Prime Infra
Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS · Medak · RERA P01000011078
PRIME INFRA is a plotted development in Ramayanpet Revenue Village, RAMAYAMPET mandal, Medak district, developed by the registered promoter Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS. The site extent is 3 Acer 40 Gts 19360 Sq. Yds, and the tentative plotted layout comprises 44 plots; no plot configurations are stated. The project is registered under TG-RERA P01000011078, with 30/11/2026 listed as the proposed and revised proposed completion date.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
11 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | PRIME INFRA RERA record |
| Project type | Plotted development / tentative plotted layout RERA record |
| Phase / registered portion | Phase not separately identified; registration covers the plotted project on the survey numbers listed below |
| TG-RERA registration | P01000011078 |
| Registration validity | Certificate states 16/03/2024 to 16/03/2026; it records no extension. Registration validity is separate from the completion deadline. |
| Registered promoter | Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS RERA record |
| Project status | RERA header describes the project as “On-Going Project.” The record supplied does not establish a current physical site condition. RERA record |
| Registration certificate | Form ‘C’, issued 21/07/2026, for registration granted under section 5 |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Ramayanpet; revenue-village wording in the layout approval is “Ramayanpet Revenue Village.” RERA certificate location is “RAMAYAMPET A, RAMAYAMPET.” |
| Mandal | RAMAYAMPET RERA record |
| District | Medak RERA record |
| PIN | 502101 RERA record |
| All project survey numbers and subdivisions | 1552/E; 1551/B5; 1551/B3/2; 1551/B4; 1552/D1; 1552/C; 1551/B3/1; 1552/A1; 1551/B1/1; 1551/B/1/2; 1552/A2; 1551/B2/2; 1552/B2; 1551/B6; 1552/F; 1551/B3/3 |
| Site extent in layout approval | 3 Acer 40 Gts 19360 Sq. Yds |
| RERA-filed land area | Total area 16186.85 sq. m; area affected in road widening/FTL of Tanks/Nala Widening 338.62 sq. m; net area 15848.23 sq. m RERA filing |
| Boundaries | East: Road; West: Agriculture land of Neighbours; North: Agriculture Land of Mettu Yadagiri; South: Agriculture Land of Mettu Siddaramulu and Raju RERA filing |
Development identity
| Field | Record |
|---|---|
| Principal approval | Tentative Layout Plan No. 0006/LO/3115/2024, approved 16 March, 2024 |
| Authority named on approval | RAMAYANPET Municipality/Municipal Corporation |
| Application number | 005361/LO/DTCP/3115/0009/2023 |
| Approved layout type and plot count | Tentative plotted layout; 44 plots |
| Approved built-up area | Not disclosed in the supplied layout-approval extraction. |
| Building / floor configuration | Not applicable to the supplied plotted-layout approval; no residential building floor configuration is provided. |
| Approved land-use allocation | Plotted Area: 2 Acer 14.45 Gts 11429 Sq. Yds (60.3%); Road Area: 1 Acer 2.09 Gts 5093 Sq. Yds (26.87%); Open space (Park): 0 Acer 14.4 Gts 1742 Sq. Yds (9.19%); Social Infrastructure: 0 Acer 4.11 Gts 497 Sq. Yds (2.62%); Utilities: 0 Acer 1.6 Gts 194 Sq. Yds (1.02%) |
| Mortgage area in approval | 0 Acer 15.64 Gts 1893 Sq. Yds, identified as 16.45% of plotted area and comprising Plot Nos. 22, 23, 27, 19, 18, 17, 21 and 20 |
Offering and status
| Field | Record |
|---|---|
| Purchasable product | Plots; the approval identifies 44 plots. Plot-wise dimensions, size bands, availability and allotment status are not established by the supplied data. |
| Booked / available counts | Not disclosed in the supplied evidence. |
| Declared completion date | RERA project information lists 30/11/2026 as the proposed and revised proposed completion date RERA filing |
| Promoter-declared completion undertaking in Form B | The Form-B declaration states completion by 16th March 2026 |
| Registration validity versus completion | The certificate states validity through 16/03/2026; the RERA project information separately lists a completion date of 30/11/2026. RERA filing |
| Construction / development progress | RERA header records completeness as 70%; this is a declared record figure, not an independent site inspection. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is identified in the supplied project documents. The project is a plotted layout; final-layout-release status is not established here. Document index |
2. The project story
PRIME INFRA is registered as a plotted development in Ramayanpet Revenue Village, RAMAYAMPET mandal, Medak district. Its tentative layout approval describes a 44-plot layout across a site of 3 Acer 40 Gts 19360 Sq. Yds. The approval allocates land to plots, roads, a park/open space, social infrastructure and utilities. RERA record
The layout approval requires the applicant to develop roads, storm-water drains, underground drainage and a common septic tank/STP, internal water supply, an overhead tank, electrical lines and street lights, a transformer, avenue planting, park development and rainwater-harvesting pits. These are stated development requirements; the supplied evidence does not independently verify which works are complete.
