True Pride Bacharam
SRI SURYA DEVELOPERS · Rangareddy · RERA P02400001545
TRUE PRIDE BACHARAM is a plotted development in Bacharam village, Abdullapurmet mandal, Ranga Reddy district, developed by registered promoter SRI SURYA DEVELOPERS. The RERA record states a total land area of 182203.74 sqmts and net area of 176059.00 sqmts; HMDA’s draft-layout approval identifies 68 plots on Ac. 45-20 Gts. No building or floor configuration, plot-size range, or RERA-filed plot count is provided. Its TG-RERA registration is P02400001545, issued 27/12/2019, with proposed completion on 02/11/2022.
More from Sri Surya Developers · 2 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | TRUE PRIDE BACHARAM RERA record |
| Project type | Plotted development; the HMDA document describes a draft residential layout of open plots. RERA record RERA filing |
| Phase / registered portion | Phase not separately identified in the supplied record. The registered land is identified in Survey Nos. 73/P, 74, 75 and 76. RERA record |
| TG-RERA registration | P02400001545, issued 27/12/2019; the certificate states validity from 27/12/2019 to 02/11/2022. RERA record |
| Registered promoter | SRI SURYA DEVELOPERS; the project record identifies the entity as a partnership. RERA record Corporate record |
| RERA status | The registration certificate records the stated validity period; the supplied certificate says it was not extended. Current registration status is not independently established by the supplied material. |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Bacharam (also stated as Bacharam village). RERA record RERA filing |
| Mandal / district / PIN | Abdullapurmet / Ranga Reddy / 509412. RERA record |
| Project survey numbers | 73/P, 74, 75 and 76. RERA record |
| Registered site extent | The RERA land record states 182203.74 sqmts total area, 6144.74 sqmts affected in road widening/FTL of tanks/Nala widening, and 176059.00 sqmts net area. RERA filing |
| HMDA draft-layout extent | Ac. 45-20 Gts. |
| Boundaries recorded in RERA fields | North: ROAD WIDTH 50; south, east and west: OTHER LAND. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA). RERA record |
| Principal approval | 07/L0/PL/HMDA/2019, approved 02-11-2019; file reference Letter No.301160/LO/Plg/HMDA/2016. The supplied document describes this as draft residential-layout approval. Approvals record |
| Approved built-up area | 108170.24 sqmts is recorded in the project fields as approved built-up area; the supplied layout-approval extraction does not explain its detailed basis. RERA filing |
| Plots / layout organization | HMDA’s draft approval identifies 68 plots and lists roads, open space, utility and social-infrastructure areas. The supplied materials do not establish the total approved plot count or provide an approved-layout drawing for plot-by-plot review. |
| Buildings / floors | Not disclosed in the supplied project record. This is a plotted layout, and no building or floor configuration is provided. RERA record Document index |
| Parking provision | No project parking count or parking-level arrangement is established by the supplied RERA fields or extracted approval. RERA filing |
Offering and status
| Field | Project record |
|---|---|
| RERA offering | Plots; no RERA-filed plot-count, plot-size range, or plot-wise inventory is supplied in the evidence provided for this overview. RERA record RERA filing |
| Booked / available counts | Not established by the supplied RERA data. RERA filing |
| Construction / development stage | The RERA record gives a proposed completion date of 02/11/2022 and an overall completeness figure of 80%; the basis and inspection date for that percentage are not supplied, so it is not treated here as independently verified site progress. RERA record |
| Completion deadline | Promoter-declared completion undertaking: 02/11/2022. |
| Occupancy / completion certificate | Not supplied. The record does not establish an occupancy or completion certificate for the layout. Document index |
2. The project story
TRUE PRIDE BACHARAM is registered as a plotted residential development in Bacharam village, Abdullapurmet mandal, Ranga Reddy district, on Survey Nos. 73/P, 74, 75 and 76. Its TG-RERA registration is P02400001545. RERA record
The project record describes land of 182203.74 sqmts in total, with a recorded net area of 176059.00 sqmts after an affected-area entry of 6144.74 sqmts. HMDA’s 02-11-2019 document records draft-layout approval for Ac. 45-20 Gts. and identifies 68 plots. The extracted approval is conditional: among its terms, plots identified as mortgaged to HMDA are restricted from sale until release and final-layout processes are completed, and specified open-space, utility, social-infrastructure and road areas are to be handed over by registered gift deed. RERA filing
The promoter’s RERA filing undertook completion by 02/11/2022. The project record also reports 80% completeness, but the supplied evidence does not give the date, measurement method or independent site verification underlying that figure. No completion/occupancy certificate or current plot-wise construction/development status is supplied. RERA record Document index
