Highland
BOTCHA SANDEEP AND OTHERS · Rangareddy · RERA P02400010142
Highland is a new plotted/open-layout residential development in Maheshwaram, Maheshwaram Mandal, Ranga Reddy District. It is being developed by BOTCHA SANDEEP AND OTHERS on a total site area of 35,754.95 sq.m. The RERA-filed layout records 20,123.54 sq.m of plotted area; the supplied record does not state a plot count, plot-size configurations, or buildings and floors. Highland is registered with TG-RERA under P02400010142, with a proposed completion date of 04/11/2028.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | Highland RERA record |
| Project type | New plotted/open-layout residential development RERA record |
| Phase / registered portion | No phase designation is identified in the supplied record; the registration is for the listed layout and land RERA record |
| TG-RERA registration | P02400010142 RERA record |
| Registration validity | 04/07/2025 to 04/07/2028 (three years, unless extended by the Authority) RERA record |
| Registered promoter | BOTCHA SANDEEP AND OTHERS RERA record |
| RERA status | Registered; the supplied record does not identify a later extension, lapse or revocation RERA record Approvals record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Maheshwaram / Maheshwaram Revenue Village RERA record |
| Mandal | Maheshwaram RERA record |
| District | Ranga Reddy RERA record |
| PIN | 501359 RERA record |
| Project survey numbers and subdivisions | 470/1/1/3, 471/1/1/3, 472/2, 472/1, 473/1/2, 479, 473/1/1, 480/-/2, 473, 471/1/1/2, 470/1/1/2, 471/2, 470/2, 470/1/2 and 471/1/2. The registration certificate and drawing/OCR also render the 480 subdivision as “480-/2” or “480/?/2”; verify the exact survey notation against the registered land schedule. RERA record |
| Total site area | 35,754.95 sq.m Land records |
| Road-affected area | 668.87 sq.m Land records |
| Net site area | 32,224.93 sq.m in the HMDA draft layout record |
| Boundaries | East: Check Dam; West: Others Land; North: Others Land; South: Road RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA) Approvals record |
| Principal layout approval | HMDA Draft Layout Letter / Layout Permit 000047/LO/Plg/HMDA/2025, dated 04 July 2025 Approvals record |
| Filed plan type | “Plan Showing the Proposed Residential Draft Layout”; open-layout/plotted residential use |
| Approved built-up area | 20,123.54 sq.m is recorded as “Approved Built up Area” in the RERA filing; it is identified in the layout land-use statement as plotted area, not as apartment-building floor area. RERA filing Layout record |
| Buildings / floors | Not disclosed as buildings or floor configurations; this is a plotted layout, not a multi-storey building scheme. RERA record |
| Parking | No project-wide parking-space count or parking-level plan is established in the supplied RERA layout records. RERA amenities |
| Layout land use | RERA-filed drawing states: Plotted Area 20,123.54 sq.m; Road Area 8,453.15 sq.m; “Organized open space/park Area/Utility Area” 2,829.18 sq.m; Social Infrastructure Area 819.18 sq.m; Amenity Area Total 3,530.02 sq.m; Buffer Zone Area 2,861.15 sq.m. |
Offering and status
| Item | Project record |
|---|---|
| Offering | Residential plots; plot count, plot-size schedule and plot-by-plot availability are not established by the supplied RERA data. RERA record Layout record |
| RERA booked / available counts | Not disclosed in the supplied evidence. RERA record RERA amenities |
| Construction / development stage | HMDA draft layout permission is recorded, followed by a Gram Panchayath Maheshwaram releasing order dated 25/08/2025. No independently verified on-site completion percentage is supplied. |
| Completion dates | Form B promoter declaration: 03-Jul-2028; RERA header proposed completion: 04/11/2028. These are separately recorded dates; this overview does not resolve the difference. RERA record |
| Registration validity versus completion | Registration validity runs to 04/07/2028 unless extended; this is distinct from the two completion dates recorded above. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. The record concerns a plotted layout; the supplied documents do not establish a certificate for the layout or any building. Document index |
The project story