The RERA header reports 70% completeness, while the project information gives 30/11/2026 as the proposed and revised completion date. These are project-record declarations, not independently verified construction progress. No plot-wise inventory or current booking/availability data is supplied. RERA record RERA filing
3. Master plan, architecture & building design
This is a plotted layout, not an apartment-building scheme in the supplied approval. The tentative layout approval identifies 44 plots and a total site extent of 3 Acer 40 Gts 19360 Sq. Yds. It allocates 2 Acer 14.45 Gts 11429 Sq. Yds to plotted area, 1 Acer 2.09 Gts 5093 Sq. Yds to roads, 0 Acer 14.4 Gts 1742 Sq. Yds to open space/park, 0 Acer 4.11 Gts 497 Sq. Yds to social infrastructure, and 0 Acer 1.6 Gts 194 Sq. Yds to utilities.
The approval identifies eight mortgaged plots—Nos. 22, 23, 27, 19, 18, 17, 21 and 20—covering 0 Acer 15.64 Gts 1893 Sq. Yds. It also requires roads to remain open for access to neighbouring sites and prohibits a compound wall or fencing around the site under the stated approval conditions.
The supplied material does not include a legible layout drawing from which individual plot dimensions, road widths, plot orientation or detailed circulation geometry can be described. No building footprints, floor plans, building heights, or residential/commercial building areas are provided. The RERA-filed land details separately state total area 16186.85 sq. m, affected area 338.62 sq. m and net area 15848.23 sq. m. RERA filing Document index
4. Homes, configurations & floor plans
The project is offered as a plotted layout. The tentative layout approval records 44 plots, but plot-wise counts by size, individual plot dimensions, saleable areas, and booked or available plot counts are not supplied. Document index
No apartment configuration table, RERA-filed plot-size schedule, or usable plot-wise floor-plan measurements are available in the supplied evidence. The two drawing records listed for floor-plan review are scans pending measurement; no software-measured areas are available. Floor plans
5. Parking & vehicle circulation
The supplied layout-approval extraction does not state parking-space counts, dedicated visitor or accessible parking, or parking allocation arrangements. The approval identifies roads as 1 Acer 2.09 Gts 5093 Sq. Yds and requires roads to remain open for access to neighbouring sites. It does not provide road widths, driveway dimensions or a detailed vehicle-circulation plan.
The approval identifies Plot Nos. 22, 23, 27, 19, 18, 17, 21 and 20 as mortgaged to the Municipality for development-condition security; this is not evidence of parking allocation.
6. Amenities, recreation & open spaces
The approval’s development schedule includes layout-level open space and facilities. The progress figures below are not independently verified site-completion findings.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / open space | 0 Acer 14.4 Gts 1742 Sq. Yds; 9.19% | Required in the tentative approval; completion not independently verified | |
| Social infrastructure site | 0 Acer 4.11 Gts 497 Sq. Yds; 2.62% | Land reservation identified; facility type and delivery status not specified | |
| Avenue plantation | No size stated | Required development work; completion not independently verified | |
| Internal roads | 1 Acer 2.09 Gts 5093 Sq. Yds; 26.87% | Road formation with black top is specified; completion not independently verified | |
| Utilities site | 0 Acer 1.6 Gts 194 Sq. Yds; 1.02% | Land reservation identified; completed facilities not independently verified |
No project-specific clubhouse, indoor recreation facility, or sports facility is identified in the supplied RERA project evidence.
