TECHPARK is a commercial project for a proposed commercial IT office building in Puppalguda, Gandipet Mandal, Ranga Reddy District. The registered promoter is Inspire Infra. The project covers 1,264.64 sq. m. and comprises one building with 2 Cellar + Ground + 4 Upper floors; the RERA unit entries have saleable areas ranging from 220.48 to 238.59 sq. m. It is registered under TG-RERA number P02400002418, with proposed completion on 31/10/2022.
More from Inspire Infra · 9 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | TECHPARK |
| Project type | Commercial; the RERA-filed project is described as a proposed commercial IT office building. RERA record |
| Phase / registered portion | One registered project/building is identified; no separate phase name is disclosed. The registration certificate identifies Survey No. 286. |
| TG-RERA registration | P02400002418; issued 17/12/2020; recorded validity 17/12/2020–31/10/2022. No extension is recorded in the supplied certificate data. |
| Registered promoter | Inspire Infra (also shown as M/s. INSPIRE INFRA); partnership. Corporate record |
| RERA status | New Project in the filing header. The certificate’s stated registration validity has ended; the separate completion and OC records are set out below. RERA record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / plots | Puppalguda; Plot Nos. 53, 54 and 55. RERA filing |
| Revenue village | Puppalguda (also rendered “Puppalguda-ORRcc” in the HMDA letter). RERA record |
| Mandal / district / PIN | Gandipet; Ranga Reddy; 500089. RERA record |
| Project survey number(s) | Survey No. 286; no subdivision is specified in the project identity or registration certificate. RERA filing |
| Registered site extent | 1,264.64 sq. m.; the RERA land-details fields give total area and net area as 1264.64 sq. m., with affected area recorded as 0. RERA filing |
| Boundaries in filing | East: Plot No. 56; West: Plot No. 52; North: Plot Nos. 45 and 46; South: 40 feet wide road. RERA filing |
Development identity
| Field | Record |
|---|---|
| Planning / technical authority | Hyderabad Metropolitan Development Authority (HMDA); the HMDA technical approval letter directs the applicant to obtain sanction and release from the local Executive Authority, identified as Manikonda Municipality in the approval record. Approvals record |
| Principal plan approval | 033719/SKP/C1/U6/HMD as filed; the HMDA technical approval letter is dated 07-Sep-2020. RERA filing Approvals record |
| Building use and configuration | Commercial IT office building; 2 Cellar + Ground + 4 Upper floors in the HMDA technical approval. |
| Approved built-up area | 3415.7 sq. m. in the RERA filing fields. The HMDA letter separately records “Total Built up Area (In Sq.mts) 3423.55”; the Overview does not treat these labels as interchangeable. RERA filing |
| Building count | One building/unit is stated in the RERA land-details fields. RERA filing |
| Parking / mortgage area | The HMDA letter says cellar and stilts approved for parking are to be used exclusively for parking. No parking-space count is supplied. The RERA fields record 347.48 sq. m. as mortgage area; the HMDA letter describes that area as mortgaged built-up space in two ground-floor offices in favour of the Metropolitan Commissioner, HMDA. RERA filing |
| Approved vs RERA-filed units | The RERA land-details fields state one total building unit and one proposed building unit. The unit table separately lists 19 unit entries; the supplied evidence does not explain this difference in counting scope. RERA filing RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed unit labels and size range | Entries are filed under office/unit labels including floors and “LAND OWNER” labels; the listed saleable areas range from 220.48 to 238.59 sq. m. RERA unit details RERA unit table |
| Booked / available | Portal-derived unit data shows 0 booked and 19 available. The source gives no as-of date, so these counts are indicative. RERA unit details RERA unit table |
| Construction progress | The RERA amenities table records 0% progress for its listed infrastructure/facility rows; this is a filed progress field, not independent site verification. RERA amenities |
| Completion dates | The header gives proposed completion 31/10/2022. The Form B declaration contains an OCR-truncated completion undertaking, so it does not provide a reliably readable separate date. RERA record |
| Occupancy certificate | An architect’s certificate records HMDA OC 000735/OC/HMDA/SKPTECHPARK 2022, dated 07-05-2022, and certifies overall project completion; the supplied record does not specify a separate tower or phase scope. |
2. The project story
TECHPARK is registered as a commercial project in Puppalguda, on Plot Nos. 53, 54 and 55 in Survey No. 286, Gandipet Mandal, Ranga Reddy District. Its filed land area is 1,264.64 sq. m. and its documented building purpose is a commercial IT office building. RERA record RERA filing
The HMDA technical approval describes a single building with two cellar levels, a ground floor and four upper floors. Its conditions state that the cellar and any approved stilt parking are to be used exclusively for vehicle parking.
