Sign in

Radha Govinda Residency

ADHIRATH AND DHRITI DEVELOPERS AND BUILDERS PRIVATE LIMITED · Rangareddy · RERA P02400002921

RADHA GOVINDA RESIDENCY is a residential apartments project in NARSINGII, Ranga Reddy district; the mandal is not disclosed in the RERA land record. It is being developed by ADHIRATH AND DHRITI DEVELOPERS AND BUILDERS PRIVATE LIMITED. The project covers 1,042.37 sq. m and comprises one building with 1Stilt + 5 upper floors and 20 3BHK apartments. Its TG-RERA registration is P02400002921, and its proposed completion date is 30/06/2023.

01What we found

Period endedTG-RERA registration ran to 30 Jun 2023 - check its extension on TG-RERA
20documents on file - each fact links to its page
1court case on this project's land (survey 258, Narsingii)
11items to check - 6 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from magicbricks.com

1. Project at a glance

Project identity

FieldProject record
Registered project nameRADHA GOVINDA RESIDENCY RERA record
Project typeResidential apartments RERA record RERA filing
Phase / registered portionOne registered project/building; a separate phase name is not disclosed RERA record
TG-RERA registrationP02400002921; certificate issued 14/05/2021, valid through 30/06/2023; no extension is recorded in the supplied certificate RERA record
Registered promoterADHIRATH AND DHRITI DEVELOPERS AND BUILDERS PRIVATE LIMITED RERA record Corporate record
RERA statusListed as an “On-Going Project”; the registration validity period above is distinct from the completion deadline and from occupancy certification RERA record RERA filing

Land and geographic identity

FieldProject record
LocalityNARSINGII; the approval documents also identify Narsingi / Manchirevula-ORRGC RERA record RERA filing
Revenue villageRERA filing: Narsingii. Approval/title records refer to Manchirevula Village / Manchirevula-ORRGC Village; the mandal is not disclosed in the RERA land record RERA record Land records
MandalNot disclosed in the RERA land record; approval document states “Narsingii Muncipality-ORRGC Mandal” Land records
District / PINRanga Reddy / 500075 RERA record RERA filing
Survey numbers212, 257 and 258 Land records
Plot numbersQ-31 and Q-32 RERA filing
Registered site extent1,042.37 sq. m; RERA land record gives both total and net area as 1,042.37 sq. m, with affected area recorded as 0 RERA filing Land records
Boundaries (RERA filing)North: 12 MTS WIDE ROAD; South: PLOT NOS Q-44 AND Q-45; East: PLOT NO Q-30C; West: PLOT NO Q-33 RERA filing

Development identity

FieldProject record
Sanctioning / technical approval authorityHMDA technical approval; building permit order issued by Narsingi Municipality Approvals record
Principal approval identifiersHMDA technical approval 037290/SKP/R1/U6/HMDA/10072020, dated 10/12/2020; Narsingi Municipality building permit BA.NO: 25/2020-21 Approvals record
Approved built-up areaRERA filing: 2,433 sq. m. The building-permit order separately states “Built up area: 2414.6 Sq Mts”; the HMDA technical approval lists “Total Built up Area … 2903.78” and “Proposed Built-up Area 2414.6.” These are figures as labelled in their respective records; this overview does not treat them as interchangeable RERA filing
Building / tower countOne building/unit in the RERA project information; one residential building is described in the approval records RERA filing
Sanctioned floor configuration1Stilt + 5 upper floors; approval record states building height 14.75
Parking levels / countA stilt level is shown in the sanctioned configuration; a sanctioned parking-space count is not available in the supplied records
Unit count20 units declared in the RERA unit record; the approval document describes a single building, but the supplied approval extracts do not state the total sanctioned apartment count RERA unit table

Offering and status

FieldProject record
RERA-filed configuration3BHK; 20 units; filed saleable area 141.0 sq. m per unit RERA unit table
Booked / available0 booked / 20 available in the portal record; no as-of date is supplied, so these counts are indicative RERA unit table
Construction statusRERA record labels the project “On-Going Project” and shows 80% completeness; this is a declared record, not an independent site inspection RERA record
Original / revised completion date30/06/2023 / 30/06/2023 RERA record
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied project documents; the approval records require an occupancy certificate before occupation Document index

2. The project story

Radha Govinda Residency is registered as a residential apartment project on plots Q-31 and Q-32, covering survey numbers 212, 257 and 258 at the locality recorded as NARSINGII. Approval materials identify the site as Manchirevula-ORRGC Village and describe a single proposed residential building configured as 1Stilt + 5 upper floors. The registered offering is 20 3BHK apartments RERA record RERA filing RERA unit table.