7. Utilities, building services & safety
The tentative layout approval specifies proposed layout infrastructure including a water reservoir, overhead tank and sump; internal water-supply pipelines and an assured water-supply source; underground drainage and a common septic tank/STP; storm-water drains; electrical supply lines, street lights and a transformer; solid-waste management; and rainwater-harvesting pits. The approval does not provide capacities or independently verified commissioning status.
The supplied RERA amenities record marks water supply, sewerage (chambers, lines, septic tank, STP), storm-water drains, street lighting, solid-waste management and disposal, and water conservation/rainwater harvesting as available at 100%. This is a recorded availability entry, not an independent verification of operational condition or capacity. RERA amenities
Fire-protection and fire-safety requirements and energy management are recorded as 0% in that amenities data; no project-specific fire-system design, clearance, security-system specification, or accessibility details are provided. RERA amenities
8. Location, access & connectivity
The registered location is RAMAYAMPET A, RAMAYAMPET, Medak district, PIN 502101; the layout approval describes the site as being in Ramayanpet Revenue Village, Ramayanpet Mandal. RERA record
The supplied location data gives the cadastral parcel centroid as 18.121186546964918, 78.41945737259556 and lists the nearest sampled Outer Ring Road interchange at approximately 55.0 km. This is a supplied approximate distance, not a travel-time estimate. Location record
The RERA evidence does not provide a detailed approach-road description, public-transport information or project-specific nearby-landmark distances.
9. Developer & development status
The registered promoter is Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS. The filing identifies the organization type as “Others” and describes it as “JOINT DEVELOPMENT”; the entity’s legal form is not otherwise established in the supplied material. RERA record RERA filing Corporate record
A RERA-filed authorization letter names Sri. PEDDABAGOLLA MALLESHAM as authorized to act for the project and handle registration-related work.
The RERA header records 70% completeness; no independent site verification is supplied. RERA record
The tentative-layout approval dated 16 March, 2024 required infrastructure and amenities to be completed within 2 years, stated as 16 March, 2026. It also provides for a possible one-year extension on specific request and payment of 20% of the total fee paid at tentative-layout approval. Separately, the RERA project information lists 30/11/2026 as the proposed and revised proposed completion date. RERA filing
10. Approvals, official records & documents
| What it establishes | Registration of PRIME INFRA under P01000011078; certificate states validity from 16/03/2024 to 16/03/2026 and is dated 21/07/2026. |
|---|
| What it establishes | Approval No. 0006/LO/3115/2024, dated 16 March, 2024, for a 44-plot tentative layout; includes land-use allocation and conditions. |
|---|
| What it establishes | Application No. 005361/LO/DTCP/3115/0009/2023 |
|---|
| What it establishes | Promoter’s authorized-signatory declaration, including the stated land-title basis, encumbrance declaration, project-account undertakings and completion undertaking by 16th March 2026. |
|---|
| What it establishes | Deed No. 608/2024, dated 26 February, 2024, identified in the layout approval for the eight mortgaged plots securing development conditions. |
|---|
| What it establishes | Advocate’s title opinion dated 10th November 2025, concerning the tentative layout; it recites six sale deeds and the layout gift/mortgage instruments. |
|---|
| What it establishes | Two RERA-filed encumbrance statements for searches stated to cover 01-01-1983 to 03-07-2026; extracted transaction rows are incomplete or garbled. |
|---|
| What it establishes | Orders for specified agricultural survey lands; the document states that conversion permission does not confer title or ownership. |
|---|
| What it establishes | Partially completed RERA-form documents; the supplied extracts have blank plot/allottee and transaction particulars. |
|---|
| What it establishes | Public lookup was unavailable in the supplied evidence; no HMDA DPMS confirmation is established here. |
|---|---|
| Source | HMDA |
The supplied project documents do not identify an occupancy or completion certificate or establish final-layout release.