The architect’s certificate records overall completion and an HMDA occupancy certificate dated 07-05-2022. This is documentary evidence of the certificate and the architect’s completion certification; it is not an independent site inspection.
The RERA unit table contains 19 entries and records 0 booked and 19 available, but does not supply a clear commercial-unit configuration description beyond the filed labels. The portal-derived counts have no stated “as of” date. The RERA amenities progress fields show 0% for listed items; those fields should not be read as an independently verified physical-progress assessment. RERA unit details RERA unit table RERA amenities
3. Master plan, architecture & building design
The RERA filing identifies a 1,264.64 sq. m. site and an approved built-up area of 3415.7 sq. m. The HMDA technical approval describes the building as 2 Cellar + Ground + 4 Upper floors, with a recorded height of 14.99 and “Total Built up Area (In Sq.mts) 3423.55.” The latter figure is presented under the HMDA letter’s own “Total Built up Area” label; it is not substituted for the filing’s approved built-up area. RERA filing RERA filing
The filing states one building unit. The supplied materials do not provide drawing-derived details on building footprint, office layout, floor-by-floor unit arrangement, lifts, stairs, entry/exit positions, circulation, landscaping area, or commercial versus common-area distribution. The floor-plan record says three drawings are pending scanning and none were measured; no software-measured carpet area or room dimensions are available. RERA filing Floor plans
The HMDA approval conditions mention a tot-lot, perimeter and frontage tree planting, a transformer space, a garbage house and rainwater-harvesting structure. These are approval conditions, not evidence in this pack that the facilities have been completed.
4. Homes, configurations & floor plans
The RERA filing lists 19 entries, but does not provide a clear standard commercial configuration. The entries below are preserved as filed rather than reclassified as verified office types. The saleable areas are RERA-filed; no measured carpet areas are available because the three drawings are pending scanning. RERA unit details RERA unit table Floor plans
| Units | 19 |
|---|---|
| Booked | 0 |
| Available | 19 |
| RERA saleable area | 220.48–238.59 sq. m. across the filed entries |
| Measured carpet area | Not available; drawings are pending scanning and no measurements were made |
| Loading (if supplied) | Not supplied |
The RERA unit data marks the three “G” entries as mortgaged; the other listed entries are not marked mortgaged in that unit table. The filing’s “LAND OWNER” labels are retained verbatim because the supplied record does not define their sale or allocation status. RERA unit table RERA unit details
Carpet area and saleable area are distinct measures: the latter may include a unit’s share of common areas, while carpet area concerns the usable internal area under the applicable measurement basis. No drawing-measured carpet figure or loading calculation is supplied here, so neither can be stated for this project. Floor plans RERA unit details
5. Parking & vehicle circulation
The HMDA technical approval states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The approval describes two cellar levels, but the supplied records do not state a parking-space count, type or allocation by unit.
