & footpaths | Size not supplied. | RERA amenities | RERA schedule: YES, 0%; completion not independently verified. |
| Green strip / tot lot / park | GHMC permit records a 1410 m² tot-lot and requires it to be fenced and maintained as greenery before occupancy certificate. | RERA amenities | Schedule progress 0%; no completion verification supplied. |
| Street lighting | Size or quantity not supplied. | RERA amenities | RERA schedule: YES, 0%; completion not independently verified. |
| Community buildings | Further description or size not supplied. | RERA amenities | RERA schedule: YES, 0%; completion not independently verified. |
| Trees | Permit extract lists 730 Trees. | Permit-listed provision; planting and survival are not verified. |
The supplier’s amenity list also names recreational and service features, but those are not established as RERA-filed or delivered facilities by the supplied evidence and are not treated here as project commitments. Promoter website
7. Utilities, building services & safety
- The RERA amenity schedule lists water supply; sewerage, including chambers, lines, septic tank and STP; storm-water drains; sewage and sullage treatment/disposal; solid-waste management and disposal; rainwater harvesting; energy management; fire protection and fire-safety requirements; and an electrical meter room, sub-station and receiving station. Each is shown as “YES” where the schedule supplies that field, but each listed progress percentage is 0%. The schedule does not state capacities, water sources, storage volumes, treatment capacity, reuse quantities, backup duration or electrical load. RERA amenities
- The GHMC permit requires space for a transformer and a garbage house within the premises. It also states that an occupancy certificate is compulsory before occupation. These are permit provisions/conditions; the supplied record does not verify installation, commissioning, or completion.
- The supplier’s specification list mentions eight passenger lifts and common-service generator backup, but those details are not supported as RERA-filed or GHMC-sanctioned specifications in the evidence supplied for this Overview. No verified lift capacities, accessible circulation details, fire-system specifications, CCTV installation status or security-operation details are available here. Promoter website
8. Location, access & connectivity
The official project location in the supplied RERA record is Nagole village, Uppal Mandal, Medchal-Malkajgiri district, Telangana 500068, on Survey Nos. 56 and 61. RERA record
The location data supplies one independently mapped connectivity reference: the nearest sampled Outer Ring Road interchange is approximately 8.8 km from the cadastral parcel centroid. This is a measured map reference, not a travel-time claim. The additional metro, airport, bus-stop and landmark distances in the supplier material are promotional/third-party claims and are not used as official project-location measurements here. Location record Promoter website
9. Developer & development status
The registered legal promoter is CONCRETE INFRA PROJECTS INDIA LLP, an LLP. The RERA filing lists Anil Kumar Reddy Arani as authorized signatory and identifies the landowners as project participants under an area-share arrangement. The supplied registration certificate gives the promoter office as Village Gachi Bowli, Mandal Serilingampally, District Ranga Reddy, PIN 500032. No official phone number, email address or website is supplied. Corporate record Parties record
The promoter’s Form B affidavit, dated 14th September, 2019, undertakes completion by 30/09/2022. The RERA record’s completeness figure is 80%, without an independent site inspection in the supplied evidence. No extension document or occupancy/completion certificate is included in this evidence pack. The GHMC permit extract gives a separate construction-completion date of 16 August, 2025 and requires an occupancy certificate before occupation. RERA record
10. Approvals, official records & documents
| Record | Supplied evidence and scope |
|---|---|
| TG-RERA registration | Form C for CONCRETE AVASA, registration P02200001445, issued 25/11/2019, stated valid through 30/09/2022. |
| GHMC building permit | Building Permit Order 1/C3/12445/2019, dated 16 August, 2019, file no. 1/HO/16042/2017; identifies Survey Nos. 56 and 61, Nagole, and the four residential blocks plus clubhouse. |
| RERA Form B declaration | Promoter affidavit dated 14th September, 2019, including the stated completion undertaking and project declarations. |
| Approved-plan records | RERA filing lists plan-approval number 1/C3/12445/2019. Plan-related uploads 73106 and 73110 are present, but their detailed drawing content is not extracted in the supplied record. Approvals record Document index |
| Layout lookup | Public HMDA DPMS layout lookup was unavailable in the supplied evidence; no layout status is established from that lookup. HMDA |
| Occupancy / completion certificate | No such certificate is included in the supplied documents; current issuance status is unverified. Document index |
| Other project-specific clearances | No project-specific environmental-clearance or pollution-control record is established here. The supplied environmental record is matched to the promoter but names a different project, so it is not evidence for CONCRETE AVASA. Regulatory record |
1. Project at a glance
Project identity
Registered project name: CONCRETE AVASA
Project type: Residential apartment project
Phase / registered portion: Phase or separately registered portion not identified in the supplied record.
