RAGHAVENDRA HOMES is a plotted development in Bahadurpet, Alair Mandal, Yadadri Bhuvanagiri District. It is being developed by the registered promoter AVANAGANTI PANDU AND OTHERS. The project has a total site area of 15,542.23 sq. m and a tentative layout of 60 plots, with drawing-derived plot sizes ranging from 102.91 sq. m to 396.32 sq. m. It is registered under TG-RERA **P02000010924**, with proposed completion **30/11/2026**.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | RAGHAVENDRA HOMES RERA record |
| Project type | Plotted development / tentative residential layout RERA record RERA filing |
| Phase / registered portion | No separate phase is identified in the supplied record; the registration is for the named project. RERA record |
| TG-RERA registration | P02000010924 RERA record |
| Registration validity | 10/07/2023 to 10/07/2026; the certificate records a three-year term and no extension. Validity is distinct from the project completion undertaking and from any completion/occupancy certificate. RERA record |
| Registered promoter | AVANAGANTI PANDU AND OTHERS RERA record |
| RERA status in supplied record | Registered; the certificate records validity through 10/07/2026. The supplied record does not establish the registration’s current status after that date. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Bahadurpet is the RERA-record locality; the filed tentative layout document describes the land as being in Alair Revenue Village. The supplied records therefore identify both names; confirm the revenue-village identity against the underlying land records. RERA record |
| Mandal / district / PIN | Alair Mandal; Yadadri Bhuvanagiri District; PIN 508101. RERA record |
| Project survey number(s) | Sy. No. 114; the layout approval identifies no subdivision. RERA record RERA filing |
| Registered site extent | 15,542.23 sq. m total site area; 14,847.10 sq. m net area; 695.13 sq. m recorded as affected by road widening/FTL of tanks/nala widening. RERA filing Land records |
| Layout document’s stated extent | 3 Acer 33.62 Gts 18589 Sq. Yds. |
| Boundaries | East: agriculture land of Barma Padma; west: road; north: other land; south: other land. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | ALAIR Municipality/Municipal Corporation; the RERA filing identifies DTCP as the authority for plan approval. Approvals record |
| Principal approval | Tentative Layout Plan LP No. 0003/LO/3102/2023, dated 07/10/2023 6:23:06 PM. Approvals record |
| Application number | 004374/LO/DTCP/3102/0006/2023. |
| Approved / plotted area | The RERA-filed project information records approved built-up area of 9076.85 sq. m; the layout drawing identifies this as plotted area. It is not a residential-building gross or carpet area. RERA filing Layout record |
| Plot count | 60 plots, as stated in the tentative layout approval. |
| Buildings / floors | Not disclosed as a multi-building or apartment development; no building count or floor configuration is established by the supplied project record. |
| Parking | No car or two-wheeler parking count or parking-level arrangement is established in the supplied record. RERA filing |
Offering and status
| Field | Record |
|---|---|
| Offering | Plots in a 60-plot tentative layout. The supplied evidence does not provide a plot-by-plot RERA inventory, booked/available counts, or a RERA-filed plot-size schedule. Layout record |
| Layout-derived plot sizes | Software-read from the layout drawing: 60 plots with sizes from 102.91 sq. m to 396.32 sq. m; median 120.02 sq. m. These are drawing-derived measurements, not a RERA-filed unit schedule. Layout record |
| Declared completion | The RERA registration record states proposed completion 30/11/2026; the Form-B declaration gives a completion undertaking of 10th July 2026. RERA record |
| Construction / development stage | The RERA-filed amenity progress entries report varying percentages for selected infrastructure items; they are promoter-reported progress and are not independent site verification. RERA amenities |
| Completion / occupancy certificate | No final layout release, completion certificate, or occupancy certificate is established in the supplied evidence. The approval on file is for a tentative layout. |
2. The project story
RAGHAVENDRA HOMES is registered as a plotted development at Sy. No. 114, Bahadurpet, Alair Mandal, in Yadadri Bhuvanagiri District. Its filed tentative layout approval describes 60 plots and reserves land for plots, roads, open space, social infrastructure, utilities, and a municipal mortgage area. The approval calls for the applicant to carry out the infrastructure works and to hand over specified open-space, utility, and road areas to the municipality by registered gift deed before release of the tentative layout. RERA record RERA filing
The available progress figures are RERA-filed amenity entries rather than an independently inspected construction report. No supplied record establishes that the layout development is complete or that a final layout release or completion/occupancy certificate has been issued. RERA amenities
3. Master plan, architecture & building design
