Rise
SCINTILLA INFRA LLP · Rangareddy · RERA P02400004890
RISE is a residential apartment project in Padmasri Hills, Bandlaguda Jagir, Gandipet mandal, Ranga Reddy district, developed by registered promoter Scintilla Infra LLP. It is on a 612.38 m² site and comprises one building with 1 stilt + 5 upper floors and 15 2BHK apartments. Its TG-RERA registration is P02400004890, and the promoter’s Form B undertaking states completion by 30 August 2024.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered name | RISE RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | Phase not separately identified in the supplied record; the registration and occupancy documents refer to the building at Plot No. 48 |
| TG-RERA registration | P02400004890 |
| Registration validity | 29 August 2022–30 August 2024; certificate says two years and no extension is recorded in the supplied registration-certificate extract |
| Registered promoter | Scintilla Infra LLP |
| RERA status | Registration period shown in the certificate has ended. The supplied documents also include an occupancy certificate for the building; these are separate records and statuses. |
Land and geographic identity
| Item | Record |
|---|---|
| Locality | Padmasri Hills RERA record |
| Revenue village | Bandlaguda Jagir (also recorded as Bandlaguda Jagir Village) |
| Mandal / district / PIN | Gandipet / Ranga Reddy / 500068 RERA record |
| Project survey number and subdivision | 96/10 RU P; the title documents also use 96/10 RU (P) and refer to Part Number 6 and Part No. 8. RERA record Land records |
| Plot / house identifier | Plot No. 48; RERA certificate also records PT No. 48, H.No. 8 |
| Registered site extent | 612.38 m²; RERA land record gives total and net area as 612.38 m² and affected area as 0 Land records |
| Boundaries | East: Plot No. 47; West: Plot No. 49; North: Plot No. 46 part; South: 30 ft wide road Land records |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Bandlaguda Jagir Municipal Corporation |
| Principal building approval | 0004/BP/3130/2021, dated 30 August 2021 |
| Approved built-up area | 1,390.35 m² residential upper-floor area is stated in the building-permit extract; the RERA filing separately records approved built-up area as 1,713.36 m². These are different labelled figures in the supplied record. RERA filing |
| Building count / configuration | One building; 1 stilt + 5 upper floors RERA record |
| Sanctioned height | 14.95 m |
| Sanctioned parking provision | Stilt parking area 289.94 m²; the supplied extract does not state a sanctioned space count |
| Unit counts | 15 total units in the RERA unit record; the approval extract does not provide a separate approved unit count RERA unit table RERA unit details |
Offering and status
| Item | Record |
|---|---|
| Configuration | 2BHK RERA unit table RERA unit details |
| RERA-filed saleable area | 115.82 m² RERA unit table RERA unit details |
| Booked / available | 9 booked and 6 available, as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative RERA unit table |
| Construction stage | A municipal occupancy certificate dated 27 February 2024 states the building was inspected and declared fit for occupation. This is an occupancy-certified building, not a statement that the RERA registration remains valid. |
| Completion dates | Promoter’s Form B undertaking states completion by 30 August 2024; the building-permit extract also states completion before 30 August 2024. The occupancy certificate records building completion date as 10 September 2021. |
| Occupancy certificate | Certificate 0009/OC/3130/2024, issued 27 February 2024; document scope is the building at Plot No. 48, Survey No. 96/10 RU P |
2. The project story
RISE is a single-building residential apartment project recorded at Plot No. 48 in Padmasri Hills, Bandlaguda Jagir, Gandipet mandal, Ranga Reddy district. Its RERA land identity is Survey No. 96/10 RU P. The municipal building approval describes a residential building of one stilt level and five upper floors on a 612.38 m² site. RERA record Land records
The RERA unit record lists 15 two-bedroom apartments, of which 9 are recorded as booked and 6 as available; those booking figures have no stated as-of date. RERA unit table The project has an occupancy certificate for the building, issued on 27 February 2024, and the certificate says it was inspected and declared fit for occupation. The supplied evidence does not independently verify current site condition, actual occupancy or whether the portal inventory has since changed.
3. Master plan, architecture & building design
The municipal approval identifies one building, “Building - BLDG (GOTTUMUKKALA),” for residential use, with 1 stilt + 5 upper floors, a stated height of 14.95 m and a site area of 612.38 m². It records residential upper-floor area of 1,390.35 m² and stilt parking area of 289.94 m².