Highland is registered with TG-RERA as a new residential plotted development at Maheshwaram, Maheshwaram Mandal, Ranga Reddy District. Its registered land identity comprises the survey numbers and subdivisions listed above, and the RERA record describes a total site area of 35,754.95 sq.m, including a road-affected area of 668.87 sq.m. The HMDA drawing identifies a net site area of 32,224.93 sq.m. RERA record Land records
The approval record is for an open-plot layout, not apartments or villas. It shows residential plots, internal roads and land designated for open space/park, social infrastructure, utilities and amenities. The promoter’s Form B affidavit declares completion by 03-Jul-2028; the RERA header separately records a proposed completion date of 04/11/2028. No site-verified progress measurement is provided, so the approval and declarations should not be read as proof that layout works are complete. RERA record
Master plan, architecture & building design
The project is organized as a plotted layout. The RERA-filed layout drawing identifies 32,224.93 sq.m as net area and 20,123.54 sq.m as plotted area. It also records 8,453.15 sq.m of layout roads, 2,829.18 sq.m under the combined “Organized open space/park Area/Utility Area” line, and 819.18 sq.m of social infrastructure area. The same drawing separately lists 3,530.02 sq.m as total amenity area and 2,861.15 sq.m as buffer-zone area.
The drawing labels the land use as residential and the development as an open layout. It shows road-width entries of 12.00 and 7.62m; the HMDA draft-layout extraction separately records an abutting road width of 12.00 and refers to roads “18 mts and above.” No building count, floor configuration, building footprint, apartment arrangement or tower design is established for this plotted project.
Homes, configurations & floor plans
The RERA record describes a plotted residential offering. The supplied evidence does not provide a complete RERA unit/plot inventory, plot-size range, booked-versus-available counts, or plot-specific saleable areas. The available drawing is a layout sheet, not a unit floor plan; no measured carpet-area or room-configuration data applies to the plots. RERA record Layout record Floor plans
A third-party vendor record contains apartment-style configurations and amenity claims, but those are not used here to describe the TG-RERA-registered plotted offering. Promoter website
Parking & vehicle circulation
The layout drawing identifies roads and road widths, but the supplied RERA evidence does not establish a total parking count, dedicated visitor or accessible parking, parking allocation to individual plots, or parking facilities by type. No car-park level, ramp, EV-charging provision or exclusive parking right is documented in the supplied project records. RERA amenities
Amenities, recreation & open spaces
The RERA-filed layout drawing identifies the following facilities and land-use provisions. The “available” entries in the RERA amenities register are recorded as project provisions; each listed progress value is 0%. The evidence supplied does not independently verify completed facilities. RERA amenities
| Description / size | Park area 2,829.18 sq.m in the HMDA layout land-use statement; the drawing also groups organized open space/park/utility area as 2,829.18 sq.m. |
|---|---|
| Evidence source | HMDA draft layout and RERA amenities register RERA amenities |
| Declared progress / verified status | Park/green-strip provision marked available; 0% progress in the RERA amenities register; not independently verified complete. |
| Description / size | 819.18 sq.m in the HMDA land-use statement. |
|---|---|
| Evidence source | HMDA draft layout |
| Declared progress / verified status | Land provision shown; community-building progress is 0% in the RERA amenities register. |
| Description / size | Shown as a layout land-use provision; no standalone area is reliably established by the combined open-space/park/utility line. |
|---|---|
| Evidence source | HMDA draft layout |
| Declared progress / verified status | Provision shown; completion not independently verified. |
| Description / size | Drawing states 3,530.02 sq.m total amenity area. |
|---|---|
| Evidence source | RERA-filed layout drawing |
| Declared progress / verified status | The HMDA draft layout extraction separately records amenities area as 0; delivery/status is not established here. |
| Description / size | Layout roads 8,453.15 sq.m in the HMDA land-use statement. |
|---|---|
| Evidence source | HMDA draft layout and RERA amenities register RERA amenities |