This is a plotted layout, not a building or apartment scheme in the supplied approval. The tentative layout drawing’s area statement records 14,847.09 sq. m as its land-use base and allocates it as follows: plots 9,076.85 sq. m (61.14%); roads 3,913.90 sq. m (26.36%); parks/open space 1,336.38 sq. m (9.00%); utilities 148.48 sq. m (1.00%); social infrastructure 371.48 sq. m (2.50%); and amenities 0.00 sq. m (0.00%). These are drawing-derived figures; the approval document also states its own area figures and terminology. Layout record
The drawing’s plot schedule contains 60 plots. Software-read plot sizes range from 102.91 sq. m to 396.32 sq. m, with a median of 120.02 sq. m. Common printed sizes include 112.88 sq. m (27 plots), 137.96 sq. m (5 plots), and 243.11 sq. m (4 plots). Verify individual plot dimensions and boundaries against the stamped layout before relying on them. Layout record
No apartment tower arrangement, building footprint, floor configuration, or phase-wise building plan is established by the supplied evidence. The tentative approval states that only detached single-family dwelling houses may be built on sites, subject to competent-authority approval; it also states that no shop, business, or industrial use is allowed except on sites specially reserved for such proposals.
4. Homes, configurations & floor plans
The registered offering is plotted, not apartments. The RERA-filed evidence supplied here does not include a plot-by-plot unit schedule or booked/available inventory.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 60 in the tentative layout approval | Not disclosed | Not disclosed | Plot-by-plot RERA schedule not supplied | Not applicable | Not supplied |
The layout drawing’s software-read schedule gives a smallest plot of 102.91 sq. m, a median of 120.02 sq. m, and a largest of 396.32 sq. m. These are plot-area measurements read from the drawing, not apartment carpet-area measurements or a RERA-filed saleable-area schedule. Layout record
The two supplied drawing sheets are layout sheets; no measured apartment floor plans or room dimensions are available. Floor plans
5. Parking & vehicle circulation
The supplied project record does not establish a count or allocation of resident, visitor, accessible, or two-wheeler parking spaces, nor does it show basement, stilt, podium, mechanical, or surface parking. The layout approval identifies internal roads, but a drawn road or plot area does not establish a purchaser’s exclusive parking entitlement. Confirm any plot-specific parking representation in the approved plans and sale documents. Layout record
6. Amenities, recreation & open spaces
The following progress percentages are RERA-filed amenity entries. They are not independent verification of completion. The tentative approval requires infrastructure and handover works; its stated conditions and full scope should be checked against the approval document. RERA amenities
| Description / size | Internal roads and footpaths; layout approval specifies road formation with black top. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 20% reported in RERA amenity data; not independently verified. |
| Description / size | Layout drawing allocates 1,336.38 sq. m (9.00%) to parks/open space. Approval states 0 Acer 13.21 Gts 1598 Sq. Yds for open space. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | 10% reported for Green Strip/TOT LOT/Park; not independently verified. |
| Description / size | 371.48 sq. m (2.50%) in the layout area statement; the approval states 0 Acer 3.67 Gts 444 Sq. Yds. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | No delivered facility or progress is established. |
| Description / size | No area is allocated in the drawing’s amenities row. |
|---|---|
| Evidence source | Layout record RERA amenities |
| Declared progress / verified status | 0% reported; no facility identified as delivered. |
| Description / size | Internal water-supply infrastructure is required by the approval. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 40% reported; not independently verified. |
| Description / size | Approval describes underground drainage lines and a common septic tank/STP. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 10% reported for sewerage; sewage/sullage treatment and disposal is listed at 0%; not independently verified. |
| Description / size | Storm-water drains are part of the approval’s development works. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 30% reported; not independently verified. |
| Description / size | Street lighting is specified in the approval’s development works. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 5% reported; not independently verified. |
7. Utilities, building services & safety
The tentative layout approval lists an assured water-supply source, internal water-supply pipelines, an overhead tank and/or sump, storm-water drains, underground drainage, and a common septic tank/STP. It also lists electrical supply lines, street lights, a transformer, solid-waste management, avenue planting, park development, and rainwater-harvesting pits. These are approval conditions or required development works; the supplied evidence does not establish installed capacity, commissioning, or completed operation.