The RERA record reports 80% completeness and the status “On-Going Project.” Those are record-declared status figures; the evidence supplied does not independently verify construction on site. The RERA completion date is 30/06/2023, while the registration certificate separately states registration validity through 30/06/2023. No occupancy or completion certificate is among the supplied documents, so completed or occupancy-certified status is not established here RERA record Document index.

3. Master plan, architecture & building design

The approval records describe a residential building on a 1,042.37 sq. m site, with 1Stilt + 5 upper floors and a stated height of 14.75. The RERA filing records approved built-up area as 2,433 sq. m. The Narsingi Municipality building-permit extract labels 2,414.6 sq. m as built-up area, while the HMDA technical approval extract lists both a total built-up area of 2,903.78 sq. m and proposed built-up area of 2,414.6 sq. m. These figures are retained with their source labels; no area-category equivalence is assumed RERA filing.

The HMDA record is a technical approval and states that building plans are to be sanctioned by the Executive Authority in conformity with the technically approved plans. The supplied documents do not include extracted drawings sufficient to describe building footprint, floor-by-floor apartment arrangement, flats per floor, lifts, stairs, entries, internal circulation, or landscaped/open-space dimensions. A separate public layout lookup was not available in the supplied HMDA record HMDA.

4. Homes, configurations & floor plans

The RERA filing records 20 3BHK units, all shown as available in the portal data, with saleable area of 141.0 sq. m per unit. Booking counts have no stated as-of date and should be treated as indicative RERA unit table.

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK20020141.0 sq. m92.9–94.4 sq. m; median 93.2 sq. m (software-measured from drawings)34% (software-measured)

The carpet-area range and median are software measurements from drawing geometry, not RERA-filed measurements; the source notes that the measurements need review. The drawing record contains a typical-floor-plan panel and room measurements for one flat, including a balcony measured at 18.0 sq. m and excluded from the measured carpet area. Carpet area, balcony area, common-area share and RERA saleable area are distinct measures; the filed 141.0 sq. m saleable area should not be read as carpet area RERA unit details Floor plans.

5. Parking & vehicle circulation

The approval documents identify a stilt level, but the supplied records do not establish the number of sanctioned car or two-wheeler spaces, visitor or accessible spaces, parking allocation to individual apartments, parking ramps or internal vehicle circulation. The RERA unit record marks the 3BHK units as mortgaged, and the approval conditions refer to a mortgaged built-up area; neither establishes exclusive parking rights for a purchaser RERA unit table.

6. Amenities, recreation & open spaces

The RERA amenity record marks water supply, green strip/tot-lot/park, rainwater harvesting and an electrical meter room/sub-station/receiving station as available at 100%. These are RERA-recorded declarations; no independent completion verification is supplied. Other listed infrastructure items have 0% recorded progress RERA amenities.

Clubhouse / indoor
Description / sizeNo clubhouse or indoor community facility is established in the supplied project records
Evidence sourceRERA amenities Document index
Declared progress / verified statusNot disclosed
Sports / recreation
Description / sizeTot-lot; approval extracts do not give a size
Evidence sourceHMDA technical approval and municipality permit; RERA record lists green strip/tot-lot/park RERA amenities
Declared progress / verified statusRERA record: 100%; independent completion verification not supplied
Landscape / open space
Description / sizeGreen strip / tot-lot / park; approval condition calls for a peripheral strip of greenery; no area is stated
Evidence sourceRERA amenities
Declared progress / verified statusRERA record: 100%; independent completion verification not supplied
Convenience / community
Description / sizeNo community building is recorded as progressed in the supplied RERA amenity data
Evidence sourceRERA amenities
Declared progress / verified statusCommunity buildings: 0% recorded

7. Utilities, building services & safety

The RERA amenity record marks water supply and rainwater harvesting as 100% available, and an electrical meter room/sub-station/receiving station as 100% available. The supplied record does not specify water source, storage or treatment capacity, nor electrical supply capacity or backup provision RERA amenities.

