Sai Chandra Hill Ridge
APURVA CONSTRUCTIONS · Rangareddy · RERA P02400002179
SAI CHANDRA HILL RIDGE is a residential apartment project in Puppalguda, Gandipet Mandal, Ranga Reddy District, developed by registered promoter APURVA CONSTRUCTIONS. The project occupies 836.54 sq. m. and comprises one proposed residential building with 1 Cellar + 1 Stilt + 5 Upper floors and 15 apartments, all 3BHK. Its TG-RERA registration number is P02400002179, and the stated proposed completion date is 09-05-2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SAI CHANDRA HILL RIDGE RERA record |
| Project type / registered portion | Residential apartment project; one building is identified in the filed land details. No separate phase name or phase number is disclosed. RERA record RERA filing |
| TG-RERA registration | P02400002179 |
| Registration validity | Certificate states four years, from 30/10/2020 to 09/05/2025; it records no extension. This is the registration period, not an occupancy certificate or completion confirmation. |
| Registered promoter | APURVA CONSTRUCTIONS; the filing identifies its organization type as Partnership. RERA record RERA filing Corporate record |
| RERA status | The supplied certificate establishes registration and its stated validity period. Current registration status after 09/05/2025 is not established by the supplied record. |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Puppalguda; locality is also recorded as puppalguda. RERA record RERA filing |
| Mandal / district / PIN | Gandipet / Ranga Reddy / 500089. RERA record RERA filing |
| Project survey identity | Survey No. 106/1 Part; the HMDA technical approval also identifies 106/1 PART. No other project survey subdivision is stated in the supplied project filing. RERA record |
| Site extent | 836.54 sq. m. is stated in the filed land details and HMDA technical approval. The RERA land form records total area 836.54 sq. m., affected area 0, and net area 836.54 sq. m. RERA filing |
| Boundaries | North: 40 Feet Wide Road; South: Plot No. 14 and 15, Block G; East: Plot No. 5, Block G; West: Plot No. 8, Block G. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority / approval | Hyderabad Metropolitan Development Authority (HMDA); approval no. 019452/SKP/R1/U6/HMDA/22012019, dated 09/05/2019. The document describes technical approval and states that building plans are to be sanctioned by the Executive Authority in conformity with those plans. Approvals record |
| Building and floors | One proposed residential building; filed technical approval describes 1 Cellar + 1 Stilt + 5 Upper floors. RERA filing |
| Approved area figures | HMDA approval lists “Built up Area 1968.8,” “Total Built up Area (In Sq.mts) 1968.8,” and “Proposed Built-up Area 2286.75.” These are reproduced as separately labelled in the approval; the supplied record does not explain the distinction. |
| Mortgage area | RERA land details state 210.62 sq. m.; the HMDA approval records 210.62 sq. m. as mortgaged built-up area. RERA filing |
| Units | RERA filing: 15 units, all 3BHK. The filed land details separately state one total building unit and one proposed building unit; the supplied data does not explain that field’s relationship to the 15 apartment units. RERA unit table RERA filing |
| Parking | HMDA technical approval states the cellar/stilt should be used exclusively for vehicle parking. A sanctioned parking-space count and unit-wise allocation are not supplied. |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed offering | 15 × 3BHK apartments; filed saleable area is 99.86 sq. m. per unit. The filing records 0 booked and 15 available, but gives no as-of date, so these counts are indicative only. RERA unit table RERA unit details |
| Construction stage | Current construction progress is not established by the supplied records. The RERA registration certificate records the project’s registration period, not construction completion. |
| Completion date | Form B promoter declaration states a project completion period of 09-05-2025. |
| Occupancy / completion certificate | No occupancy certificate or completion certificate is supplied. Its status for this building is therefore not established. Document index |
2. The project story
SAI CHANDRA HILL RIDGE is registered as a residential apartment project on Plot Nos. 6 and 7, Survey No. 106/1 Part, in Puppalguda, Gandipet Mandal, Ranga Reddy District. The registered site extent is 836.54 sq. m. RERA record RERA filing
The filed proposal is for one residential building, described in HMDA’s technical approval as having a cellar, stilt and five upper floors. TG-RERA unit information lists 15 apartments, all 3BHK. The project’s completion date is stated in the promoter’s Form B declaration as 09-05-2025, while the registration certificate’s separate validity period ended on that same date. Neither document establishes that construction was completed or that an occupancy certificate was issued. No independently verified construction-stage information is supplied. RERA unit table
3. Master plan, architecture & building design
The filed HMDA technical approval identifies a proposed residential building on a site of 836.54 sq. m., with 1 Cellar + 1 Stilt + 5 Upper floors. It records “Built up Area 1968.8,” “Total Built up Area (In Sq.mts) 1968.8,” and “Proposed Built-up Area 2286.75.” The supplied document does not define the relationship among these area labels, so they should not be treated as interchangeable measurements.