3. Master plan, architecture & building design
This is a plotted-layout project, not a building or apartment development in the supplied RERA record. HMDA’s draft approval identifies 68 plots on Ac. 45-20 Gts. in Survey Nos. 73/P, 74, 75 and 76 at Bacharam village. It records the following layout components:
| Layout component | Area / description | Evidence |
|---|---|---|
| Open space | 13794.80 Sq.Mtrs | HMDA draft-layout approval, p2 |
| Utility area | 594 Sq,Mtrs | HMDA draft-layout approval, p2 |
| Social Infrastructure area | 4469.65 Sq.Mtrs. | HMDA draft-layout approval, p2 |
| Roads area | 52230.25Sq.Mtrs. | HMDA draft-layout approval, p2 |
| Area affected under H.T. Line | 3099.73 Sq.Mtrs. | HMDA draft-layout approval, p2 |
| Road width noted | 100' wide road | HMDA draft-layout approval |
The RERA fields separately state total area 182203.74 sqmts, affected area 6144.74 sqmts, net area 176059.00 sqmts, and approved built-up area 108170.24 sqmts. The supplied evidence does not provide a drawing-based reconciliation of those area figures or a plot schedule from which individual plot sizes, layout arrangement or land-use allocation can be checked. RERA filing RERA filing
No building count, floor configuration, tower arrangement, building footprint, apartment circulation or building-level plans are provided. The HMDA approval document says construction is not to be allowed on plots until HMDA issues the final layout.
4. Homes, configurations & floor plans
The RERA evidence identifies the offering as plots, but does not provide a RERA-filed plot inventory, plot-size bands, booked/available plot counts or plot-wise saleable areas in the supplied materials. RERA record RERA filing
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not supplied |
The floor-plan dataset contains two drawings, both scans pending; none have been measured. Apartment carpet-area measurements therefore do not apply to the evidence available for this plotted project. Floor plans
5. Parking & vehicle circulation
The supplied RERA record and extracted HMDA approval do not establish a parking-space count, visitor or accessible parking provision, parking allocation to plots, or a parking-level arrangement. HMDA’s approval records a 100' wide road and a roads area of 52230.25Sq.Mtrs.; it also requires roads to be opened for access to neighboring sites. These are layout-road records, not evidence of individual plot parking or an exclusive parking right.
6. Amenities, recreation & open spaces
The RERA amenity register lists proposed/common infrastructure items, but the supplied progress figures are 0 where recorded; these are not evidence of completed or independently inspected facilities. HMDA’s draft approval separately specifies layout areas and handover conditions. RERA amenities
| Description / size | Listed in the RERA amenity register; no size or detailed specification supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0; completion not verified. |
| Description / size | Listed in the RERA amenity register. HMDA approval records open space of 13794.80 Sq.Mtrs. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Amenity progress recorded as 0; HMDA requires development of open space and transfer by registered gift deed before final layout release. Delivery is not verified. |
| Description / size | Aggregate area of recreational open space is listed; no separate size beyond the HMDA open-space figure is supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0; completion not verified. |
| Description / size | 594 Sq,Mtrs in the HMDA approval. |
|---|---|
| Declared progress / verified status | HMDA approval requires handover by registered gift deed before final layout release; completion/handover not verified. |
| Description / size | 4469.65 Sq.Mtrs. in the HMDA approval. |
|---|---|
| Declared progress / verified status | Handover is specified as a condition; completion/handover not verified. |
| Description / size | Vendor listings mention a clubhouse, swimming pool, park and children’s play areas, among other amenities. These are vendor/marketing statements, not established here as RERA-filed or delivered facilities. |
|---|---|
| Evidence source | Promoter website |
| Declared progress / verified status | Not independently verified; no supplied RERA progress evidence establishes delivery. |
7. Utilities, building services & safety
The RERA amenity register includes internal roads and footpaths, water supply, sewerage infrastructure, storm-water drains, street lighting, sewage/sullage treatment and disposal, solid-waste management, rainwater harvesting, energy management, fire-protection requirements and electrical meter/substation/receiving-station facilities. Most entries have a recorded progress figure of 0; the supplied record does not establish completed facilities or provide capacities and technical specifications. RERA amenities