The approval documents require a rainwater-harvesting structure, a transformer and a garbage house within the premises; the municipality permit also refers to a percolation pit. These are approval conditions, not evidence that the facilities have been completed. RERA records sewerage, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, street lighting, energy management and fire-protection requirements at 0% RERA amenities.

The supplied documents do not establish lift or service-lift provision, lift capacity, fire-system specifications, escape-stair arrangement, CCTV, access control, accessibility features, or completed utility services. The municipality permit states that public water supply and electricity connections will be provided only on production of an occupancy certificate; the approval record also requires an occupancy certificate before occupation.

8. Location, access & connectivity

The RERA record places the project in NARSINGII, Ranga Reddy District, PIN 500075, and records a 12 MTS WIDE ROAD along the northern boundary. Approval materials identify plots Q-31 and Q-32 in Manchirevula-ORRGC Village RERA record RERA filing.

The supplied location dataset gives these measured distances from the project’s cadastral-parcel centroid: Financial District (Nanakramguda), 1.2 km; IndusInd Bank, 0.4 km; unnamed bus station, 2.2 km; Manuu Polytechnic Hyderabad, 1.6 km; Sankaraya Eye Hospital, 1.6 km; ADP, 0.0 km; South india shopping mall, 2.6 km; unnamed park, 1.2 km; and Nanakramguda Govt primary school, 0.5 km. No travel times or broader public-transport service details are supplied Location record.

9. Developer & development status

The registered promoter is ADHIRATH AND DHRITI DEVELOPERS AND BUILDERS PRIVATE LIMITED, a private limited company. The supplied corporate identifier is GSTIN 36AALCA8075B1ZN. The project record gives a promoter address at DD Colony, Manchiravula Village, Narsingii, Ranga Reddy, 500075; a separate verified registered-office address and official contact details are not provided Corporate record RERA filing.

The promoter’s Form B declaration records an undertaking to complete by 31 December 2022. The TG-RERA record gives original and revised completion dates of 30/06/2023 and reports 80% completeness. These are separate promoter/RERA record statements; the supplied evidence does not independently verify site progress or establish an occupancy certificate RERA record Document index.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400002921, issued 14/05/2021; valid to 30/06/2023
What the supplied record establishesFORM C registration for RADHA GOVINDA RESIDENCY; includes the separate-account condition
HMDA technical approval
Identifier / date037290/SKP/R1/U6/HMDA/10072020, dated 10/12/2020
What the supplied record establishesTechnical approval for the proposed 1Stilt + 5 residential building on plots Q-31 and Q-32; the record directs the applicant to obtain sanction/release from the Executive Authority
Narsingi Municipality building permit order
Identifier / dateBA.NO: 25/2020-21; file G1/4286/2020
What the supplied record establishesBuilding permit order for a 1Stilt +5 building on the stated 1,042.37 sq. m site, subject to conditions
Title-report documents filed with RERA
Identifier / dateDocuments 161901–161909
What the supplied record establishesSupplied title-report materials include a 2020 sale deed and development agreement-cum-GPA, earlier title/revenue materials and related records Document index
Form B declaration
Identifier / dateDocument 161995, verified 8 April 2021
What the supplied record establishesPromoter declaration and completion undertaking filed with the project record
Occupancy / completion certificate
Identifier / dateNot included in supplied documents
What the supplied record establishesNo certificate is established by the supplied project evidence Document index

Frequently asked questions

Is RADHA GOVINDA RESIDENCY registered with Telangana RERA?

Yes. RADHA GOVINDA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02400002921; the registration status is On-Going Project.

Who is the developer of RADHA GOVINDA RESIDENCY?

The promoter named in the RERA registration is ADHIRATH AND DHRITI DEVELOPERS AND BUILDERS PRIVATE LIMITED.

Where is RADHA GOVINDA RESIDENCY located?

RADHA GOVINDA RESIDENCY is in NARSINGII, Rangareddy, Telangana (500075).

When will RADHA GOVINDA RESIDENCY be completed?

The promoter's proposed date of completion filed with RERA is 30/06/2023. This is the promoter's declaration, not a guarantee.

More projects in Rangareddy