The approval calls for a tot-lot to be fenced and maintained as greenery, and specifies that the cellar/stilt be used exclusively for vehicle parking. It also identifies provision for a transformer, garbage house and rainwater-harvesting structures. The supplied drawing data contains no measured floor-plan geometry or layout sheets; it does not establish the building footprint, floor-by-floor apartment arrangement, flats per floor, lift or stair details, internal circulation, or landscaped-area dimensions. Floor plans
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 15 | 0 | 15 | 99.86 sq. m. | Not available: the supplied floor-plan records report no measured plans. | Not supplied. |
The unit counts, booking counts and saleable area are RERA-filed figures; the booking record has no as-of date. No drawing-based carpet-area measurement or room dimensions are available in the supplied drawing data. Saleable area and carpet area are distinct measures; the supplied records do not provide enough information to quantify any common-area loading or balcony/utility area for these units. RERA unit table RERA unit details Floor plans
5. Parking & vehicle circulation
The HMDA technical approval directs that the cellar/stilt be used exclusively for vehicle parking, without partition walls or rolling shutters. It does not provide a parking-space count, parking-type breakdown, ramp or driveway details, visitor or accessible-space provision, EV charging information, or unit-wise parking allocation. The supplied record therefore establishes a parking-use requirement for the cellar/stilt, but not the number of spaces or any buyer’s exclusive parking entitlement.
6. Amenities, recreation & open spaces
The following are recorded in the HMDA technical approval or the RERA amenity data. Declared progress is reported as supplied; it is not independent confirmation of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / greenery | To be fenced and maintained as greenery; no area or capacity supplied. | HMDA technical approval | Approval condition; completion not verified. |
| Green Strip/TOT LOT/Park | Listed as available “YES”; no size supplied. | RERA amenity record RERA amenities | Progress shown as 0%; completion not verified. |
| Community buildings | Listed; no description or size supplied. | RERA amenity record RERA amenities | Progress shown as 0%; completion not verified. |
The supplied project records do not establish a clubhouse, gym, swimming pool, children’s play area or other indoor/sports facilities as approved or delivered project amenities. RERA amenities
7. Utilities, building services & safety
The HMDA technical approval requires rainwater-harvesting structures and provisions for a transformer and garbage house. It also states that water supply and sewerage disposal sources should be located at an appropriate distance within the site, preferably 100 feet, to avoid contamination. These are approval requirements; their installation or operation is not independently verified.
The RERA amenity record marks water supply, storm-water drains, rainwater harvesting, fire-protection/fire-safety requirements, and an electrical meter room/sub-station/receiving station as “YES.” It records progress as 0% for these items. The same record lists sewerage, treatment and disposal of sewage and sullage water, energy management, solid-waste management and disposal, and street lighting, but the supplied data does not establish completed facilities, capacities, systems or operating arrangements. RERA amenities
HMDA’s approval assigns structural-safety and fire-safety responsibilities to the owner/developer and relevant professionals, and requires applicable fire-fighting installations. The supplied documents do not include fire-system specifications, clearance certificates, lift information, backup-power capacity, accessibility details, or verified completion evidence.