| What the supplied project record establishes | “Water Supply” is listed in the RERA amenity register. A vendor listing states “Water Supply Corporation and Borewell.” |
|---|---|
| Status / limitation | The vendor statement is not independently verified; source capacity, storage and treatment details are not supplied. RERA amenities Promoter website |
| What the supplied project record establishes | RERA lists sewerage infrastructure including chambers, lines, septic tank and STP; storm-water drains and sewage/sullage treatment and disposal are also listed. |
|---|---|
| Status / limitation | Progress figures are recorded as 0 where provided; no capacity or completion evidence supplied. RERA amenities |
| What the supplied project record establishes | Listed in the RERA amenity register. |
|---|---|
| Status / limitation | Progress is recorded as 0; completion not verified. RERA amenities |
| What the supplied project record establishes | Electrical meter room, substation/receiving station and energy management are listed. |
|---|---|
| Status / limitation | No capacity, supply arrangement, backup provision or completion evidence supplied. RERA amenities |
| What the supplied project record establishes | Fire protection and fire-safety requirements are listed. |
|---|---|
| Status / limitation | No detailed system specification, clearance or completed-system evidence supplied. RERA amenities |
| What the supplied project record establishes | Solid-waste management and disposal are listed. |
|---|---|
| Status / limitation | Progress recorded as 0; operating arrangements and completion not verified. RERA amenities |
| What the supplied project record establishes | Internal roads and footpaths are listed; HMDA’s approval refers to road access and opening roads for neighboring-site accessibility. |
|---|---|
| Status / limitation | No accessible-route, ramp or detailed pedestrian-separation specification supplied. RERA amenities |
8. Location, access & connectivity
The registered location is Bacharam village, Abdullapurmet mandal, Ranga Reddy district, PIN 509412, on Survey Nos. 73/P, 74, 75 and 76. RERA record
The supplied location dataset records the nearest sampled Outer Ring Road interchange at approximately 6.1 km. The HMDA approval also records a 100' wide road and requires roads to be opened for accessibility to neighboring sites. No public-transport route or independently verified travel time is supplied. Location record
9. Developer & development status
The registered promoter is SRI SURYA DEVELOPERS, identified in the project record as a partnership. The RERA filing names KANCHI SURENDRANATH as an authorized signatory and KANCHI GOPI KRISHNA as a partner. The supplied project record gives the promoter address as B, ROAD NO 6-B, BACHARAM, BACHARAM, Abdullapurmet, Ranga Reddy, 509412. Corporate record Parties record
The Form-B declaration dated 15/05/2019 records the promoter’s completion undertaking as 02/11/2022, along with declarations concerning title basis, encumbrances, project funds and pending approvals. These are promoter declarations, not independent verification of those matters.
The project header reports 80% completeness, but the supplied evidence does not state the measurement date or method. No current phase- or plot-wise progress schedule, independent site inspection, completion certificate or occupancy certificate is supplied. RERA record Document index
10. Approvals, official records & documents
| Supplied evidence | FORM ‘C’, registration P02400001545, issued 27/12/2019, with stated validity to 02/11/2022. |
|---|---|
| Scope / note | Project: TRUE PRIDE BACHARAM; survey numbers 73/P, 74, 75 and 76. Certificate states no extension in the supplied record. |
| Supplied evidence | Approval 07/L0/PL/HMDA/2019, dated 02-11-2019; file reference 301160/LO/Plg/HMDA/2016. |
|---|---|
| Scope / note | Draft residential layout for Ac. 45-20 Gts.; approval conditions include mortgage-plot restrictions, specified area handovers and no plot construction before final layout approval. |
| Supplied evidence | Form-B affidavit dated 15/05/2019, made for SRI SURYA DEVELOPERS. |
|---|---|
| Scope / note | Includes promoter declarations and completion undertaking. |
| Supplied evidence | Title report and deed/agreement extracts include documents 81555–81561, 81605–81608 and 89971. Document index |
|---|---|
| Scope / note | These are source documents in the file; their title-chain details are outside this overview. |
| Supplied evidence | Not available in the supplied evidence. |
|---|---|
| Scope / note | The HMDA DPMS lookup is reported as unavailable from the public internet; this does not establish refusal or non-existence of a record. HMDA |
| Supplied evidence | Not supplied. |
|---|---|
| Scope / note | No certificate status can be confirmed from the evidence provided. Document index |
1. Project at a glance
Project identity
Registered project name: TRUE PRIDE BACHARAM
Project type: Plotted development; the HMDA document describes a draft residential layout of open plots.