The record does not establish resident or visitor parking numbers, accessible parking, two-wheeler spaces, mechanical parking, ramp or driveway arrangements, pedestrian separation, EV charging, or a unit-specific parking entitlement. A parking provision in the approval does not itself establish exclusive ownership or allocation to a purchaser. RERA filing
6. Amenities, recreation & open spaces
The RERA amenities table lists 14 infrastructure or facility categories. It records “YES” for water supply, sewerage, storm-water drains, rainwater conservation/harvesting and electrical meter room/sub-station/receiving station; progress is recorded as 0% for every listed row. Separately, the HMDA technical approval specifies facilities and conditions including a tot-lot, tree planting, transformer space, garbage house and rainwater harvesting. The records do not independently verify completion of these items. RERA amenities
| Description / size | Size/details not supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | RERA table says “YES”; source/capacity not stated |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | RERA table says “YES” for “Sewerage (Chamber, Lines, Septic Tank, STP)”; specific system/capacity not identified |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | Details not supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | HMDA approval calls for a fenced tot-lot maintained as greenery and tree planting along the periphery and in front of the premises; no area stated |
|---|---|
| Evidence source | RERA amenities table; HMDA technical approval |
| Declared progress / verified status | RERA table: 0%; completion not independently verified RERA amenities |
| Description / size | Details not supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | No type or size supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | No treatment method or capacity supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | HMDA approval also requires a garbage house within the premises; size/details not supplied |
|---|---|
| Evidence source | RERA amenities table; HMDA technical approval |
| Declared progress / verified status | RERA table: 0%; completion not independently verified RERA amenities |
| Description / size | HMDA approval calls for a rainwater-harvesting structure (percolation pit); size/capacity not stated |
|---|---|
| Evidence source | RERA amenities table; HMDA technical approval |
| Declared progress / verified status | RERA table: 0%; completion not independently verified RERA amenities |
| Description / size | Details not supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
| Description / size | No system or equipment details supplied in the amenities table |
|---|---|
| Evidence source | RERA amenities table; municipal permission conditions |
| Declared progress / verified status | RERA table: 0%; completion not independently verified RERA amenities |
| Description / size | RERA table says “YES”; HMDA approval requires space for a transformer |
|---|---|
| Evidence source | RERA amenities table; HMDA technical approval |
| Declared progress / verified status | RERA table: 0%; completion not independently verified RERA amenities |
| Description / size | Area/details not supplied |
|---|---|
| Evidence source | RERA amenities table |
| Declared progress / verified status | 0%; not independently verified RERA amenities |
7. Utilities, building services & safety
The RERA amenities record marks water supply, sewerage, storm-water drainage, rainwater conservation/harvesting and electrical meter room/sub-station/receiving station as “YES,” while showing 0% progress for those rows. The supplied records do not give water source or storage capacity, treatment plant capacity, reuse arrangements, storm-water design, electrical load, backup generation, or utility completion status. RERA amenities
The HMDA technical approval requires a transformer space, garbage house and rainwater-harvesting structure. It also requires services such as sanitation, plumbing, fire safety, lifts and electrical installations to be executed under qualified technical personnel, and includes worker-safety and construction-insurance conditions. These are stated approval conditions; the supplied evidence does not establish that each service has been installed or that the conditions have been independently inspected as satisfied.
The Manikonda Municipality permission calls for fire-service clearance before applying for the occupancy certificate. The architect’s certificate records an HMDA occupancy certificate, but no separate fire-clearance document is included in the supplied overview evidence. The records do not specify lift count or capacity, fire-system equipment, escape-stair details, CCTV, access-control arrangements, waste segregation, or accessible circulation.
8. Location, access & connectivity
The registered location is Puppalguda, Gandipet Mandal, Ranga Reddy District, PIN 500089; the site is identified in the filing as Plot Nos. 53, 54 and 55 in Survey No. 286. The south boundary is recorded as a 40 feet wide road. RERA record RERA filing