The RERA filing separately records approved built-up area of 1,713.36 m². RERA filing The supplied extracts do not identify a building footprint, floor-by-floor unit arrangement, number of flats per floor, lifts, stairs, entry/exit layout, or a quantified residential/common-area breakdown. The permit lists 5% open space and requires a fenced tot-lot maintained as greenery; the occupancy-certificate extract records tot-lot area as 0 m².
The approval extract specifies a first-floor area of 158.23 m² as handed over and describes surrender of any road-affected portion to the municipality without compensation; the recorded road-affected area is 0.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading |
|---|---|---|---|---|---|---|
| 2BHK | 15 | 9 | 6 | 115.82 m² | Software-measured range: 71.2–79.6 m²; median: 72.6 m² | 37% |
RERA-filed unit counts, bookings and saleable area are from the project unit record; booked and available counts are indicative because the source provides no as-of date. RERA unit table RERA unit details Carpet-area measurements are software-measured from the filed drawing, not RERA disclosures; the supplied note says the geometry measurement needs review. Floor plans
For one measured flat design, the drawing labels a hall, dining area, kitchen, two bedrooms, two toilets, a wash area and two balconies. The drawing extract gives room dimensions, including a hall of 2.48 × 4.32 m, kitchen of 2.4 × 3.3 m and master bedroom of 3.3 × 3.9 m. Balcony areas are excluded from the software-measured carpet area. RERA unit details
Carpet area is a drawing-based interior-area measurement in this analysis. RERA saleable area is the filed saleable figure and is not interchangeable with carpet area; the supplied record does not provide a RERA-filed carpet-area figure or a separate balcony-area disclosure. RERA unit details Floor plans
5. Parking & vehicle circulation
The building permit provides stilt parking with an area of 289.94 m². The occupancy-certificate extract records parking area as 299.9 m². The supplied materials do not state the number of car or two-wheeler spaces, visitor or accessible spaces, mechanical parking, EV charging, parking allocation to particular apartments, or a spaces-per-home ratio.
The permit says approved cellar and stilt areas for parking are to be used exclusively for vehicle parking and not partitioned or converted to another use. The supplied extract identifies stilt parking but does not establish a cellar level or document individual parking allocations.
6. Amenities, recreation & open spaces
The following items are in the supplied RERA amenity record or approval/occupancy documents. The percentages in the amenity record are recorded progress fields, not independent site verification. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Permit requires a fenced tot-lot maintained as greenery; no area stated in the permit extract. Occupancy-certificate extract records tot-lot area as 0 m². | RERA amenity record: YES, 100%; completion not independently verified. RERA amenities | |
| Community buildings | No community building recorded | RERA amenities | 0% in RERA amenity record RERA amenities |
| Aggregate recreational open space | No area recorded | RERA amenities | 0% in RERA amenity record RERA amenities |
7. Utilities, building services & safety
| Service | Evidence in the project record |
|---|---|
| Water | RERA amenity record marks water supply as YES, 100%. The permit requires four rainwater-harvesting pits; the occupancy-certificate extract also records four. No water source, storage capacity or treatment capacity is stated. RERA amenities |
| Sewerage and drainage | RERA amenity record marks sewerage (chambers, lines, septic tank, STP) as YES, 100%; treatment and disposal of sewage and sullage water is separately recorded as 0%. No STP capacity or reuse arrangement is supplied. RERA amenities |
| Storm-water | Storm-water drains are recorded as 0% in the RERA amenity record. RERA amenities |
| Electrical | Energy management and electrical meter room/sub-station/receiving station are each recorded as YES, 100%. The permit requires transformer space; no backup-power details or capacity are stated. RERA amenities |
| Fire and life safety | Fire protection and fire-safety requirements are recorded as 0% in the RERA amenity record. The permit assigns responsibility for required fire-fighting installations and safety requirements to the owner, builder/developer and technical professionals; the supplied extracts do not establish installed systems or completion. RERA amenities |
| Waste | Permit requires a garbage house with dry/wet segregation; solid-waste management and disposal are recorded as 0% in the RERA amenity record. RERA amenities |
| Lifts and accessibility | The permit refers to lifts and requires facilities for physically handicapped persons in public and semi-public buildings. No lift count/capacity or project-specific accessible-route details are provided. |
| Roads and footpaths | Internal roads and footpaths are recorded as YES, 100% in the RERA amenity record. The supplied material gives no dimensions or independent completion evidence. RERA amenities |
8. Location, access & connectivity
The registered project location is Padmasri Hills, Bandlaguda Jagir, Gandipet mandal, Ranga Reddy district, PIN 500068. The RERA filing records the south boundary as a 30 ft wide road; the building-permit extract also lists a road width of 4.5 m. RERA record Land records
The location record lists these distances to nearby points: Glendale Academy International, 0.4 km; an unnamed park, 0.6 km; DIVA Multispeciality Clinics, 0.8 km; Union Bank of India, 0.9 km; an unnamed bus station, 1.3 km; Shadan College of Engineering, 2.4 km; and Shamserganj metro, marked under construction, 7.8 km. Location record These are supplied location-record distances; no travel times are provided.