Phase / registered portion: Phase not separately identified in the supplied record. The registered land is identified in Survey Nos. 73/P, 74, 75 and 76.
TG-RERA registration: P02400001545, issued 27/12/2019; the certificate states validity from 27/12/2019 to 02/11/2022.
Registered promoter: SRI SURYA DEVELOPERS; the project record identifies the entity as a partnership.
RERA status: The registration certificate records the stated validity period; the supplied certificate says it was not extended. Current registration status is not independently established by the supplied material.
Land and geographic identity
Locality / revenue village: Bacharam (also stated as Bacharam village).
Mandal / district / PIN: Abdullapurmet / Ranga Reddy / 509412.
Project survey numbers: 73/P, 74, 75 and 76.
Registered site extent: The RERA land record states 182203.74 sqmts total area, 6144.74 sqmts affected in road widening/FTL of tanks/Nala widening, and 176059.00 sqmts net area.
HMDA draft-layout extent: Ac. 45-20 Gts.
Boundaries recorded in RERA fields: North: ROAD WIDTH 50; south, east and west: OTHER LAND.
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA).
Principal approval: 07/L0/PL/HMDA/2019, approved 02-11-2019; file reference Letter No.301160/LO/Plg/HMDA/2016. The supplied document describes this as draft residential-layout approval.
Approved built-up area: 108170.24 sqmts is recorded in the project fields as approved built-up area; the supplied layout-approval extraction does not explain its detailed basis.
Plots / layout organization: HMDA’s draft approval identifies 68 plots and lists roads, open space, utility and social-infrastructure areas. The supplied materials do not establish the total approved plot count or provide an approved-layout drawing for plot-by-plot review.
Buildings / floors: Not disclosed in the supplied project record. This is a plotted layout, and no building or floor configuration is provided.
Parking provision: No project parking count or parking-level arrangement is established by the supplied RERA fields or extracted approval.
Offering and status
RERA offering: Plots; no RERA-filed plot-count, plot-size range, or plot-wise inventory is supplied in the evidence provided for this overview.
Booked / available counts: Not established by the supplied RERA data.
Construction / development stage: The RERA record gives a proposed completion date of 02/11/2022 and an overall completeness figure of 80%; the basis and inspection date for that percentage are not supplied, so it is not treated here as independently verified site progress.
Completion deadline: Promoter-declared completion undertaking: 02/11/2022.
Occupancy / completion certificate: Not supplied. The record does not establish an occupancy or completion certificate for the layout.
2. The project story
TRUE PRIDE BACHARAM is registered as a plotted residential development in Bacharam village, Abdullapurmet mandal, Ranga Reddy district, on Survey Nos. 73/P, 74, 75 and 76. Its TG-RERA registration is P02400001545.
The project record describes land of 182203.74 sqmts in total, with a recorded net area of 176059.00 sqmts after an affected-area entry of 6144.74 sqmts. HMDA’s 02-11-2019 document records draft-layout approval for Ac. 45-20 Gts. and identifies 68 plots. The extracted approval is conditional: among its terms, plots identified as mortgaged to HMDA are restricted from sale until release and final-layout processes are completed, and specified open-space, utility, social-infrastructure and road areas are to be handed over by registered gift deed.
The promoter’s RERA filing undertook completion by 02/11/2022. The project record also reports 80% completeness, but the supplied evidence does not give the date, measurement method or independent site verification underlying that figure. No completion/occupancy certificate or current plot-wise construction/development status is supplied.