The supplied location data gives these measured distances from its location record: Sankaraya Eye Hospital 0.4 km, an unnamed park 0.4 km, Keystone International School 1.3 km, ADP 1.6 km, ICICI Bank 1.7 km, Financial District (Nanakramguda) 2.0 km, and Holy Mary College 2.4 km. The record does not identify public-transport services, named approach roads beyond the boundary road, or travel times. Location record
9. Developer & development status
The registered promoter is INSPIRE INFRA, recorded as a partnership. The supplied corporate identifier is GSTIN 36AAGFI2208C1ZX. The promoter address recorded in the project data is CHALLAS MY SPACE III, IIIA, ROAD NO 15, FUTURE KIDS SCHOOL STREET, PUPPALGUDA, Gandipet, Ranga Reddy, 500089. The supplied official website is inspireinfra.in; no project-specific email or phone number is provided. Corporate record RERA record Promoter website
The project record names Srinivasa Reddy Bonam as authorized signatory and Vijayalakshmi Bonam as partner. The project data identifies 12 RERA landowners under area-share agreements. Parties record
The RERA header gives proposed completion as 31/10/2022. A separate architect’s certificate dated 14-10-2024 certifies overall project completion and records HMDA occupancy certificate 000735/OC/HMDA/SKPTECHPARK 2022, dated 07-05-2022. These are the completion and certificate records supplied; no separate construction-progress inspection is included. RERA record
10. Approvals, official records & documents
| Identifier / date | P02400002418; issued 17/12/2020; valid to 31/10/2022 |
|---|---|
| Scope and evidence | Form C for TECHPARK, Inspire Infra, Survey No. 286, Plot Nos. 53, 54 and 55. |
| Identifier / date | Filed plan approval number 033719/SKP/C1/U6/HMD; letter dated 07-Sep-2020 |
|---|---|
| Scope and evidence | Proposed commercial IT office building; two cellar levels, ground and four upper floors. The letter directs the applicant to obtain sanction and release from the local Executive Authority. Approvals record |
| Identifier / date | Proceedings number is OCR-rendered as “MCIMNKITPI ll lzOzo-zozt”; dated 2020 in the supplied record |
|---|---|
| Scope and evidence | Municipal construction permission record for Plot Nos. 53, 54 and 55, Survey No. 286, describing two cellars, ground and four upper floors. Approvals record |
| Identifier / date | 000735/OC/HMDA/SKPTECHPARK 2022; 07-05-2022 |
|---|---|
| Scope and evidence | Recorded in the architect’s certificate for TECHPARK, RERA No. P02400002418; the certificate states overall completion. |
| Identifier / date | Declaration date is OCR-rendered and not reliably readable |
|---|---|
| Scope and evidence | Includes promoter declarations about title, encumbrances, completion undertaking and RERA account requirements; the declarant and completion text are partly illegible/truncated. |
| Identifier / date | Portal-derived; capture/as-of date not stated for unit counts |
|---|---|
| Scope and evidence | Records 19 unit entries and amenities/progress fields; counts are indicative, and listed amenity progress is recorded as 0%. RERA unit details RERA unit table RERA amenities |
The HMDA technical approval includes conditions concerning parking use, tot-lot, tree planting, rainwater harvesting, transformer space, a garbage house, building services, safety and occupancy certification. The full conditions are not reproduced here; the approval letter is the cited record.
1. Project at a glance
Project identity
Registered project name: TECHPARK
Project type: Commercial; the RERA-filed project is described as a proposed commercial IT office building.
Phase / registered portion: One registered project/building is identified; no separate phase name is disclosed. The registration certificate identifies Survey No. 286.
TG-RERA registration: P02400002418; issued 17/12/2020; recorded validity 17/12/2020–31/10/2022. No extension is recorded in the supplied certificate data.
Registered promoter: Inspire Infra (also shown as M/s. INSPIRE INFRA); partnership.
RERA status: New Project in the filing header. The certificate’s stated registration validity has ended; the separate completion and OC records are set out below.
Land and geographic identity
Locality / plots: Puppalguda; Plot Nos. 53, 54 and 55.
Revenue village: Puppalguda (also rendered “Puppalguda-ORRcc” in the HMDA letter).
Mandal / district / PIN: Gandipet; Ranga Reddy; 500089.
Project survey number(s): Survey No. 286; no subdivision is specified in the project identity or registration certificate.
Registered site extent: 1,264.64 sq. m.; the RERA land-details fields give total area and net area as 1264.64 sq. m., with affected area recorded as 0.
Boundaries in filing: East: Plot No. 56; West: Plot No. 52; North: Plot Nos. 45 and 46; South: 40 feet wide road.
Development identity
Planning / technical authority: Hyderabad Metropolitan Development Authority (HMDA); the HMDA technical approval letter directs the applicant to obtain sanction and release from the local Executive Authority, identified as Manikonda Municipality in the approval record.
Principal plan approval: 033719/SKP/C1/U6/HMD as filed; the HMDA technical approval letter is dated 07-Sep-2020.
Building use and configuration: Commercial IT office building; 2 Cellar + Ground + 4 Upper floors in the HMDA technical approval.