| Declared progress / verified status | Marked available; 0% progress in the RERA amenities register; not independently verified complete. |
| Description / size | Layout drawing labels internal water-supply pipelines and an overhead water tank; the amenities register marks water supply available. |
|---|---|
| Evidence source | RERA-filed layout drawing and amenities register RERA amenities |
| Declared progress / verified status | Marked available; 0% progress; not independently verified complete. |
| Description / size | Layout drawing specifies a common septic tank; HMDA conditions refer to underground drainage and a common septic tank / STP. |
|---|---|
| Evidence source | RERA-filed layout drawing and HMDA draft-layout conditions |
| Declared progress / verified status | Provision specified; no completion verification supplied. |
| Description / size | “Garbage Pit” appears in the layout drawing; the amenities register includes solid waste management and disposal. RERA amenities |
|---|---|
| Evidence source | RERA-filed layout drawing and amenities register RERA amenities |
| Declared progress / verified status | No completed-status evidence; amenities-register progress 0%. |
| Description / size | Rainwater-harvesting pits are specified in the HMDA draft-layout conditions; the amenities register lists water conservation/rainwater harvesting. RERA amenities |
|---|---|
| Evidence source | HMDA draft layout and RERA amenities register RERA amenities |
| Declared progress / verified status | No completed-status evidence; amenities-register progress 0%. |
| Description / size | Distribution transformer is shown in the layout drawing; the RERA amenities register marks an electrical meter room/sub-station/receiving station available. RERA amenities |
|---|---|
| Evidence source | RERA-filed layout drawing and amenities register RERA amenities |
| Declared progress / verified status | Marked available in the register; 0% progress; not independently verified complete. |
| Description / size | HMDA conditions specify street lights and avenue plantation. |
|---|---|
| Evidence source | HMDA draft-layout conditions |
| Declared progress / verified status | Required development works; completion not independently verified. |
Utilities, building services & safety
The layout drawing and HMDA draft-layout conditions specify internal water-supply pipelines, an overhead water tank, an assured water-supply source, underground drainage lines, a common septic tank / STP, storm-water drains, rainwater-harvesting pits, electrical supply lines, street lights and a transformer. These are recorded as layout provisions or required development works; the supplied evidence does not establish their completed status, capacities, or operating performance.
Fire protection and fire-safety requirements appear in the RERA amenities register, but progress is recorded as 0% and no project-specific fire clearance or completed fire-safety installation is supplied. The record does not establish building lifts, accessibility features, CCTV, security arrangements, backup power, or other building services for the plotted layout. RERA amenities Document index
Location, access & connectivity
The registered location is Maheshwaram Revenue Village, Maheshwaram Mandal, Ranga Reddy District, Telangana, PIN 501359. The supplied project boundaries identify a road to the south, a check dam to the east, and other land to the north and west. The HMDA drawing identifies a 12.00 abutting-road-width entry and internal road-width entries of 12.00 and 7.62m. RERA record RERA filing
The location record provides one measured connectivity reference: the nearest sampled Outer Ring Road interchange is approximately 10.8 km away. The supplied RERA project record does not provide travel times or a broader public-transport or landmark-distance schedule. Location record
Developer & development status
The registered promoter is BOTCHA SANDEEP AND OTHERS, with organization type recorded as “Others”; the legal entity type is not further established in the supplied records. Botcha Sandeep is identified as an authorized signatory in the promoter’s Form B affidavit, dated 25-August-2025. RERA record Corporate record