TG-RERA registration: P02200001445; Form C records registration from 25/11/2019 to 30/09/2022. The certificate lists a two-year validity and says extension would be subject to Authority approval; the supplied certificate records no extension. Registration validity is distinct from the completion deadline and occupancy-certificate status.
Registered promoter: CONCRETE INFRA PROJECTS INDIA LLP, an LLP.
RERA-record status: The filing labels the project “New Project.” The supplied record does not establish a current registration status beyond the certificate’s stated validity period.
Land and geographic identity
Locality / revenue village: Nagole / Nagole
Mandal / district / PIN: Uppal / Medchal-Malkajgiri / 500068
Project survey numbers: SY. NO. 56 AND 61; the registration certificate lists SY. NO. 56 and 61. No subdivision is specified in the project identity.
Site extent: GHMC permit: 14600.42 m² site area; 765.35 m² road-affected area; 13835.06 m² net area. The RERA filing records 14600.42 m² total area, 765.35 m² affected area, and 13835.07 m² net area.
Boundaries in RERA filing: East: ROAD WIDTH 9; west: VACANT LAND; north: ROAD WIDHT 12; south: VACANT LAND.
GHMC permit road reference: The permit extract also refers to 18 mt. road widths.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building permit: Permit 1/C3/12445/2019, approved 16 August, 2019; file no. 1/HO/16042/2017.
Approved built-up area: The RERA filing records approved built-up area of 35180.85 m². The permit extract separately states “Proposed Covered builtup area 2,848,120.00”; the supplied extract does not identify the unit for that figure.
Building count and uses: Permit extract identifies four residential blocks—A-1, B-1, C-1 and D-1—and a clubhouse building.
Sanctioned floors and heights: B-1, C-1 and D-1: 1Stilt + 5, each 14.95 m; A-1: 1Cellar + 1Stilt + 5, 14.4 m; CLUB HOUSE-1: 1Ground + 2, 9.45 m.
Parking levels: GHMC permit extract says cellar and stilts approved for parking, and requires those areas to be used exclusively for vehicle parking. A parking-space count is not supplied.
Unit count: RERA filing records 270 units across 4 buildings. The supplied GHMC extract identifies five permitted blocks including the clubhouse, but does not provide an approved dwelling-unit count.
Offering and status
RERA-filed configurations: 2BHK: 175 units; 3BHK: 95 units.
RERA-filed saleable area: 2BHK: 18.8 m²; 3BHK: 117.93 m². These are the figures recorded in the supplied RERA unit data.
Booked / available: The portal-derived counts show 0 booked / 175 available for 2BHK and 0 booked / 95 available for 3BHK; the record has no as-of date, so these counts are indicative rather than a current inventory confirmation.
Completion dates: Promoter’s Form B undertaking: 30/09/2022. RERA project information: 30/09/2022 at registration. GHMC permit extract states construction to be completed before 16 August, 2025. These are completion deadlines, not registration-validity dates.
Construction stage: The supplied record includes a declared RERA completeness figure of 80%, but no site inspection or independent construction-progress verification is supplied.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. GHMC’s permit conditions require an occupancy certificate before occupation. The certificate’s absence from this evidence pack does not establish whether one has since been issued.
2. The project story
CONCRETE AVASA is recorded with TG-RERA as a residential apartment project in Nagole, Uppal Mandal, Medchal-Malkajgiri district, on Survey Nos. 56 and 61. The GHMC building permit extract describes four residential blocks and a separate clubhouse building, with the residential blocks approved as stilt-and-five-floor buildings, one of them also having a cellar.