3. Master plan, architecture & building design
This is a plotted-layout project, not a building or apartment development in the supplied RERA record. HMDA’s draft approval identifies 68 plots on Ac. 45-20 Gts. in Survey Nos. 73/P, 74, 75 and 76 at Bacharam village. It records the following layout components:
| Layout component | Area / description | Evidence |
|---|---|---|
| Open space | 13794.80 Sq.Mtrs | HMDA draft-layout approval, p2 |
| Utility area | 594 Sq,Mtrs | HMDA draft-layout approval, p2 |
| Social Infrastructure area | 4469.65 Sq.Mtrs. | HMDA draft-layout approval, p2 |
| Roads area | 52230.25Sq.Mtrs. | HMDA draft-layout approval, p2 |
| Area affected under H.T. Line | 3099.73 Sq.Mtrs. | HMDA draft-layout approval, p2 |
| Road width noted | 100' wide road | HMDA draft-layout approval |
The RERA fields separately state total area 182203.74 sqmts, affected area 6144.74 sqmts, net area 176059.00 sqmts, and approved built-up area 108170.24 sqmts. The supplied evidence does not provide a drawing-based reconciliation of those area figures or a plot schedule from which individual plot sizes, layout arrangement or land-use allocation can be checked.
No building count, floor configuration, tower arrangement, building footprint, apartment circulation or building-level plans are provided. The HMDA approval document says construction is not to be allowed on plots until HMDA issues the final layout.
4. Homes, configurations & floor plans
The RERA evidence identifies the offering as plots, but does not provide a RERA-filed plot inventory, plot-size bands, booked/available plot counts or plot-wise saleable areas in the supplied materials.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not supplied |
The floor-plan dataset contains two drawings, both scans pending; none have been measured. Apartment carpet-area measurements therefore do not apply to the evidence available for this plotted project.
5. Parking & vehicle circulation
The supplied RERA record and extracted HMDA approval do not establish a parking-space count, visitor or accessible parking provision, parking allocation to plots, or a parking-level arrangement. HMDA’s approval records a 100' wide road and a roads area of 52230.25Sq.Mtrs.; it also requires roads to be opened for access to neighboring sites. These are layout-road records, not evidence of individual plot parking or an exclusive parking right.
6. Amenities, recreation & open spaces
The RERA amenity register lists proposed/common infrastructure items, but the supplied progress figures are 0 where recorded; these are not evidence of completed or independently inspected facilities. HMDA’s draft approval separately specifies layout areas and handover conditions.
| Description / size | Listed in the RERA amenity register; no size or detailed specification supplied. |
|---|---|
| Declared progress / verified status | Progress recorded as 0; completion not verified. |
| Description / size | Listed in the RERA amenity register. HMDA approval records open space of 13794.80 Sq.Mtrs. |
|---|---|
| Declared progress / verified status | Amenity progress recorded as 0; HMDA requires development of open space and transfer by registered gift deed before final layout release. Delivery is not verified. |
| Description / size | Aggregate area of recreational open space is listed; no separate size beyond the HMDA open-space figure is supplied. |
|---|---|
| Declared progress / verified status | Progress recorded as 0; completion not verified. |
| Description / size | 594 Sq,Mtrs in the HMDA approval. |
|---|---|
| Declared progress / verified status | HMDA approval requires handover by registered gift deed before final layout release; completion/handover not verified. |
| Description / size | 4469.65 Sq.Mtrs. in the HMDA approval. |
|---|---|
| Declared progress / verified status | Handover is specified as a condition; completion/handover not verified. |
| Description / size | Vendor listings mention a clubhouse, swimming pool, park and children’s play areas, among other amenities. These are vendor/marketing statements, not established here as RERA-filed or delivered facilities. |
|---|---|
| Declared progress / verified status | Not independently verified; no supplied RERA progress evidence establishes delivery. |
7. Utilities, building services & safety
The RERA amenity register includes internal roads and footpaths, water supply, sewerage infrastructure, storm-water drains, street lighting, sewage/sullage treatment and disposal, solid-waste management, rainwater harvesting, energy management, fire-protection requirements and electrical meter/substation/receiving-station facilities. Most entries have a recorded progress figure of 0; the supplied record does not establish completed facilities or provide capacities and technical specifications.