Approved built-up area: 3415.7 sq. m. in the RERA filing fields. The HMDA letter separately records “Total Built up Area (In Sq.mts) 3423.55”; the Overview does not treat these labels as interchangeable.
Building count: One building/unit is stated in the RERA land-details fields.
Parking / mortgage area: The HMDA letter says cellar and stilts approved for parking are to be used exclusively for parking. No parking-space count is supplied. The RERA fields record 347.48 sq. m. as mortgage area; the HMDA letter describes that area as mortgaged built-up space in two ground-floor offices in favour of the Metropolitan Commissioner, HMDA.
Approved vs RERA-filed units: The RERA land-details fields state one total building unit and one proposed building unit. The unit table separately lists 19 unit entries; the supplied evidence does not explain this difference in counting scope.
Offering and status
RERA-filed unit labels and size range: Entries are filed under office/unit labels including floors and “LAND OWNER” labels; the listed saleable areas range from 220.48 to 238.59 sq. m.
Booked / available: Portal-derived unit data shows 0 booked and 19 available. The source gives no as-of date, so these counts are indicative.
Construction progress: The RERA amenities table records 0% progress for its listed infrastructure/facility rows; this is a filed progress field, not independent site verification.
Completion dates: The header gives proposed completion 31/10/2022. The Form B declaration contains an OCR-truncated completion undertaking, so it does not provide a reliably readable separate date.
Occupancy certificate: An architect’s certificate records HMDA OC 000735/OC/HMDA/SKPTECHPARK 2022, dated 07-05-2022, and certifies overall project completion; the supplied record does not specify a separate tower or phase scope.
2. The project story
TECHPARK is registered as a commercial project in Puppalguda, on Plot Nos. 53, 54 and 55 in Survey No. 286, Gandipet Mandal, Ranga Reddy District. Its filed land area is 1,264.64 sq. m. and its documented building purpose is a commercial IT office building.
The HMDA technical approval describes a single building with two cellar levels, a ground floor and four upper floors. Its conditions state that the cellar and any approved stilt parking are to be used exclusively for vehicle parking.
The architect’s certificate records overall completion and an HMDA occupancy certificate dated 07-05-2022. This is documentary evidence of the certificate and the architect’s completion certification; it is not an independent site inspection.
The RERA unit table contains 19 entries and records 0 booked and 19 available, but does not supply a clear commercial-unit configuration description beyond the filed labels. The portal-derived counts have no stated “as of” date. The RERA amenities progress fields show 0% for listed items; those fields should not be read as an independently verified physical-progress assessment.
3. Master plan, architecture & building design
The RERA filing identifies a 1,264.64 sq. m. site and an approved built-up area of 3415.7 sq. m. The HMDA technical approval describes the building as 2 Cellar + Ground + 4 Upper floors, with a recorded height of 14.99 and “Total Built up Area (In Sq.mts) 3423.55.” The latter figure is presented under the HMDA letter’s own “Total Built up Area” label; it is not substituted for the filing’s approved built-up area.
The filing states one building unit. The supplied materials do not provide drawing-derived details on building footprint, office layout, floor-by-floor unit arrangement, lifts, stairs, entry/exit positions, circulation, landscaping area, or commercial versus common-area distribution. The floor-plan record says three drawings are pending scanning and none were measured; no software-measured carpet area or room dimensions are available.
The HMDA approval conditions mention a tot-lot, perimeter and frontage tree planting, a transformer space, a garbage house and rainwater-harvesting structure. These are approval conditions, not evidence in this pack that the facilities have been completed.
4. Homes, configurations & floor plans
The RERA filing lists 19 entries, but does not provide a clear standard commercial configuration. The entries below are preserved as filed rather than reclassified as verified office types. The saleable areas are RERA-filed; no measured carpet areas are available because the three drawings are pending scanning.
| Units | 19 |
|---|---|
| Booked | 0 |
| Available | 19 |
| RERA saleable area | 220.48–238.59 sq. m. across the filed entries |
| Measured carpet area | Not available; drawings are pending scanning and no measurements were made |
| Loading (if supplied) | Not supplied |
The RERA unit data marks the three “G” entries as mortgaged; the other listed entries are not marked mortgaged in that unit table. The filing’s “LAND OWNER” labels are retained verbatim because the supplied record does not define their sale or allocation status.