9. Developer & development status
The registered promoter is Scintilla Infra LLP, an LLP, with GSTIN 36AEKFS1547N1ZG. The RERA project record gives the promoter address as Plot No. 12, Flat No. 201, 9th Phase, KPHB Colony, Padmasri Hills, Gandipet, Ranga Reddy, PIN 500068. Corporate record RERA filing RERA filing
The promoter’s Form B, signed by authorised signatory Varun Kumar Raju Sagiraju, declares a completion undertaking of 30 August 2024. The building-permit extract gives the same completion-before date, while the occupancy certificate records the building as completed on 10 September 2021 and fit for occupation when certified on 27 February 2024. These are distinct records; the supplied evidence does not provide a separate verified current site-progress report.
10. Approvals, official records & documents
| Identifier / date | P02400004890, issued 29 August 2022; valid to 30 August 2024 |
|---|---|
| Scope and source | Project RISE; Form C |
| Identifier / date | 0004/BP/3130/2021, dated 30 August 2021 |
|---|---|
| Scope and source | Bandlaguda Jagir Municipal Corporation; Survey No. 96/10 RU P, Plot No. 48; residential building |
| Identifier / date | 0009/OC/3130/2024, dated 27 February 2024 |
|---|---|
| Scope and source | Bandlaguda Jagir Municipal Corporation; building at Plot No. 48, Survey No. 96/10 RU P |
| Identifier / date | Application 000675/OC/DTCP/3130/0006/2024; proceedings 0009/OC/3130/2024 |
|---|---|
| Scope and source | Occupancy-certificate record |
| Identifier / date | 2337/LRS/PLG/H/08 |
|---|---|
| Scope and source | Cited in the building approval and occupancy-certificate extracts |
| Identifier / date | Form B dated 16 April 2022 |
|---|---|
| Scope and source | Title, encumbrance and completion-period declarations by the authorised signatory |
| Identifier / date | Document 216605 |
|---|---|
| Scope and source | Drawing-derived measurements; supplied plan document is not extracted as a complete drawing in this record |
The supplied record includes the registration certificate, building approval, occupancy certificate, promoter Form B, title-related filings and a floor-plan document. The Overview does not independently verify the completeness or present-day status of records beyond those supplied.
1. Project at a glance
Project identity
Registered name: RISE
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified in the supplied record; the registration and occupancy documents refer to the building at Plot No. 48
TG-RERA registration: P02400004890
Registration validity: 29 August 2022–30 August 2024; certificate says two years and no extension is recorded in the supplied registration-certificate extract
Registered promoter: Scintilla Infra LLP
RERA status: Registration period shown in the certificate has ended. The supplied documents also include an occupancy certificate for the building; these are separate records and statuses.
Land and geographic identity
Locality: Padmasri Hills
Revenue village: Bandlaguda Jagir (also recorded as Bandlaguda Jagir Village)
Mandal / district / PIN: Gandipet / Ranga Reddy / 500068
Project survey number and subdivision: 96/10 RU P; the title documents also use 96/10 RU (P) and refer to Part Number 6 and Part No. 8.
Plot / house identifier: Plot No. 48; RERA certificate also records PT No. 48, H.No. 8
Registered site extent: 612.38 m²; RERA land record gives total and net area as 612.38 m² and affected area as 0
Boundaries: East: Plot No. 47; West: Plot No. 49; North: Plot No. 46 part; South: 30 ft wide road
Development identity
Sanctioning authority: Bandlaguda Jagir Municipal Corporation
Principal building approval: 0004/BP/3130/2021, dated 30 August 2021
Approved built-up area: 1,390.35 m² residential upper-floor area is stated in the building-permit extract; the RERA filing separately records approved built-up area as 1,713.36 m². These are different labelled figures in the supplied record.
Building count / configuration: One building; 1 stilt + 5 upper floors
Sanctioned height: 14.95 m
Sanctioned parking provision: Stilt parking area 289.94 m²; the supplied extract does not state a sanctioned space count
Unit counts: 15 total units in the RERA unit record; the approval extract does not provide a separate approved unit count
Offering and status
Configuration: 2BHK
RERA-filed saleable area: 115.82 m²
Booked / available: 9 booked and 6 available, as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative
Construction stage: A municipal occupancy certificate dated 27 February 2024 states the building was inspected and declared fit for occupation. This is an occupancy-certified building, not a statement that the RERA registration remains valid.