The RERA filing describes an offering of 270 homes: 175 two-bedroom and 95 three-bedroom units. Its portal-derived booking figures show all 270 as available and none booked, but carry no as-of date. The filing also reports 80% completeness; this is a recorded progress figure, not independently verified site progress. No occupancy or completion certificate is included in the supplied documents, and the GHMC permit requires an occupancy certificate before occupation.
3. Master plan, architecture & building design
- The supplied GHMC permit extract describes four residential blocks plus CLUB HOUSE-1. Blocks B-1, C-1 and D-1 are each sanctioned as 1Stilt + 5, while A-1 is 1Cellar + 1Stilt + 5. The clubhouse is 1Ground + 2. The listed heights are 14.95 m for B-1, C-1 and D-1; 14.4 m for A-1; and 9.45 m for the clubhouse.
- The permit extract records a site area of 14600.42 m², road-affected area of 765.35 m², net area of 13835.06 m², and a 1410 m² tot-lot. The RERA filing separately records approved built-up area of 35180.85 m². No evidence supplied here specifies the FSI-counted area, gross built-up area, detailed building footprints, flats per floor, lift or stair arrangement, internal circulation, or phase-wise organization.
- The RERA-uploaded plan items are identified as documents 73106 and 73110, but the supplied record does not include their extracted architectural details. No layout approval details are available from the public lookup in the evidence pack.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 175 | 0 | 175 | 18.8 m² | Not measured from supplied drawings | Not supplied |
| 3BHK | 95 | 0 | 95 | 117.93 m² | 86.5–117.5 m², median 110.7 m²; software-measured from drawings, not a RERA disclosure | Not supplied |
RERA configuration and inventory figures come from the project filing; booking counts have no recorded as-of date. The 3BHK carpet-area range is a software measurement of approved floor-plan drawing geometry, based on 12 measured designs, and is flagged in the source as needing review. Carpet area describes the measured dwelling area; saleable area is a separate RERA-filed measure that includes the home’s share of common areas. No balcony, utility, or loading calculation is supplied that would support a further breakdown.
The 3BHK drawing sample includes bedrooms, a guest room, living/dining, kitchen, toilets and a utility area. For example, drawing 73110, “FIRST FLOOR PLAN,” flat C-6, includes a 4.42 m² utility area; this is drawing-derived, not a RERA-filed unit specification. No 2BHK carpet measurement was established from the supplied drawings.
5. Parking & vehicle circulation
- The GHMC permit extract states that the cellar and stilt areas approved in the plan are to be used exclusively for vehicle parking, without partition walls or rolling shutters. It does not provide sanctioned parking-space counts, accessible or visitor-space numbers, mechanical-parking provision, ramp details, or a unit-wise parking allocation. A parking bay shown in a plan, by itself, would not establish exclusive ownership or allotment.
- The RERA filing records a 2617.39 m² mortgage area, but the supplied material does not specify its parking allocation or relationship to individual units. The RERA unit data marks both configurations as mortgaged.
6. Amenities, recreation & open spaces
The RERA amenity schedule records 15 items. Each item with an explicit “YES” is shown as available in the schedule; all listed progress percentages are 0%, so this record does not establish completed or independently verified delivery. The GHMC permit separately specifies a tot-lot and site provisions for trees, transformer space and a garbage house.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Clubhouse | Club house listed; permit identifies CLUB HOUSE-1 as 1Ground + 2, height 9.45 m. | RERA schedule: YES, 0%; completion not independently verified. | |
| Internal roads & footpaths | Size not supplied. | RERA schedule: YES, 0%; completion not independently verified. | |
| Green strip / tot lot / park | GHMC permit records a 1410 m² tot-lot and requires it to be fenced and maintained as greenery before occupancy certificate. | Schedule progress 0%; no completion verification supplied. | |
| Street lighting | Size or quantity not supplied. | RERA schedule: YES, 0%; completion not independently verified. | |
| Community buildings | Further description or size not supplied. | RERA schedule: YES, 0%; completion not independently verified. | |
| Trees | Permit extract lists 730 Trees. | Permit-listed provision; planting and survival are not verified. |
The supplier’s amenity list also names recreational and service features, but those are not established as RERA-filed or delivered facilities by the supplied evidence and are not treated here as project commitments.