1. Project at a glance
Project identity
Registered project name: PRIME INFRA
Project type: Plotted development / tentative plotted layout
Phase / registered portion: Phase not separately identified; registration covers the plotted project on the survey numbers listed below
TG-RERA registration: P01000011078
Registration validity: Certificate states 16/03/2024 to 16/03/2026; it records no extension. Registration validity is separate from the completion deadline.
Registered promoter: Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS
Project status: RERA header describes the project as “On-Going Project.” The record supplied does not establish a current physical site condition.
Registration certificate: Form ‘C’, issued 21/07/2026, for registration granted under section 5
Land and geographic identity
Locality / revenue village: Ramayanpet; revenue-village wording in the layout approval is “Ramayanpet Revenue Village.” RERA certificate location is “RAMAYAMPET A, RAMAYAMPET.”
Mandal: RAMAYAMPET
District: Medak
PIN: 502101
All project survey numbers and subdivisions: 1552/E; 1551/B5; 1551/B3/2; 1551/B4; 1552/D1; 1552/C; 1551/B3/1; 1552/A1; 1551/B1/1; 1551/B/1/2; 1552/A2; 1551/B2/2; 1552/B2; 1551/B6; 1552/F; 1551/B3/3
Site extent in layout approval: 3 Acer 40 Gts 19360 Sq. Yds
RERA-filed land area: Total area 16186.85 sq. m; area affected in road widening/FTL of Tanks/Nala Widening 338.62 sq. m; net area 15848.23 sq. m
Boundaries: East: Road; West: Agriculture land of Neighbours; North: Agriculture Land of Mettu Yadagiri; South: Agriculture Land of Mettu Siddaramulu and Raju
Development identity
Principal approval: Tentative Layout Plan No. 0006/LO/3115/2024, approved 16 March, 2024
Authority named on approval: RAMAYANPET Municipality/Municipal Corporation
Application number: 005361/LO/DTCP/3115/0009/2023
Approved layout type and plot count: Tentative plotted layout; 44 plots
Approved built-up area: Not disclosed in the supplied layout-approval extraction.
Building / floor configuration: Not applicable to the supplied plotted-layout approval; no residential building floor configuration is provided.
Approved land-use allocation: Plotted Area: 2 Acer 14.45 Gts 11429 Sq. Yds (60.3%); Road Area: 1 Acer 2.09 Gts 5093 Sq. Yds (26.87%); Open space (Park): 0 Acer 14.4 Gts 1742 Sq. Yds (9.19%); Social Infrastructure: 0 Acer 4.11 Gts 497 Sq. Yds (2.62%); Utilities: 0 Acer 1.6 Gts 194 Sq. Yds (1.02%)
Mortgage area in approval: 0 Acer 15.64 Gts 1893 Sq. Yds, identified as 16.45% of plotted area and comprising Plot Nos. 22, 23, 27, 19, 18, 17, 21 and 20
Offering and status
Purchasable product: Plots; the approval identifies 44 plots. Plot-wise dimensions, size bands, availability and allotment status are not established by the supplied data.
Booked / available counts: Not disclosed in the supplied evidence.
Declared completion date: RERA project information lists 30/11/2026 as the proposed and revised proposed completion date
Promoter-declared completion undertaking in Form B: The Form-B declaration states completion by 16th March 2026
Registration validity versus completion: The certificate states validity through 16/03/2026; the RERA project information separately lists a completion date of 30/11/2026.
Construction / development progress: RERA header records completeness as 70%; this is a declared record figure, not an independent site inspection.
Occupancy / completion certificate: No occupancy or completion certificate is identified in the supplied project documents. The project is a plotted layout; final-layout-release status is not established here.
2. The project story
PRIME INFRA is registered as a plotted development in Ramayanpet Revenue Village, RAMAYAMPET mandal, Medak district. Its tentative layout approval describes a 44-plot layout across a site of 3 Acer 40 Gts 19360 Sq. Yds. The approval allocates land to plots, roads, a park/open space, social infrastructure and utilities.
The layout approval requires the applicant to develop roads, storm-water drains, underground drainage and a common septic tank/STP, internal water supply, an overhead tank, electrical lines and street lights, a transformer, avenue planting, park development and rainwater-harvesting pits. These are stated development requirements; the supplied evidence does not independently verify which works are complete.