Carpet area and saleable area are distinct measures: the latter may include a unit’s share of common areas, while carpet area concerns the usable internal area under the applicable measurement basis. No drawing-measured carpet figure or loading calculation is supplied here, so neither can be stated for this project.
5. Parking & vehicle circulation
The HMDA technical approval states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The approval describes two cellar levels, but the supplied records do not state a parking-space count, type or allocation by unit.
The record does not establish resident or visitor parking numbers, accessible parking, two-wheeler spaces, mechanical parking, ramp or driveway arrangements, pedestrian separation, EV charging, or a unit-specific parking entitlement. A parking provision in the approval does not itself establish exclusive ownership or allocation to a purchaser.
6. Amenities, recreation & open spaces
The RERA amenities table lists 14 infrastructure or facility categories. It records “YES” for water supply, sewerage, storm-water drains, rainwater conservation/harvesting and electrical meter room/sub-station/receiving station; progress is recorded as 0% for every listed row. Separately, the HMDA technical approval specifies facilities and conditions including a tot-lot, tree planting, transformer space, garbage house and rainwater harvesting. The records do not independently verify completion of these items.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | Size/details not supplied | RERA amenities table | 0%; not independently verified |
| Water supply | RERA table says “YES”; source/capacity not stated | RERA amenities table | 0%; not independently verified |
| Sewerage | RERA table says “YES” for “Sewerage (Chamber, Lines, Septic Tank, STP)”; specific system/capacity not identified | RERA amenities table | 0%; not independently verified |
| Storm-water drains | Details not supplied | RERA amenities table | 0%; not independently verified |
| Green strip / tot lot / park | HMDA approval calls for a fenced tot-lot maintained as greenery and tree planting along the periphery and in front of the premises; no area stated | RERA amenities table; HMDA technical approval | RERA table: 0%; completion not independently verified |
| Street lighting | Details not supplied | RERA amenities table | 0%; not independently verified |
| Community buildings | No type or size supplied | RERA amenities table | 0%; not independently verified |
| Sewage / sullage treatment and disposal | No treatment method or capacity supplied | RERA amenities table | 0%; not independently verified |
| Solid-waste management and disposal | HMDA approval also requires a garbage house within the premises; size/details not supplied | RERA amenities table; HMDA technical approval | RERA table: 0%; completion not independently verified |
| Water conservation / rainwater harvesting | HMDA approval calls for a rainwater-harvesting structure (percolation pit); size/capacity not stated | RERA amenities table; HMDA technical approval | RERA table: 0%; completion not independently verified |
| Energy management | Details not supplied | RERA amenities table | 0%; not independently verified |
| Fire protection and fire safety | No system or equipment details supplied in the amenities table | RERA amenities table; municipal permission conditions | RERA table: 0%; completion not independently verified |
| Electrical meter room / sub-station / receiving station | RERA table says “YES”; HMDA approval requires space for a transformer | RERA amenities table; HMDA technical approval | RERA table: 0%; completion not independently verified |
| Recreational open space | Area/details not supplied | RERA amenities table | 0%; not independently verified |
7. Utilities, building services & safety
The RERA amenities record marks water supply, sewerage, storm-water drainage, rainwater conservation/harvesting and electrical meter room/sub-station/receiving station as “YES,” while showing 0% progress for those rows. The supplied records do not give water source or storage capacity, treatment plant capacity, reuse arrangements, storm-water design, electrical load, backup generation, or utility completion status.
The HMDA technical approval requires a transformer space, garbage house and rainwater-harvesting structure. It also requires services such as sanitation, plumbing, fire safety, lifts and electrical installations to be executed under qualified technical personnel, and includes worker-safety and construction-insurance conditions. These are stated approval conditions; the supplied evidence does not establish that each service has been installed or that the conditions have been independently inspected as satisfied.
The Manikonda Municipality permission calls for fire-service clearance before applying for the occupancy certificate. The architect’s certificate records an HMDA occupancy certificate, but no separate fire-clearance document is included in the supplied overview evidence. The records do not specify lift count or capacity, fire-system equipment, escape-stair details, CCTV, access-control arrangements, waste segregation, or accessible circulation.