The promoter declares that the project will be completed by 03-Jul-2028 and that project funds will be handled under the separate-account arrangements described in the affidavit. The RERA header records 04/11/2028 as the proposed completion date. No construction-progress certificate, site inspection result, or independently verified completion status is supplied. The RERA certificate’s registration validity is separately stated as ending 04/07/2028, unless extended. RERA record
Approvals, official records & documents
| Identifier / date | P02400010142; validity 04/07/2025–04/07/2028 |
|---|---|
| What it establishes | Registration of Highland under the named promoter, with project location and land identity. |
| Identifier / date | Permit 000047/LO/Plg/HMDA/2025, approved 04 July 2025; application 056744/SMD/LT/U6/HMDA/13092022 |
|---|---|
| What it establishes | Draft open-layout permission and stated land-use, mortgage and layout-development conditions. The drawing is dated 04-07-2025. |
| Identifier / date | GPM/LAYOUT/2025, dated 25/08/2025; proceedings number recorded as 000047/LO/PIg/HMDA/2025 |
|---|---|
| What it establishes | Local-body releasing order for the stated layout area, directing compliance with HMDA’s draft proceedings and conditions. |
| Identifier / date | Dated 25-August-2025 |
|---|---|
| What it establishes | Promoter declaration on title, encumbrances, funds, approvals and a completion undertaking of 03-Jul-2028. |
| Identifier / date | One sheet, scale 1:600, sheet 01/01 |
|---|---|
| What it establishes | RERA-filed layout drawing, land-use schedule, layout features and recorded plot mortgages. |
| Identifier / date | Documents 10090/2025 and 10089/2025, dated 09/06/2025 |
|---|---|
| What it establishes | HMDA security over specified plots for layout-development obligations. |
| Identifier / date | Document 10088/2025, dated 09.06.2025 |
|---|---|
| What it establishes | Gift-deed reference for roads, park, social infrastructure, utility and road-widening areas to the local body. |
| Identifier / date | Document 10321 / 2025 |
|---|---|
| What it establishes | The releasing-order record cites a gift deed for land areas in favour of Gram Panchayath Maheshwaram. |
| Identifier / date | Not supplied as a distinct project certificate in the evidence reviewed Document index |
|---|---|
| What it establishes | No building commencement certificate, occupancy certificate or completion certificate is established by the supplied record. |
The HMDA document is expressly described as a draft layout and records development conditions, including completing specified layout works within three years. The Gram Panchayath order is recorded as a releasing order subject to HMDA’s terms. The supplied documents do not establish that the required layout works have been completed or that a final occupancy/completion certificate has been issued.
Project at a glance
Project identity
Registered project name: Highland
Project type: New plotted/open-layout residential development
Phase / registered portion: No phase designation is identified in the supplied record; the registration is for the listed layout and land
TG-RERA registration: P02400010142
Registration validity: 04/07/2025 to 04/07/2028 (three years, unless extended by the Authority)
Registered promoter: BOTCHA SANDEEP AND OTHERS
RERA status: Registered; the supplied record does not identify a later extension, lapse or revocation
Land and geographic identity
Locality / revenue village: Maheshwaram / Maheshwaram Revenue Village
Mandal: Maheshwaram
District: Ranga Reddy
PIN: 501359
Project survey numbers and subdivisions: 470/1/1/3, 471/1/1/3, 472/2, 472/1, 473/1/2, 479, 473/1/1, 480/-/2, 473, 471/1/1/2, 470/1/1/2, 471/2, 470/2, 470/1/2 and 471/1/2. The registration certificate and drawing/OCR also render the 480 subdivision as “480-/2” or “480/?/2”; verify the exact survey notation against the registered land schedule.
Total site area: 35,754.95 sq.m
Road-affected area: 668.87 sq.m
Net site area: 32,224.93 sq.m in the HMDA draft layout record
Boundaries: East: Check Dam; West: Others Land; North: Others Land; South: Road
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA)
Principal layout approval: HMDA Draft Layout Letter / Layout Permit 000047/LO/Plg/HMDA/2025, dated 04 July 2025
Filed plan type: “Plan Showing the Proposed Residential Draft Layout”; open-layout/plotted residential use
Approved built-up area: 20,123.54 sq.m is recorded as “Approved Built up Area” in the RERA filing; it is identified in the layout land-use statement as plotted area, not as apartment-building floor area.