7. Utilities, building services & safety
- The RERA amenity schedule lists water supply; sewerage, including chambers, lines, septic tank and STP; storm-water drains; sewage and sullage treatment/disposal; solid-waste management and disposal; rainwater harvesting; energy management; fire protection and fire-safety requirements; and an electrical meter room, sub-station and receiving station. Each is shown as “YES” where the schedule supplies that field, but each listed progress percentage is 0%. The schedule does not state capacities, water sources, storage volumes, treatment capacity, reuse quantities, backup duration or electrical load.
- The GHMC permit requires space for a transformer and a garbage house within the premises. It also states that an occupancy certificate is compulsory before occupation. These are permit provisions/conditions; the supplied record does not verify installation, commissioning, or completion.
- The supplier’s specification list mentions eight passenger lifts and common-service generator backup, but those details are not supported as RERA-filed or GHMC-sanctioned specifications in the evidence supplied for this Overview. No verified lift capacities, accessible circulation details, fire-system specifications, CCTV installation status or security-operation details are available here.
8. Location, access & connectivity
The official project location in the supplied RERA record is Nagole village, Uppal Mandal, Medchal-Malkajgiri district, Telangana 500068, on Survey Nos. 56 and 61.
The location data supplies one independently mapped connectivity reference: the nearest sampled Outer Ring Road interchange is approximately 8.8 km from the cadastral parcel centroid. This is a measured map reference, not a travel-time claim. The additional metro, airport, bus-stop and landmark distances in the supplier material are promotional/third-party claims and are not used as official project-location measurements here.
9. Developer & development status
The registered legal promoter is CONCRETE INFRA PROJECTS INDIA LLP, an LLP. The RERA filing lists Anil Kumar Reddy Arani as authorized signatory and identifies the landowners as project participants under an area-share arrangement. The supplied registration certificate gives the promoter office as Village Gachi Bowli, Mandal Serilingampally, District Ranga Reddy, PIN 500032. No official phone number, email address or website is supplied.
The promoter’s Form B affidavit, dated 14th September, 2019, undertakes completion by 30/09/2022. The RERA record’s completeness figure is 80%, without an independent site inspection in the supplied evidence. No extension document or occupancy/completion certificate is included in this evidence pack. The GHMC permit extract gives a separate construction-completion date of 16 August, 2025 and requires an occupancy certificate before occupation.
10. Approvals, official records & documents
TG-RERA registration: Form C for CONCRETE AVASA, registration P02200001445, issued 25/11/2019, stated valid through 30/09/2022.
GHMC building permit: Building Permit Order 1/C3/12445/2019, dated 16 August, 2019, file no. 1/HO/16042/2017; identifies Survey Nos. 56 and 61, Nagole, and the four residential blocks plus clubhouse.
RERA Form B declaration: Promoter affidavit dated 14th September, 2019, including the stated completion undertaking and project declarations.
Approved-plan records: RERA filing lists plan-approval number 1/C3/12445/2019. Plan-related uploads 73106 and 73110 are present, but their detailed drawing content is not extracted in the supplied record.
Layout lookup: Public HMDA DPMS layout lookup was unavailable in the supplied evidence; no layout status is established from that lookup.
Occupancy / completion certificate: No such certificate is included in the supplied documents; current issuance status is unverified.
Other project-specific clearances: No project-specific environmental-clearance or pollution-control record is established here. The supplied environmental record is matched to the promoter but names a different project, so it is not evidence for CONCRETE AVASA.
Frequently asked questions
Is CONCRETE AVASA registered with Telangana RERA?
Yes. CONCRETE AVASA is registered with the Telangana Real Estate Regulatory Authority as P02200001445; the registration status is New Project.
Who is the developer of CONCRETE AVASA?
The promoter named in the RERA registration is CONCRETE INFRA PROJECTS INDIA LLP.
Where is CONCRETE AVASA located?
CONCRETE AVASA is in NAGOLE, Uppal, Medchal-Malkajgiri, Telangana (500068).
When will CONCRETE AVASA be completed?
The promoter's proposed date of completion filed with RERA is 30/09/2023. This is the promoter's declaration, not a guarantee.
More projects in Nagole