RERA amenity data reports water supply at 40%, sewerage at 10%, storm-water drains at 30%, street lighting at 5%, and an electrical meter room/sub-station/receiving station at 20%. Solid-waste management and disposal and water conservation/rainwater harvesting are listed at 0%; the entries do not independently verify site completion. RERA amenities
No project-specific capacities or completion evidence are supplied for water storage or treatment, sewage treatment, electrical backup, EV charging, fire-protection systems, security, accessibility, lifts, or building escape routes. The project is a plotted layout in the supplied approval, so apartment-building services such as lifts are not established. RERA amenities
8. Location, access & connectivity
The registered project location is Bahadurpet, Alair Mandal, Yadadri Bhuvanagiri District, Telangana, PIN 508101; the layout approval describes the site as being in Alair Revenue Village. The supplied map coordinate is 17.625619, 79.042096, labelled “Sub Centre, Bahadurpet, NH163, Bahadurpet, Alair mandal, Yadadri Bhuvanagiri, Telangana, 508101, India.” RERA record Location record
The supplied location data lists an approximate 43.1 km distance to the nearest sampled Outer Ring Road interchange. No public-transport details, further measured landmark distances, or verified travel times are supplied. Location record
9. Developer & development status
The registered promoter is AVANAGANTI PANDU AND OTHERS. The supplied RERA record classifies the organization type as “Others” and describes it as a joint development; the legal entity type and corporate identifier are not established in the supplied evidence. The RERA certificate gives the promoter office location as Ranga Reddy District, PIN 500068, but does not supply a complete street address or official contact details. RERA record RERA filing
A Form-B declaration by Avanaganti Pandu, stated to be authorized by the promoter, undertakes completion by 10th July 2026. The project header separately records a proposed completion date of 30/11/2026. These are promoter-filed completion statements; the evidence supplied does not establish actual completion or an extension of registration. RERA record
The TG-RERA certificate records registration through 10/07/2026, while no completion/occupancy certificate or final layout release is supplied.
10. Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration certificate | FORM “C” registration for RAGHAVENDRA HOMES, P02000010924, valid 10/07/2023–10/07/2026; issued 20/06/2026. |
| Tentative layout approval | ALAIR Municipality/Municipal Corporation tentative layout approval, LP No. 0003/LO/3102/2023, dated 07/10/2023; identifies Sy. No. 114 and 60 plots. It states that tentative approval is not proof of title and specifies development and handover conditions. |
| Layout drawing | Two-sheet layout drawing with a plot schedule and land-use area statement; plot areas and distribution cited above are software-read from the drawing. Layout record |
| Form-B declaration | Promoter affidavit/declaration identifying the promoter, title basis, encumbrance declaration, and completion undertaking. |
| Commencement-certificate filing | The supplied OCR is fragmentary and does not identify the approval instrument, authority, land, parties, or terms. It contains references 00303102/2023 and 336/2026; the document does not establish a readable commencement approval. |
| Mortgage deed | Registered mortgage deed 11560/2023 in favour of the municipality, concerning layout plots 53 through 62, measuring 1936 Sq. Yds., as security for completion of layout infrastructure and amenities. |
| Completion / occupancy / final layout release | Not established by the documents supplied. |
1. Project at a glance
Project identity
Registered project name: RAGHAVENDRA HOMES
Project type: Plotted development / tentative residential layout
Phase / registered portion: No separate phase is identified in the supplied record; the registration is for the named project.