8. Location, access & connectivity
The registered project location is Puppalguda, Gandipet Mandal, Ranga Reddy District, Telangana 500089; the project land is identified as Survey No. 106/1 Part, Plot Nos. 6 and 7. The north boundary is a 40 Feet Wide Road. RERA record RERA filing
The supplied location record gives the Financial District (Nanakramguda) as an anchor at 4.9 km. No route, measurement method or travel time is supplied. The HMDA approval also refers to an 18 mt. road width in a condition concerning a site abutting such a road; the supplied record does not establish that this project site abuts an 18 mt. road. Location record
9. Developer & development status
The registered promoter is APURVA CONSTRUCTIONS, identified in the RERA filing as a partnership. The supplied promoter information names Purendar Reddy Bekkem as partner and authorized signatory. The Form B affidavit is stated to have been made by Purender Reddy Bekkem as authorized signatory and declares a completion period of 09-05-2025. Corporate record Parties record
The registration certificate records validity from 30/10/2020 through 09/05/2025 and does not record an extension. The supplied records do not establish the project’s current construction stage or whether an occupancy or completion certificate has since been issued. Document index
10. Approvals, official records & documents
| Supplied details | Form C for SAI CHANDRA HILL RIDGE; registration P02400002179; issued 30/10/2020; validity stated through 09/05/2025. |
|---|
| Supplied details | Approval no. 019452/SKP/R1/U6/HMDA/22012019; dated 09/05/2019; identifies Survey No. 106/1 PART and a proposed residential building. |
|---|
| Supplied details | Signed by the named authorized signatory; declares development rights and a completion period of 09-05-2025. |
|---|
| Supplied details | No certificate is included in the supplied documents. |
|---|---|
| Evidence | Document index |
| Supplied details | The supplied floor-plan data reports two drawings, with no measured plans and no layout sheets. |
|---|---|
| Evidence | Floor plans |
1. Project at a glance
Project identity
Registered project name: SAI CHANDRA HILL RIDGE
Project type / registered portion: Residential apartment project; one building is identified in the filed land details. No separate phase name or phase number is disclosed.
TG-RERA registration: P02400002179
Registration validity: Certificate states four years, from 30/10/2020 to 09/05/2025; it records no extension. This is the registration period, not an occupancy certificate or completion confirmation.
Registered promoter: APURVA CONSTRUCTIONS; the filing identifies its organization type as Partnership.
RERA status: The supplied certificate establishes registration and its stated validity period. Current registration status after 09/05/2025 is not established by the supplied record.
Land and geographic identity
Locality / revenue village: Puppalguda; locality is also recorded as puppalguda.
Mandal / district / PIN: Gandipet / Ranga Reddy / 500089.
Project survey identity: Survey No. 106/1 Part; the HMDA technical approval also identifies 106/1 PART. No other project survey subdivision is stated in the supplied project filing.
Site extent: 836.54 sq. m. is stated in the filed land details and HMDA technical approval. The RERA land form records total area 836.54 sq. m., affected area 0, and net area 836.54 sq. m.
Boundaries: North: 40 Feet Wide Road; South: Plot No. 14 and 15, Block G; East: Plot No. 5, Block G; West: Plot No. 8, Block G.
Development identity
Sanctioning authority / approval: Hyderabad Metropolitan Development Authority (HMDA); approval no. 019452/SKP/R1/U6/HMDA/22012019, dated 09/05/2019. The document describes technical approval and states that building plans are to be sanctioned by the Executive Authority in conformity with those plans.
Building and floors: One proposed residential building; filed technical approval describes 1 Cellar + 1 Stilt + 5 Upper floors.
