Sign in

Shantiniketan

VIJETHA DHANALAXMI PROJECTS · Rangareddy · RERA P02400002977

SHANTINIKETAN is a residential apartment project in ERSTWHILE HYDERABAD AIRPORT DEVELOPMENT AUTHORITY (HADA), MANNA GUDA, Abdullapurmet, Ranga Reddy. The registered promoter is VIJETHA DHANALAXMI PROJECTS, partnership. The RERA filing records a site area of 2780.42 sqmts, one proposed building and 60 apartments, with 2BHK and 3BHK configurations; the HMDA extract describes 1Cellar + 1Stilt + 5 Upper floors. Its TG-RERA registration is P02400002977, and the proposed completion date is 31/12/2024.

More from Vijetha Dhana Laxmi Projects · 2 projects →

01What we found

Period endedTG-RERA registration ran to 31 Dec 2024 - check its extension on TG-RERA
12documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Developer renderProject photo
▦ View all 2 photos
Manna Guda, Abdullapurmet, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

FieldRecord
Registered project nameSHANTINIKETAN RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionPhase is not separately identified; the RERA filing records one proposed building. RERA filing
TG-RERA registrationP02400002977; Form C issued 20/05/2021.
Registration validity20/05/2021–31/12/2024; certificate states three years and no extension is recorded in the supplied certificate data. Registration validity is distinct from the completion undertaking and occupancy-certificate status.
Registered promoterVIJETHA DHANALAXMI PROJECTS, partnership. RERA record RERA filing
RERA status in supplied recordThe project is identified as “New Project”; the certificate records registration through 31/12/2024. The supplied record does not establish a current registration status after that date. RERA record

Land and geographic identity

FieldRecord
Locality / revenue villageRERA filing locality: ERSTWHILE HYDERABAD AIRPORT DEVELOPMENT AUTHORITY (HADA); revenue village: MANNA GUDA. The HMDA technical approval names Manneguda. RERA record RERA filing
Mandal / district / PINAbdullapurmet / Ranga Reddy / 501510. RERA record RERA filing
Project survey numbersSurvey Nos. 46 and 52; no project subdivision is specified in the RERA filing or supplied approval extract. RERA filing
Site extentRERA filing: total area 2780.42 sqmts and net area 2780.42 sqmts. HMDA technical-approval extract separately states an extent of 2,281.06 Sq. Mt. RERA filing
Boundaries (RERA-filed)East: CTS NO; west: PLOT NO 1 TO 6; north: ROAD WIDTH - 9; south: PLOT NO32 AND 46. RERA filing

Development identity

FieldRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) technical approval; the document states that building plans are to be sanctioned by the Executive Authority.
Principal approval020433/GHT/R1/U6/HMDA/15022019, approved date recorded as 16/04/2021. The RERA filing lists plan approval number 020433/GHT/R1/U6/HM. Approvals record
Approved built-up areaRERA filing: 6885.47 sqmts. The HMDA technical-approval extract separately lists “Built up Area 6706.35” and “Total Built up Area (In Sq.mts) 8921.27”; these labels are retained as recorded, not treated as interchangeable. RERA filing
Buildings / sanctioned floorsOne proposed building is recorded in the RERA filing. HMDA extract describes A (PROPOSED) as 1Cellar + 1Stilt + 5 Upper floors. RERA filing
Parking levels / provisionOne cellar and one stilt are shown in the floor configuration. A parking count or parking-allocation schedule is not supplied.
Unit countRERA filing: 60 total units; the supplied approval extract does not state an approved unit count. RERA unit table RERA filing

Offering and status

FieldRecord
Unit types2BHK and 3BHK apartments. RERA unit table
RERA-filed saleable areas2BHK: 58.0 sqm; 3BHK: 153.0 sqm. RERA unit table
Booked / availablePortal snapshot reports 0 booked and 60 available (50 2BHK and 10 3BHK); the portal record has no as-of date, so counts are indicative. RERA unit table
Completion datesRERA project information gives proposed completion 31/12/2024. A Form B declaration dated 5 May 2020 states the promoter’s completion undertaking as 15/04/2026. These are recorded as separate filed statements. RERA filing
Construction stageNo construction-progress percentage or independently verified site-stage evidence is supplied. Document index RERA amenities
Occupancy / completion certificateNo occupancy or completion certificate is supplied in the reviewed documents. The HMDA approval makes an occupancy certificate compulsory before occupation.