8. Location, access & connectivity
The registered location is Puppalguda, Gandipet Mandal, Ranga Reddy District, PIN 500089; the site is identified in the filing as Plot Nos. 53, 54 and 55 in Survey No. 286. The south boundary is recorded as a 40 feet wide road.
The supplied location data gives these measured distances from its location record: Sankaraya Eye Hospital 0.4 km, an unnamed park 0.4 km, Keystone International School 1.3 km, ADP 1.6 km, ICICI Bank 1.7 km, Financial District (Nanakramguda) 2.0 km, and Holy Mary College 2.4 km. The record does not identify public-transport services, named approach roads beyond the boundary road, or travel times.
9. Developer & development status
The registered promoter is INSPIRE INFRA, recorded as a partnership. The supplied corporate identifier is GSTIN 36AAGFI2208C1ZX. The promoter address recorded in the project data is CHALLAS MY SPACE III, IIIA, ROAD NO 15, FUTURE KIDS SCHOOL STREET, PUPPALGUDA, Gandipet, Ranga Reddy, 500089. The supplied official website is inspireinfra.in; no project-specific email or phone number is provided.
The project record names Srinivasa Reddy Bonam as authorized signatory and Vijayalakshmi Bonam as partner. The project data identifies 12 RERA landowners under area-share agreements.
The RERA header gives proposed completion as 31/10/2022. A separate architect’s certificate dated 14-10-2024 certifies overall project completion and records HMDA occupancy certificate 000735/OC/HMDA/SKPTECHPARK 2022, dated 07-05-2022. These are the completion and certificate records supplied; no separate construction-progress inspection is included.
10. Approvals, official records & documents
| Identifier / date | P02400002418; issued 17/12/2020; valid to 31/10/2022 |
|---|---|
| Scope and evidence | Form C for TECHPARK, Inspire Infra, Survey No. 286, Plot Nos. 53, 54 and 55. |
| Identifier / date | Filed plan approval number 033719/SKP/C1/U6/HMD; letter dated 07-Sep-2020 |
|---|---|
| Scope and evidence | Proposed commercial IT office building; two cellar levels, ground and four upper floors. The letter directs the applicant to obtain sanction and release from the local Executive Authority. |
| Identifier / date | Proceedings number is OCR-rendered as “MCIMNKITPI ll lzOzo-zozt”; dated 2020 in the supplied record |
|---|---|
| Scope and evidence | Municipal construction permission record for Plot Nos. 53, 54 and 55, Survey No. 286, describing two cellars, ground and four upper floors. |
| Identifier / date | 000735/OC/HMDA/SKPTECHPARK 2022; 07-05-2022 |
|---|---|
| Scope and evidence | Recorded in the architect’s certificate for TECHPARK, RERA No. P02400002418; the certificate states overall completion. |
| Identifier / date | Declaration date is OCR-rendered and not reliably readable |
|---|---|
| Scope and evidence | Includes promoter declarations about title, encumbrances, completion undertaking and RERA account requirements; the declarant and completion text are partly illegible/truncated. |
| Identifier / date | Portal-derived; capture/as-of date not stated for unit counts |
|---|---|
| Scope and evidence | Records 19 unit entries and amenities/progress fields; counts are indicative, and listed amenity progress is recorded as 0%. |
The HMDA technical approval includes conditions concerning parking use, tot-lot, tree planting, rainwater harvesting, transformer space, a garbage house, building services, safety and occupancy certification. The full conditions are not reproduced here; the approval letter is the cited record.
Frequently asked questions
Is TECHPARK registered with Telangana RERA?
Yes. TECHPARK is registered with the Telangana Real Estate Regulatory Authority as P02400002418; the registration status is New Project.
Who is the developer of TECHPARK?
The promoter named in the RERA registration is INSPIRE INFRA.
Where is TECHPARK located?
TECHPARK is in PUPPALGUDA, Gandipet, Rangareddy, Telangana (500089).
When will TECHPARK be completed?
The promoter's proposed date of completion filed with RERA is 31/10/2022. This is the promoter's declaration, not a guarantee.