TG-RERA registration: P02000010924
Registration validity: 10/07/2023 to 10/07/2026; the certificate records a three-year term and no extension. Validity is distinct from the project completion undertaking and from any completion/occupancy certificate.
Registered promoter: AVANAGANTI PANDU AND OTHERS
RERA status in supplied record: Registered; the certificate records validity through 10/07/2026. The supplied record does not establish the registration’s current status after that date.
Land and geographic identity
Locality / revenue village: Bahadurpet is the RERA-record locality; the filed tentative layout document describes the land as being in Alair Revenue Village. The supplied records therefore identify both names; confirm the revenue-village identity against the underlying land records.
Mandal / district / PIN: Alair Mandal; Yadadri Bhuvanagiri District; PIN 508101.
Project survey number(s): Sy. No. 114; the layout approval identifies no subdivision.
Registered site extent: 15,542.23 sq. m total site area; 14,847.10 sq. m net area; 695.13 sq. m recorded as affected by road widening/FTL of tanks/nala widening.
Layout document’s stated extent: 3 Acer 33.62 Gts 18589 Sq. Yds.
Boundaries: East: agriculture land of Barma Padma; west: road; north: other land; south: other land.
Development identity
Sanctioning authority: ALAIR Municipality/Municipal Corporation; the RERA filing identifies DTCP as the authority for plan approval.
Principal approval: Tentative Layout Plan LP No. 0003/LO/3102/2023, dated 07/10/2023 6:23:06 PM.
Application number: 004374/LO/DTCP/3102/0006/2023.
Approved / plotted area: The RERA-filed project information records approved built-up area of 9076.85 sq. m; the layout drawing identifies this as plotted area. It is not a residential-building gross or carpet area.
Plot count: 60 plots, as stated in the tentative layout approval.
Buildings / floors: Not disclosed as a multi-building or apartment development; no building count or floor configuration is established by the supplied project record.
Parking: No car or two-wheeler parking count or parking-level arrangement is established in the supplied record.
Offering and status
Offering: Plots in a 60-plot tentative layout. The supplied evidence does not provide a plot-by-plot RERA inventory, booked/available counts, or a RERA-filed plot-size schedule.
Layout-derived plot sizes: Software-read from the layout drawing: 60 plots with sizes from 102.91 sq. m to 396.32 sq. m; median 120.02 sq. m. These are drawing-derived measurements, not a RERA-filed unit schedule.
Declared completion: The RERA registration record states proposed completion 30/11/2026; the Form-B declaration gives a completion undertaking of 10th July 2026.
Construction / development stage: The RERA-filed amenity progress entries report varying percentages for selected infrastructure items; they are promoter-reported progress and are not independent site verification.
Completion / occupancy certificate: No final layout release, completion certificate, or occupancy certificate is established in the supplied evidence. The approval on file is for a tentative layout.
2. The project story
RAGHAVENDRA HOMES is registered as a plotted development at Sy. No. 114, Bahadurpet, Alair Mandal, in Yadadri Bhuvanagiri District. Its filed tentative layout approval describes 60 plots and reserves land for plots, roads, open space, social infrastructure, utilities, and a municipal mortgage area. The approval calls for the applicant to carry out the infrastructure works and to hand over specified open-space, utility, and road areas to the municipality by registered gift deed before release of the tentative layout.
The available progress figures are RERA-filed amenity entries rather than an independently inspected construction report. No supplied record establishes that the layout development is complete or that a final layout release or completion/occupancy certificate has been issued.