Approved area figures: HMDA approval lists “Built up Area 1968.8,” “Total Built up Area (In Sq.mts) 1968.8,” and “Proposed Built-up Area 2286.75.” These are reproduced as separately labelled in the approval; the supplied record does not explain the distinction.
Mortgage area: RERA land details state 210.62 sq. m.; the HMDA approval records 210.62 sq. m. as mortgaged built-up area.
Units: RERA filing: 15 units, all 3BHK. The filed land details separately state one total building unit and one proposed building unit; the supplied data does not explain that field’s relationship to the 15 apartment units.
Parking: HMDA technical approval states the cellar/stilt should be used exclusively for vehicle parking. A sanctioned parking-space count and unit-wise allocation are not supplied.
Offering and status
RERA-filed offering: 15 × 3BHK apartments; filed saleable area is 99.86 sq. m. per unit. The filing records 0 booked and 15 available, but gives no as-of date, so these counts are indicative only.
Construction stage: Current construction progress is not established by the supplied records. The RERA registration certificate records the project’s registration period, not construction completion.
Completion date: Form B promoter declaration states a project completion period of 09-05-2025.
Occupancy / completion certificate: No occupancy certificate or completion certificate is supplied. Its status for this building is therefore not established.
2. The project story
SAI CHANDRA HILL RIDGE is registered as a residential apartment project on Plot Nos. 6 and 7, Survey No. 106/1 Part, in Puppalguda, Gandipet Mandal, Ranga Reddy District. The registered site extent is 836.54 sq. m.
The filed proposal is for one residential building, described in HMDA’s technical approval as having a cellar, stilt and five upper floors. TG-RERA unit information lists 15 apartments, all 3BHK. The project’s completion date is stated in the promoter’s Form B declaration as 09-05-2025, while the registration certificate’s separate validity period ended on that same date. Neither document establishes that construction was completed or that an occupancy certificate was issued. No independently verified construction-stage information is supplied.
3. Master plan, architecture & building design
The filed HMDA technical approval identifies a proposed residential building on a site of 836.54 sq. m., with 1 Cellar + 1 Stilt + 5 Upper floors. It records “Built up Area 1968.8,” “Total Built up Area (In Sq.mts) 1968.8,” and “Proposed Built-up Area 2286.75.” The supplied document does not define the relationship among these area labels, so they should not be treated as interchangeable measurements.
The approval calls for a tot-lot to be fenced and maintained as greenery, and specifies that the cellar/stilt be used exclusively for vehicle parking. It also identifies provision for a transformer, garbage house and rainwater-harvesting structures. The supplied drawing data contains no measured floor-plan geometry or layout sheets; it does not establish the building footprint, floor-by-floor apartment arrangement, flats per floor, lift or stair details, internal circulation, or landscaped-area dimensions.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 15 | 0 | 15 | 99.86 sq. m. | Not available: the supplied floor-plan records report no measured plans. | Not supplied. |
The unit counts, booking counts and saleable area are RERA-filed figures; the booking record has no as-of date. No drawing-based carpet-area measurement or room dimensions are available in the supplied drawing data. Saleable area and carpet area are distinct measures; the supplied records do not provide enough information to quantify any common-area loading or balcony/utility area for these units.
5. Parking & vehicle circulation
The HMDA technical approval directs that the cellar/stilt be used exclusively for vehicle parking, without partition walls or rolling shutters. It does not provide a parking-space count, parking-type breakdown, ramp or driveway details, visitor or accessible-space provision, EV charging information, or unit-wise parking allocation. The supplied record therefore establishes a parking-use requirement for the cellar/stilt, but not the number of spaces or any buyer’s exclusive parking entitlement.