2. The project story

SHANTINIKETAN is a residential apartment project registered with TG-RERA as P02400002977, on land identified in the filing as Survey Nos. 46 and 52 at MANNA GUDA, Abdullapurmet, Ranga Reddy. The filing describes one building and 60 apartments, comprising 50 2BHK and 10 3BHK units. RERA record RERA filing RERA unit table

HMDA’s technical-approval extract describes a proposed residential building with one cellar, one stilt and five upper floors. The supplied material does not establish how many apartments are on each floor, the present construction stage, or whether any portion is complete or occupied. The portal’s unit availability is an undated record and is not evidence of current sales or construction progress. RERA unit table

The project has a RERA-filed completion date of 31/12/2024, while a Form B declaration contains a separate promoter completion undertaking of 15/04/2026. The registration certificate records validity through 31/12/2024. These dates describe different recorded matters; the supplied material does not establish an extension, completion, or occupancy certification. RERA filing

3. Master plan, architecture & building design

The RERA filing records a site area of 2780.42 sqmts, with the same figure as net area, and an approved built-up area of 6885.47 sqmts. The HMDA technical-approval extract gives a site extent of 2,281.06 Sq. Mt. and separately records “Built up Area 6706.35” and “Total Built up Area (In Sq.mts) 8921.27.” These figures are reported with their source labels; no FSI-counted area or carpet-area schedule is supplied. RERA filing RERA filing

The RERA filing records one building. The HMDA extract identifies it as A (PROPOSED), with 1Cellar + 1Stilt + 5 Upper floors. The supplied extracts do not describe building footprint, flats per floor, lifts, stairs, entrances, internal circulation, landscaping, or residential/common-area distribution. RERA filing

The HMDA document lists a “Tot-lot” among the amenities/utilities and requires rainwater-harvesting structures, a transformer and garbage house, and an STP. The supplied drawings and extracts do not provide their locations, sizes or detailed layouts.

4. Homes, configurations & floor plans

The unit figures and saleable areas below are TG-RERA filing data. The available floor-plan record says two drawings are present, but none has been measured; no drawing-based carpet or room dimensions are available. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK5005058.0 sqmNot measuredNot supplied
3BHK10010153.0 sqmNot measuredNot supplied

The portal booking/availability counts are indicative because no as-of date is provided. The saleable areas above are RERA-filed figures; the supplied records do not provide a carpet-area figure or a loading calculation. RERA unit table Floor plans

5. Parking & vehicle circulation

The HMDA technical approval describes one cellar and one stilt, but the supplied extracts do not specify parking-space counts, parking types, visitor or accessible spaces, ramps, vehicle entries/exits, EV charging, or an allocation of spaces to individual apartments. A parking count or exclusive unit entitlement therefore cannot be established from this record. Document index

6. Amenities, recreation & open spaces

TG-RERA amenity fields mark several facilities as available in the filing, while progress percentages shown in the supplied amenity record are 0. These entries are not independent confirmation that facilities have been built or are operational. The HMDA technical-approval extract also lists certain required or provided features, as noted below. RERA amenities

Internal Roads & Footpaths
Description / sizeSize not supplied
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Green Strip/TOT LOT/Park
Description / sizeSize not supplied; HMDA extract lists “Tot-lot”
Evidence sourceRERA amenity record RERA amenities; HMDA technical approval
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Community Buildings
Description / sizeSize or use not specified
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Water Supply
Description / sizeSource and capacity not specified
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Sewerage (Chamber, Lines, Septic Tank, STP)
Description / sizeCapacity not supplied; HMDA extract requires an STP
Evidence sourceRERA amenity record RERA amenities; HMDA technical approval
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Treatment and disposal of sewage and sullage water
Description / sizeDetails/capacity not supplied
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Water conservation / rainwater harvesting
Description / sizeHMDA extract requires rainwater-harvesting structures; size/capacity not supplied
Evidence sourceRERA amenity record RERA amenities; HMDA technical approval
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified
Storm-water drains
Description / sizeDetails not supplied
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusProgress 0%; provision/completion not independently verified
Solid waste management and disposal
Description / sizeDetails not supplied; HMDA extract requires a garbage house
Evidence sourceRERA amenity record RERA amenities; HMDA technical approval
Declared progress / verified statusProgress 0%; provision/completion not independently verified
Street lighting
Description / sizeDetails not supplied
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusListed “YES”; progress 0%; completion not independently verified