Buildings / floors: Not disclosed as buildings or floor configurations; this is a plotted layout, not a multi-storey building scheme.
Parking: No project-wide parking-space count or parking-level plan is established in the supplied RERA layout records.
Layout land use: RERA-filed drawing states: Plotted Area 20,123.54 sq.m; Road Area 8,453.15 sq.m; “Organized open space/park Area/Utility Area” 2,829.18 sq.m; Social Infrastructure Area 819.18 sq.m; Amenity Area Total 3,530.02 sq.m; Buffer Zone Area 2,861.15 sq.m.
Offering and status
Offering: Residential plots; plot count, plot-size schedule and plot-by-plot availability are not established by the supplied RERA data.
RERA booked / available counts: Not disclosed in the supplied evidence.
Construction / development stage: HMDA draft layout permission is recorded, followed by a Gram Panchayath Maheshwaram releasing order dated 25/08/2025. No independently verified on-site completion percentage is supplied.
Completion dates: Form B promoter declaration: 03-Jul-2028; RERA header proposed completion: 04/11/2028. These are separately recorded dates; this overview does not resolve the difference.
Registration validity versus completion: Registration validity runs to 04/07/2028 unless extended; this is distinct from the two completion dates recorded above.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. The record concerns a plotted layout; the supplied documents do not establish a certificate for the layout or any building.
The project story
Highland is registered with TG-RERA as a new residential plotted development at Maheshwaram, Maheshwaram Mandal, Ranga Reddy District. Its registered land identity comprises the survey numbers and subdivisions listed above, and the RERA record describes a total site area of 35,754.95 sq.m, including a road-affected area of 668.87 sq.m. The HMDA drawing identifies a net site area of 32,224.93 sq.m.
The approval record is for an open-plot layout, not apartments or villas. It shows residential plots, internal roads and land designated for open space/park, social infrastructure, utilities and amenities. The promoter’s Form B affidavit declares completion by 03-Jul-2028; the RERA header separately records a proposed completion date of 04/11/2028. No site-verified progress measurement is provided, so the approval and declarations should not be read as proof that layout works are complete.
Master plan, architecture & building design
The project is organized as a plotted layout. The RERA-filed layout drawing identifies 32,224.93 sq.m as net area and 20,123.54 sq.m as plotted area. It also records 8,453.15 sq.m of layout roads, 2,829.18 sq.m under the combined “Organized open space/park Area/Utility Area” line, and 819.18 sq.m of social infrastructure area. The same drawing separately lists 3,530.02 sq.m as total amenity area and 2,861.15 sq.m as buffer-zone area.
The drawing labels the land use as residential and the development as an open layout. It shows road-width entries of 12.00 and 7.62m; the HMDA draft-layout extraction separately records an abutting road width of 12.00 and refers to roads “18 mts and above.” No building count, floor configuration, building footprint, apartment arrangement or tower design is established for this plotted project.
Homes, configurations & floor plans
The RERA record describes a plotted residential offering. The supplied evidence does not provide a complete RERA unit/plot inventory, plot-size range, booked-versus-available counts, or plot-specific saleable areas. The available drawing is a layout sheet, not a unit floor plan; no measured carpet-area or room-configuration data applies to the plots.
A third-party vendor record contains apartment-style configurations and amenity claims, but those are not used here to describe the TG-RERA-registered plotted offering.
Parking & vehicle circulation
The layout drawing identifies roads and road widths, but the supplied RERA evidence does not establish a total parking count, dedicated visitor or accessible parking, parking allocation to individual plots, or parking facilities by type. No car-park level, ramp, EV-charging provision or exclusive parking right is documented in the supplied project records.