3. Master plan, architecture & building design
This is a plotted layout, not a building or apartment scheme in the supplied approval. The tentative layout drawing’s area statement records 14,847.09 sq. m as its land-use base and allocates it as follows: plots 9,076.85 sq. m (61.14%); roads 3,913.90 sq. m (26.36%); parks/open space 1,336.38 sq. m (9.00%); utilities 148.48 sq. m (1.00%); social infrastructure 371.48 sq. m (2.50%); and amenities 0.00 sq. m (0.00%). These are drawing-derived figures; the approval document also states its own area figures and terminology.
The drawing’s plot schedule contains 60 plots. Software-read plot sizes range from 102.91 sq. m to 396.32 sq. m, with a median of 120.02 sq. m. Common printed sizes include 112.88 sq. m (27 plots), 137.96 sq. m (5 plots), and 243.11 sq. m (4 plots). Verify individual plot dimensions and boundaries against the stamped layout before relying on them.
No apartment tower arrangement, building footprint, floor configuration, or phase-wise building plan is established by the supplied evidence. The tentative approval states that only detached single-family dwelling houses may be built on sites, subject to competent-authority approval; it also states that no shop, business, or industrial use is allowed except on sites specially reserved for such proposals.
4. Homes, configurations & floor plans
The registered offering is plotted, not apartments. The RERA-filed evidence supplied here does not include a plot-by-plot unit schedule or booked/available inventory.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 60 in the tentative layout approval | Not disclosed | Not disclosed | Plot-by-plot RERA schedule not supplied | Not applicable | Not supplied |
The layout drawing’s software-read schedule gives a smallest plot of 102.91 sq. m, a median of 120.02 sq. m, and a largest of 396.32 sq. m. These are plot-area measurements read from the drawing, not apartment carpet-area measurements or a RERA-filed saleable-area schedule.
The two supplied drawing sheets are layout sheets; no measured apartment floor plans or room dimensions are available.
5. Parking & vehicle circulation
The supplied project record does not establish a count or allocation of resident, visitor, accessible, or two-wheeler parking spaces, nor does it show basement, stilt, podium, mechanical, or surface parking. The layout approval identifies internal roads, but a drawn road or plot area does not establish a purchaser’s exclusive parking entitlement. Confirm any plot-specific parking representation in the approved plans and sale documents.
6. Amenities, recreation & open spaces
The following progress percentages are RERA-filed amenity entries. They are not independent verification of completion. The tentative approval requires infrastructure and handover works; its stated conditions and full scope should be checked against the approval document.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Roads and footpaths | Internal roads and footpaths; layout approval specifies road formation with black top. | 20% reported in RERA amenity data; not independently verified. | |
| Park / open space | Layout drawing allocates 1,336.38 sq. m (9.00%) to parks/open space. Approval states 0 Acer 13.21 Gts 1598 Sq. Yds for open space. | 10% reported for Green Strip/TOT LOT/Park; not independently verified. | |
| Social infrastructure | 371.48 sq. m (2.50%) in the layout area statement; the approval states 0 Acer 3.67 Gts 444 Sq. Yds. | No delivered facility or progress is established. | |
| Community buildings | No area is allocated in the drawing’s amenities row. | 0% reported; no facility identified as delivered. | |
| Water supply | Internal water-supply infrastructure is required by the approval. | 40% reported; not independently verified. | |
| Sewerage / septic / STP | Approval describes underground drainage lines and a common septic tank/STP. | 10% reported for sewerage; sewage/sullage treatment and disposal is listed at 0%; not independently verified. | |
| Storm-water drains | Storm-water drains are part of the approval’s development works. | 30% reported; not independently verified. | |
| Street lighting | Street lighting is specified in the approval’s development works. | 5% reported; not independently verified. |
7. Utilities, building services & safety
The tentative layout approval lists an assured water-supply source, internal water-supply pipelines, an overhead tank and/or sump, storm-water drains, underground drainage, and a common septic tank/STP. It also lists electrical supply lines, street lights, a transformer, solid-waste management, avenue planting, park development, and rainwater-harvesting pits. These are approval conditions or required development works; the supplied evidence does not establish installed capacity, commissioning, or completed operation.