Completion dates: Promoter’s Form B undertaking states completion by 30 August 2024; the building-permit extract also states completion before 30 August 2024. The occupancy certificate records building completion date as 10 September 2021.
Occupancy certificate: Certificate 0009/OC/3130/2024, issued 27 February 2024; document scope is the building at Plot No. 48, Survey No. 96/10 RU P
2. The project story
RISE is a single-building residential apartment project recorded at Plot No. 48 in Padmasri Hills, Bandlaguda Jagir, Gandipet mandal, Ranga Reddy district. Its RERA land identity is Survey No. 96/10 RU P. The municipal building approval describes a residential building of one stilt level and five upper floors on a 612.38 m² site.
The RERA unit record lists 15 two-bedroom apartments, of which 9 are recorded as booked and 6 as available; those booking figures have no stated as-of date. The project has an occupancy certificate for the building, issued on 27 February 2024, and the certificate says it was inspected and declared fit for occupation. The supplied evidence does not independently verify current site condition, actual occupancy or whether the portal inventory has since changed.
3. Master plan, architecture & building design
The municipal approval identifies one building, “Building - BLDG (GOTTUMUKKALA),” for residential use, with 1 stilt + 5 upper floors, a stated height of 14.95 m and a site area of 612.38 m². It records residential upper-floor area of 1,390.35 m² and stilt parking area of 289.94 m².
The RERA filing separately records approved built-up area of 1,713.36 m². The supplied extracts do not identify a building footprint, floor-by-floor unit arrangement, number of flats per floor, lifts, stairs, entry/exit layout, or a quantified residential/common-area breakdown. The permit lists 5% open space and requires a fenced tot-lot maintained as greenery; the occupancy-certificate extract records tot-lot area as 0 m².
The approval extract specifies a first-floor area of 158.23 m² as handed over and describes surrender of any road-affected portion to the municipality without compensation; the recorded road-affected area is 0.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading |
|---|---|---|---|---|---|---|
| 2BHK | 15 | 9 | 6 | 115.82 m² | Software-measured range: 71.2–79.6 m²; median: 72.6 m² | 37% |
RERA-filed unit counts, bookings and saleable area are from the project unit record; booked and available counts are indicative because the source provides no as-of date. Carpet-area measurements are software-measured from the filed drawing, not RERA disclosures; the supplied note says the geometry measurement needs review.
For one measured flat design, the drawing labels a hall, dining area, kitchen, two bedrooms, two toilets, a wash area and two balconies. The drawing extract gives room dimensions, including a hall of 2.48 × 4.32 m, kitchen of 2.4 × 3.3 m and master bedroom of 3.3 × 3.9 m. Balcony areas are excluded from the software-measured carpet area.
Carpet area is a drawing-based interior-area measurement in this analysis. RERA saleable area is the filed saleable figure and is not interchangeable with carpet area; the supplied record does not provide a RERA-filed carpet-area figure or a separate balcony-area disclosure.
5. Parking & vehicle circulation
The building permit provides stilt parking with an area of 289.94 m². The occupancy-certificate extract records parking area as 299.9 m². The supplied materials do not state the number of car or two-wheeler spaces, visitor or accessible spaces, mechanical parking, EV charging, parking allocation to particular apartments, or a spaces-per-home ratio.
The permit says approved cellar and stilt areas for parking are to be used exclusively for vehicle parking and not partitioned or converted to another use. The supplied extract identifies stilt parking but does not establish a cellar level or document individual parking allocations.
6. Amenities, recreation & open spaces
The following items are in the supplied RERA amenity record or approval/occupancy documents. The percentages in the amenity record are recorded progress fields, not independent site verification.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Permit requires a fenced tot-lot maintained as greenery; no area stated in the permit extract. Occupancy-certificate extract records tot-lot area as 0 m². | RERA amenity record: YES, 100%; completion not independently verified. | |
| Community buildings | No community building recorded | 0% in RERA amenity record | |
| Aggregate recreational open space | No area recorded | 0% in RERA amenity record |
7. Utilities, building services & safety
Water: RERA amenity record marks water supply as YES, 100%. The permit requires four rainwater-harvesting pits; the occupancy-certificate extract also records four. No water source, storage capacity or treatment capacity is stated.