7. Utilities, building services & safety

The RERA amenity record lists water supply, sewerage, sewage treatment, water conservation/rainwater harvesting, and street lighting, without capacities or detailed system designs. HMDA’s technical-approval conditions call for rainwater-harvesting structures, a transformer, a garbage house within the premises, and an STP. These are recorded provisions or requirements; the supplied evidence does not verify installation or operation. RERA amenities

The amenity record also includes fire protection and fire-safety requirements and electrical meter room/sub-station/receiving station, but shows no progress percentage beyond 0 and provides no equipment specifications, capacity or completion evidence. No lift details, backup-power provision, accessibility information, CCTV or security arrangements are supplied. RERA amenities

8. Location, access & connectivity

The registered location is MANNA GUDA, Abdullapurmet Mandal, Ranga Reddy District, PIN 501510. The filing also identifies the locality as “ERSTWHILE HYDERABAD AIRPORT DEVELOPMENT AUTHORITY (HADA).” A supplied geocode identifies Abdullapurmet mandal, Ranga Reddy, Telangana. RERA record RERA filing Location record

The location dataset reports these approximate distances:

Reference pointSupplied distance
Outer Ring Road (nearest sampled interchange, approx)7.7 km
HDFC Bank1.5 km
Brilliant Group of Institutions1.5 km
Urban Primary Health Centre Abdullapur1.1 km
Shiva Gardens1.2 km
ZPHS School0.9 km

These are supplied location-dataset distances; no travel times, public-transport details or approach-road descriptions are provided. Location record

9. Developer & development status

The registered promoter is VIJETHA DHANALAXMI PROJECTS, recorded as a partnership, with GSTIN 36AARFV2282N1ZC. The project filing lists the promoter address as #12-1-520 GSI ROAD, BANDLAGUDA, ERSTWHILE HYDERABAD AIRPORT DEVELOPMENT AUTHORITY (HADA), Abdullapurmet, Ranga Reddy, PIN 501510. RERA record RERA filing RERA filing Corporate record

The RERA certificate gives a promoter-office address at Village Nagole, Mandal Uppal, Medchal-Malkajgiri, PIN 500068. The supplied record does not provide official contact details.

A Form B dated 5 May 2020 is made by CHEEDALLA VIVEK SAI and names M/s. VIJETHA INFRA PROJECTS; it includes a completion undertaking of 15/04/2026. The record does not identify this declaration’s named entity as the registered promoter in the project identity fields. RERA record

No construction-progress percentage, independently verified site status, or occupancy/completion certificate is supplied. The RERA filing records 31/12/2024 as the proposed completion date, and the Form B records the separate undertaking noted above. RERA filing Document index

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C for SHANTINIKETAN, registration P02400002977, issued 20/05/2021; validity stated through 31/12/2024.
Principal building approvalHMDA technical approval 020433/GHT/R1/U6/HMDA/15022019, recorded approved date 16/04/2021; proposed building configuration is set out in the approval extract.
Commencement / building-plan documentFiled under “Commencement Certificates for each building in each phase”; the supplied extraction describes HMDA technical approval and associated conditions.
Layout planRERA filing requests a layout approval or approved layout plan; the supplied document entry is not extracted.
Form B declarationDeclaration dated 5 May 2020, with title, encumbrance, separate-account and completion statements attributed to its declarant.
Title and encumbrance materialsRERA-filed title report and encumbrance statement are available as documents; their detailed assessment belongs in the title and encumbrance sections.
Occupancy / completion certificateNone is supplied in the reviewed project documents. The HMDA approval states that an occupancy certificate is compulsory before occupation.
Environmental clearance searchThe shared record reports no environmental-clearance result found in a promoter-name search; it is not a project-specific clearance determination. Regulatory record

Frequently asked questions

Is SHANTINIKETAN registered with Telangana RERA?

Yes. SHANTINIKETAN is registered with the Telangana Real Estate Regulatory Authority as P02400002977; the registration status is New Project.

Who is the developer of SHANTINIKETAN?

The promoter named in the RERA registration is VIJETHA DHANALAXMI PROJECTS.

Where is SHANTINIKETAN located?

SHANTINIKETAN is in ERSTWHILE HYDERABAD AIRPORT DEVELOPMENT AUTHORITY (HADA), MANNA GUDA, Abdullapurmet, Rangareddy, Telangana (501510).

When will SHANTINIKETAN be completed?

The promoter's proposed date of completion filed with RERA is 31/12/2024. This is the promoter's declaration, not a guarantee.