RERA amenity data reports water supply at 40%, sewerage at 10%, storm-water drains at 30%, street lighting at 5%, and an electrical meter room/sub-station/receiving station at 20%. Solid-waste management and disposal and water conservation/rainwater harvesting are listed at 0%; the entries do not independently verify site completion.
No project-specific capacities or completion evidence are supplied for water storage or treatment, sewage treatment, electrical backup, EV charging, fire-protection systems, security, accessibility, lifts, or building escape routes. The project is a plotted layout in the supplied approval, so apartment-building services such as lifts are not established.
8. Location, access & connectivity
The registered project location is Bahadurpet, Alair Mandal, Yadadri Bhuvanagiri District, Telangana, PIN 508101; the layout approval describes the site as being in Alair Revenue Village. The supplied map coordinate is 17.625619, 79.042096, labelled “Sub Centre, Bahadurpet, NH163, Bahadurpet, Alair mandal, Yadadri Bhuvanagiri, Telangana, 508101, India.”
The supplied location data lists an approximate 43.1 km distance to the nearest sampled Outer Ring Road interchange. No public-transport details, further measured landmark distances, or verified travel times are supplied.
9. Developer & development status
The registered promoter is AVANAGANTI PANDU AND OTHERS. The supplied RERA record classifies the organization type as “Others” and describes it as a joint development; the legal entity type and corporate identifier are not established in the supplied evidence. The RERA certificate gives the promoter office location as Ranga Reddy District, PIN 500068, but does not supply a complete street address or official contact details.
A Form-B declaration by Avanaganti Pandu, stated to be authorized by the promoter, undertakes completion by 10th July 2026. The project header separately records a proposed completion date of 30/11/2026. These are promoter-filed completion statements; the evidence supplied does not establish actual completion or an extension of registration.
The TG-RERA certificate records registration through 10/07/2026, while no completion/occupancy certificate or final layout release is supplied.
10. Approvals, official records & documents
TG-RERA registration certificate: FORM “C” registration for RAGHAVENDRA HOMES, P02000010924, valid 10/07/2023–10/07/2026; issued 20/06/2026.
Tentative layout approval: ALAIR Municipality/Municipal Corporation tentative layout approval, LP No. 0003/LO/3102/2023, dated 07/10/2023; identifies Sy. No. 114 and 60 plots. It states that tentative approval is not proof of title and specifies development and handover conditions.
Layout drawing: Two-sheet layout drawing with a plot schedule and land-use area statement; plot areas and distribution cited above are software-read from the drawing.
Form-B declaration: Promoter affidavit/declaration identifying the promoter, title basis, encumbrance declaration, and completion undertaking.
Commencement-certificate filing: The supplied OCR is fragmentary and does not identify the approval instrument, authority, land, parties, or terms. It contains references 00303102/2023 and 336/2026; the document does not establish a readable commencement approval.
Mortgage deed: Registered mortgage deed 11560/2023 in favour of the municipality, concerning layout plots 53 through 62, measuring 1936 Sq. Yds., as security for completion of layout infrastructure and amenities.
Completion / occupancy / final layout release: Not established by the documents supplied.
Frequently asked questions
Is RAGHAVENDRA HOMES registered with Telangana RERA?
Yes. RAGHAVENDRA HOMES is registered with the Telangana Real Estate Regulatory Authority as P02000010924; the registration status is New Project.
Who is the developer of RAGHAVENDRA HOMES?
The promoter named in the RERA registration is AVANAGANTI PANDU AND OTHERS.
Where is RAGHAVENDRA HOMES located?
RAGHAVENDRA HOMES is in Alair, Bahadurpet, Yadadri Bhuvanagiri, Telangana (508101).
When will RAGHAVENDRA HOMES be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.