Amenities, recreation & open spaces
The RERA-filed layout drawing identifies the following facilities and land-use provisions. The “available” entries in the RERA amenities register are recorded as project provisions; each listed progress value is 0%. The evidence supplied does not independently verify completed facilities.
| Description / size | Park area 2,829.18 sq.m in the HMDA layout land-use statement; the drawing also groups organized open space/park/utility area as 2,829.18 sq.m. |
|---|---|
| Evidence source | HMDA draft layout and RERA amenities register |
| Declared progress / verified status | Park/green-strip provision marked available; 0% progress in the RERA amenities register; not independently verified complete. |
| Description / size | 819.18 sq.m in the HMDA land-use statement. |
|---|---|
| Evidence source | HMDA draft layout |
| Declared progress / verified status | Land provision shown; community-building progress is 0% in the RERA amenities register. |
| Description / size | Shown as a layout land-use provision; no standalone area is reliably established by the combined open-space/park/utility line. |
|---|---|
| Evidence source | HMDA draft layout |
| Declared progress / verified status | Provision shown; completion not independently verified. |
| Description / size | Drawing states 3,530.02 sq.m total amenity area. |
|---|---|
| Evidence source | RERA-filed layout drawing |
| Declared progress / verified status | The HMDA draft layout extraction separately records amenities area as 0; delivery/status is not established here. |
| Description / size | Layout roads 8,453.15 sq.m in the HMDA land-use statement. |
|---|---|
| Evidence source | HMDA draft layout and RERA amenities register |
| Declared progress / verified status | Marked available; 0% progress in the RERA amenities register; not independently verified complete. |
| Description / size | Layout drawing labels internal water-supply pipelines and an overhead water tank; the amenities register marks water supply available. |
|---|---|
| Evidence source | RERA-filed layout drawing and amenities register |
| Declared progress / verified status | Marked available; 0% progress; not independently verified complete. |
| Description / size | Layout drawing specifies a common septic tank; HMDA conditions refer to underground drainage and a common septic tank / STP. |
|---|---|
| Evidence source | RERA-filed layout drawing and HMDA draft-layout conditions |
| Declared progress / verified status | Provision specified; no completion verification supplied. |
| Description / size | “Garbage Pit” appears in the layout drawing; the amenities register includes solid waste management and disposal. |
|---|---|
| Evidence source | RERA-filed layout drawing and amenities register |
| Declared progress / verified status | No completed-status evidence; amenities-register progress 0%. |
| Description / size | Rainwater-harvesting pits are specified in the HMDA draft-layout conditions; the amenities register lists water conservation/rainwater harvesting. |
|---|---|
| Evidence source | HMDA draft layout and RERA amenities register |
| Declared progress / verified status | No completed-status evidence; amenities-register progress 0%. |
| Description / size | Distribution transformer is shown in the layout drawing; the RERA amenities register marks an electrical meter room/sub-station/receiving station available. |
|---|---|
| Evidence source | RERA-filed layout drawing and amenities register |
| Declared progress / verified status | Marked available in the register; 0% progress; not independently verified complete. |
| Description / size | HMDA conditions specify street lights and avenue plantation. |
|---|---|
| Evidence source | HMDA draft-layout conditions |
| Declared progress / verified status | Required development works; completion not independently verified. |
Utilities, building services & safety
The layout drawing and HMDA draft-layout conditions specify internal water-supply pipelines, an overhead water tank, an assured water-supply source, underground drainage lines, a common septic tank / STP, storm-water drains, rainwater-harvesting pits, electrical supply lines, street lights and a transformer. These are recorded as layout provisions or required development works; the supplied evidence does not establish their completed status, capacities, or operating performance.
Fire protection and fire-safety requirements appear in the RERA amenities register, but progress is recorded as 0% and no project-specific fire clearance or completed fire-safety installation is supplied. The record does not establish building lifts, accessibility features, CCTV, security arrangements, backup power, or other building services for the plotted layout.