| What the supplied project record establishes | “Water Supply” is listed in the RERA amenity register. A vendor listing states “Water Supply Corporation and Borewell.” |
|---|---|
| Status / limitation | The vendor statement is not independently verified; source capacity, storage and treatment details are not supplied. |
| What the supplied project record establishes | RERA lists sewerage infrastructure including chambers, lines, septic tank and STP; storm-water drains and sewage/sullage treatment and disposal are also listed. |
|---|---|
| Status / limitation | Progress figures are recorded as 0 where provided; no capacity or completion evidence supplied. |
| What the supplied project record establishes | Listed in the RERA amenity register. |
|---|---|
| Status / limitation | Progress is recorded as 0; completion not verified. |
| What the supplied project record establishes | Electrical meter room, substation/receiving station and energy management are listed. |
|---|---|
| Status / limitation | No capacity, supply arrangement, backup provision or completion evidence supplied. |
| What the supplied project record establishes | Fire protection and fire-safety requirements are listed. |
|---|---|
| Status / limitation | No detailed system specification, clearance or completed-system evidence supplied. |
| What the supplied project record establishes | Solid-waste management and disposal are listed. |
|---|---|
| Status / limitation | Progress recorded as 0; operating arrangements and completion not verified. |
| What the supplied project record establishes | Internal roads and footpaths are listed; HMDA’s approval refers to road access and opening roads for neighboring-site accessibility. |
|---|---|
| Status / limitation | No accessible-route, ramp or detailed pedestrian-separation specification supplied. |
8. Location, access & connectivity
The registered location is Bacharam village, Abdullapurmet mandal, Ranga Reddy district, PIN 509412, on Survey Nos. 73/P, 74, 75 and 76.
The supplied location dataset records the nearest sampled Outer Ring Road interchange at approximately 6.1 km. The HMDA approval also records a 100' wide road and requires roads to be opened for accessibility to neighboring sites. No public-transport route or independently verified travel time is supplied.
9. Developer & development status
The registered promoter is SRI SURYA DEVELOPERS, identified in the project record as a partnership. The RERA filing names KANCHI SURENDRANATH as an authorized signatory and KANCHI GOPI KRISHNA as a partner. The supplied project record gives the promoter address as B, ROAD NO 6-B, BACHARAM, BACHARAM, Abdullapurmet, Ranga Reddy, 509412.
The Form-B declaration dated 15/05/2019 records the promoter’s completion undertaking as 02/11/2022, along with declarations concerning title basis, encumbrances, project funds and pending approvals. These are promoter declarations, not independent verification of those matters.
The project header reports 80% completeness, but the supplied evidence does not state the measurement date or method. No current phase- or plot-wise progress schedule, independent site inspection, completion certificate or occupancy certificate is supplied.
10. Approvals, official records & documents
| Supplied evidence | FORM ‘C’, registration P02400001545, issued 27/12/2019, with stated validity to 02/11/2022. |
|---|---|
| Scope / note | Project: TRUE PRIDE BACHARAM; survey numbers 73/P, 74, 75 and 76. Certificate states no extension in the supplied record. |
| Supplied evidence | Approval 07/L0/PL/HMDA/2019, dated 02-11-2019; file reference 301160/LO/Plg/HMDA/2016. |
|---|---|
| Scope / note | Draft residential layout for Ac. 45-20 Gts.; approval conditions include mortgage-plot restrictions, specified area handovers and no plot construction before final layout approval. |
| Supplied evidence | Form-B affidavit dated 15/05/2019, made for SRI SURYA DEVELOPERS. |
|---|---|
| Scope / note | Includes promoter declarations and completion undertaking. |
| Supplied evidence | Title report and deed/agreement extracts include documents 81555–81561, 81605–81608 and 89971. |
|---|---|
| Scope / note | These are source documents in the file; their title-chain details are outside this overview. |
| Supplied evidence | Not available in the supplied evidence. |
|---|---|
| Scope / note | The HMDA DPMS lookup is reported as unavailable from the public internet; this does not establish refusal or non-existence of a record. |
| Supplied evidence | Not supplied. |
|---|---|
| Scope / note | No certificate status can be confirmed from the evidence provided. |
Frequently asked questions
Is TRUE PRIDE BACHARAM registered with Telangana RERA?
Yes. TRUE PRIDE BACHARAM is registered with the Telangana Real Estate Regulatory Authority as P02400001545; the registration status is New Project.
Who is the developer of TRUE PRIDE BACHARAM?
The promoter named in the RERA registration is SRI SURYA DEVELOPERS.
Where is TRUE PRIDE BACHARAM located?
TRUE PRIDE BACHARAM is in BACHARAM, Abdullapurmet, Rangareddy, Telangana (509412).
When will TRUE PRIDE BACHARAM be completed?
The promoter's proposed date of completion filed with RERA is 02/11/2022. This is the promoter's declaration, not a guarantee.