6. Amenities, recreation & open spaces
The following are recorded in the HMDA technical approval or the RERA amenity data. Declared progress is reported as supplied; it is not independent confirmation of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / greenery | To be fenced and maintained as greenery; no area or capacity supplied. | HMDA technical approval | Approval condition; completion not verified. |
| Green Strip/TOT LOT/Park | Listed as available “YES”; no size supplied. | RERA amenity record | Progress shown as 0%; completion not verified. |
| Community buildings | Listed; no description or size supplied. | RERA amenity record | Progress shown as 0%; completion not verified. |
The supplied project records do not establish a clubhouse, gym, swimming pool, children’s play area or other indoor/sports facilities as approved or delivered project amenities.
7. Utilities, building services & safety
The HMDA technical approval requires rainwater-harvesting structures and provisions for a transformer and garbage house. It also states that water supply and sewerage disposal sources should be located at an appropriate distance within the site, preferably 100 feet, to avoid contamination. These are approval requirements; their installation or operation is not independently verified.
The RERA amenity record marks water supply, storm-water drains, rainwater harvesting, fire-protection/fire-safety requirements, and an electrical meter room/sub-station/receiving station as “YES.” It records progress as 0% for these items. The same record lists sewerage, treatment and disposal of sewage and sullage water, energy management, solid-waste management and disposal, and street lighting, but the supplied data does not establish completed facilities, capacities, systems or operating arrangements.
HMDA’s approval assigns structural-safety and fire-safety responsibilities to the owner/developer and relevant professionals, and requires applicable fire-fighting installations. The supplied documents do not include fire-system specifications, clearance certificates, lift information, backup-power capacity, accessibility details, or verified completion evidence.
8. Location, access & connectivity
The registered project location is Puppalguda, Gandipet Mandal, Ranga Reddy District, Telangana 500089; the project land is identified as Survey No. 106/1 Part, Plot Nos. 6 and 7. The north boundary is a 40 Feet Wide Road.
The supplied location record gives the Financial District (Nanakramguda) as an anchor at 4.9 km. No route, measurement method or travel time is supplied. The HMDA approval also refers to an 18 mt. road width in a condition concerning a site abutting such a road; the supplied record does not establish that this project site abuts an 18 mt. road.
9. Developer & development status
The registered promoter is APURVA CONSTRUCTIONS, identified in the RERA filing as a partnership. The supplied promoter information names Purendar Reddy Bekkem as partner and authorized signatory. The Form B affidavit is stated to have been made by Purender Reddy Bekkem as authorized signatory and declares a completion period of 09-05-2025.
The registration certificate records validity from 30/10/2020 through 09/05/2025 and does not record an extension. The supplied records do not establish the project’s current construction stage or whether an occupancy or completion certificate has since been issued.
10. Approvals, official records & documents
| Supplied details | Form C for SAI CHANDRA HILL RIDGE; registration P02400002179; issued 30/10/2020; validity stated through 09/05/2025. |
|---|
| Supplied details | Approval no. 019452/SKP/R1/U6/HMDA/22012019; dated 09/05/2019; identifies Survey No. 106/1 PART and a proposed residential building. |
|---|
| Supplied details | Signed by the named authorized signatory; declares development rights and a completion period of 09-05-2025. |
|---|
| Supplied details | No certificate is included in the supplied documents. |
|---|
| Supplied details | The supplied floor-plan data reports two drawings, with no measured plans and no layout sheets. |
|---|
Frequently asked questions
Is SAI CHANDRA HILL RIDGE registered with Telangana RERA?
Yes. SAI CHANDRA HILL RIDGE is registered with the Telangana Real Estate Regulatory Authority as P02400002179; the registration status is New Project.
Who is the developer of SAI CHANDRA HILL RIDGE?
The promoter named in the RERA registration is APURVA CONSTRUCTIONS.
Where is SAI CHANDRA HILL RIDGE located?
SAI CHANDRA HILL RIDGE is in puppalguda, Gandipet, Rangareddy, Telangana (500089).
When will SAI CHANDRA HILL RIDGE be completed?
The promoter's proposed date of completion filed with RERA is 09/05/2025. This is the promoter's declaration, not a guarantee.