Location, access & connectivity
The registered location is Maheshwaram Revenue Village, Maheshwaram Mandal, Ranga Reddy District, Telangana, PIN 501359. The supplied project boundaries identify a road to the south, a check dam to the east, and other land to the north and west. The HMDA drawing identifies a 12.00 abutting-road-width entry and internal road-width entries of 12.00 and 7.62m.
The location record provides one measured connectivity reference: the nearest sampled Outer Ring Road interchange is approximately 10.8 km away. The supplied RERA project record does not provide travel times or a broader public-transport or landmark-distance schedule.
Developer & development status
The registered promoter is BOTCHA SANDEEP AND OTHERS, with organization type recorded as “Others”; the legal entity type is not further established in the supplied records. Botcha Sandeep is identified as an authorized signatory in the promoter’s Form B affidavit, dated 25-August-2025.
The promoter declares that the project will be completed by 03-Jul-2028 and that project funds will be handled under the separate-account arrangements described in the affidavit. The RERA header records 04/11/2028 as the proposed completion date. No construction-progress certificate, site inspection result, or independently verified completion status is supplied. The RERA certificate’s registration validity is separately stated as ending 04/07/2028, unless extended.
Approvals, official records & documents
| Identifier / date | P02400010142; validity 04/07/2025–04/07/2028 |
|---|---|
| What it establishes | Registration of Highland under the named promoter, with project location and land identity. |
| Identifier / date | Permit 000047/LO/Plg/HMDA/2025, approved 04 July 2025; application 056744/SMD/LT/U6/HMDA/13092022 |
|---|---|
| What it establishes | Draft open-layout permission and stated land-use, mortgage and layout-development conditions. The drawing is dated 04-07-2025. |
| Identifier / date | GPM/LAYOUT/2025, dated 25/08/2025; proceedings number recorded as 000047/LO/PIg/HMDA/2025 |
|---|---|
| What it establishes | Local-body releasing order for the stated layout area, directing compliance with HMDA’s draft proceedings and conditions. |
| Identifier / date | Dated 25-August-2025 |
|---|---|
| What it establishes | Promoter declaration on title, encumbrances, funds, approvals and a completion undertaking of 03-Jul-2028. |
| Identifier / date | One sheet, scale 1:600, sheet 01/01 |
|---|---|
| What it establishes | RERA-filed layout drawing, land-use schedule, layout features and recorded plot mortgages. |
| Identifier / date | Documents 10090/2025 and 10089/2025, dated 09/06/2025 |
|---|---|
| What it establishes | HMDA security over specified plots for layout-development obligations. |
| Identifier / date | Document 10088/2025, dated 09.06.2025 |
|---|---|
| What it establishes | Gift-deed reference for roads, park, social infrastructure, utility and road-widening areas to the local body. |
| Identifier / date | Document 10321 / 2025 |
|---|---|
| What it establishes | The releasing-order record cites a gift deed for land areas in favour of Gram Panchayath Maheshwaram. |
| Identifier / date | Not supplied as a distinct project certificate in the evidence reviewed |
|---|---|
| What it establishes | No building commencement certificate, occupancy certificate or completion certificate is established by the supplied record. |
The HMDA document is expressly described as a draft layout and records development conditions, including completing specified layout works within three years. The Gram Panchayath order is recorded as a releasing order subject to HMDA’s terms. The supplied documents do not establish that the required layout works have been completed or that a final occupancy/completion certificate has been issued.
Frequently asked questions
Is Highland registered with Telangana RERA?
Yes. Highland is registered with the Telangana Real Estate Regulatory Authority as P02400010142; the registration status is New Project.
Who is the developer of Highland?
The promoter named in the RERA registration is BOTCHA SANDEEP AND OTHERS.
Where is Highland located?
Highland is in MAHESWARAM, Maheshwaram, Rangareddy, Telangana (501359).
When will Highland be completed?
The promoter's proposed date of completion filed with RERA is 04/11/2028. This is the promoter's declaration, not a guarantee.