Sewerage and drainage: RERA amenity record marks sewerage (chambers, lines, septic tank, STP) as YES, 100%; treatment and disposal of sewage and sullage water is separately recorded as 0%. No STP capacity or reuse arrangement is supplied.
Storm-water: Storm-water drains are recorded as 0% in the RERA amenity record.
Electrical: Energy management and electrical meter room/sub-station/receiving station are each recorded as YES, 100%. The permit requires transformer space; no backup-power details or capacity are stated.
Fire and life safety: Fire protection and fire-safety requirements are recorded as 0% in the RERA amenity record. The permit assigns responsibility for required fire-fighting installations and safety requirements to the owner, builder/developer and technical professionals; the supplied extracts do not establish installed systems or completion.
Waste: Permit requires a garbage house with dry/wet segregation; solid-waste management and disposal are recorded as 0% in the RERA amenity record.
Lifts and accessibility: The permit refers to lifts and requires facilities for physically handicapped persons in public and semi-public buildings. No lift count/capacity or project-specific accessible-route details are provided.
Roads and footpaths: Internal roads and footpaths are recorded as YES, 100% in the RERA amenity record. The supplied material gives no dimensions or independent completion evidence.
8. Location, access & connectivity
The registered project location is Padmasri Hills, Bandlaguda Jagir, Gandipet mandal, Ranga Reddy district, PIN 500068. The RERA filing records the south boundary as a 30 ft wide road; the building-permit extract also lists a road width of 4.5 m.
The location record lists these distances to nearby points: Glendale Academy International, 0.4 km; an unnamed park, 0.6 km; DIVA Multispeciality Clinics, 0.8 km; Union Bank of India, 0.9 km; an unnamed bus station, 1.3 km; Shadan College of Engineering, 2.4 km; and Shamserganj metro, marked under construction, 7.8 km. These are supplied location-record distances; no travel times are provided.
9. Developer & development status
The registered promoter is Scintilla Infra LLP, an LLP, with GSTIN 36AEKFS1547N1ZG. The RERA project record gives the promoter address as Plot No. 12, Flat No. 201, 9th Phase, KPHB Colony, Padmasri Hills, Gandipet, Ranga Reddy, PIN 500068.
The promoter’s Form B, signed by authorised signatory Varun Kumar Raju Sagiraju, declares a completion undertaking of 30 August 2024. The building-permit extract gives the same completion-before date, while the occupancy certificate records the building as completed on 10 September 2021 and fit for occupation when certified on 27 February 2024. These are distinct records; the supplied evidence does not provide a separate verified current site-progress report.
10. Approvals, official records & documents
| Identifier / date | P02400004890, issued 29 August 2022; valid to 30 August 2024 |
|---|---|
| Scope and source | Project RISE; Form C |
| Identifier / date | 0004/BP/3130/2021, dated 30 August 2021 |
|---|---|
| Scope and source | Bandlaguda Jagir Municipal Corporation; Survey No. 96/10 RU P, Plot No. 48; residential building |
| Identifier / date | 0009/OC/3130/2024, dated 27 February 2024 |
|---|---|
| Scope and source | Bandlaguda Jagir Municipal Corporation; building at Plot No. 48, Survey No. 96/10 RU P |
| Identifier / date | Application 000675/OC/DTCP/3130/0006/2024; proceedings 0009/OC/3130/2024 |
|---|---|
| Scope and source | Occupancy-certificate record |
| Identifier / date | 2337/LRS/PLG/H/08 |
|---|---|
| Scope and source | Cited in the building approval and occupancy-certificate extracts |
| Identifier / date | Form B dated 16 April 2022 |
|---|---|
| Scope and source | Title, encumbrance and completion-period declarations by the authorised signatory |
| Identifier / date | Document 216605 |
|---|---|
| Scope and source | Drawing-derived measurements; supplied plan document is not extracted as a complete drawing in this record |
The supplied record includes the registration certificate, building approval, occupancy certificate, promoter Form B, title-related filings and a floor-plan document. The Overview does not independently verify the completeness or present-day status of records beyond those supplied.
Frequently asked questions
Is RISE registered with Telangana RERA?
Yes. RISE is registered with the Telangana Real Estate Regulatory Authority as P02400004890; the registration status is New Project.
Who is the developer of RISE?
The promoter named in the RERA registration is SCINTILLA INFRA LLP.
Where is RISE located?
RISE is in PADMASRI HILLS, Bandlaguda, Gandipet, Rangareddy, Telangana (500068).
When will RISE be completed?
The promoter's proposed date of completion filed with RERA is 30/08/2024. This is the promoter's declaration, not a guarantee.