The RERA header reports 70% completeness, while the project information gives 30/11/2026 as the proposed and revised completion date. These are project-record declarations, not independently verified construction progress. No plot-wise inventory or current booking/availability data is supplied.
3. Master plan, architecture & building design
This is a plotted layout, not an apartment-building scheme in the supplied approval. The tentative layout approval identifies 44 plots and a total site extent of 3 Acer 40 Gts 19360 Sq. Yds. It allocates 2 Acer 14.45 Gts 11429 Sq. Yds to plotted area, 1 Acer 2.09 Gts 5093 Sq. Yds to roads, 0 Acer 14.4 Gts 1742 Sq. Yds to open space/park, 0 Acer 4.11 Gts 497 Sq. Yds to social infrastructure, and 0 Acer 1.6 Gts 194 Sq. Yds to utilities.
The approval identifies eight mortgaged plots—Nos. 22, 23, 27, 19, 18, 17, 21 and 20—covering 0 Acer 15.64 Gts 1893 Sq. Yds. It also requires roads to remain open for access to neighbouring sites and prohibits a compound wall or fencing around the site under the stated approval conditions.
The supplied material does not include a legible layout drawing from which individual plot dimensions, road widths, plot orientation or detailed circulation geometry can be described. No building footprints, floor plans, building heights, or residential/commercial building areas are provided. The RERA-filed land details separately state total area 16186.85 sq. m, affected area 338.62 sq. m and net area 15848.23 sq. m.
4. Homes, configurations & floor plans
The project is offered as a plotted layout. The tentative layout approval records 44 plots, but plot-wise counts by size, individual plot dimensions, saleable areas, and booked or available plot counts are not supplied.
No apartment configuration table, RERA-filed plot-size schedule, or usable plot-wise floor-plan measurements are available in the supplied evidence. The two drawing records listed for floor-plan review are scans pending measurement; no software-measured areas are available.
5. Parking & vehicle circulation
The supplied layout-approval extraction does not state parking-space counts, dedicated visitor or accessible parking, or parking allocation arrangements. The approval identifies roads as 1 Acer 2.09 Gts 5093 Sq. Yds and requires roads to remain open for access to neighbouring sites. It does not provide road widths, driveway dimensions or a detailed vehicle-circulation plan.
The approval identifies Plot Nos. 22, 23, 27, 19, 18, 17, 21 and 20 as mortgaged to the Municipality for development-condition security; this is not evidence of parking allocation.
6. Amenities, recreation & open spaces
The approval’s development schedule includes layout-level open space and facilities. The progress figures below are not independently verified site-completion findings.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / open space | 0 Acer 14.4 Gts 1742 Sq. Yds; 9.19% | Required in the tentative approval; completion not independently verified | |
| Social infrastructure site | 0 Acer 4.11 Gts 497 Sq. Yds; 2.62% | Land reservation identified; facility type and delivery status not specified | |
| Avenue plantation | No size stated | Required development work; completion not independently verified | |
| Internal roads | 1 Acer 2.09 Gts 5093 Sq. Yds; 26.87% | Road formation with black top is specified; completion not independently verified | |
| Utilities site | 0 Acer 1.6 Gts 194 Sq. Yds; 1.02% | Land reservation identified; completed facilities not independently verified |
No project-specific clubhouse, indoor recreation facility, or sports facility is identified in the supplied RERA project evidence.
7. Utilities, building services & safety
The tentative layout approval specifies proposed layout infrastructure including a water reservoir, overhead tank and sump; internal water-supply pipelines and an assured water-supply source; underground drainage and a common septic tank/STP; storm-water drains; electrical supply lines, street lights and a transformer; solid-waste management; and rainwater-harvesting pits. The approval does not provide capacities or independently verified commissioning status.
The supplied RERA amenities record marks water supply, sewerage (chambers, lines, septic tank, STP), storm-water drains, street lighting, solid-waste management and disposal, and water conservation/rainwater harvesting as available at 100%. This is a recorded availability entry, not an independent verification of operational condition or capacity.
Fire-protection and fire-safety requirements and energy management are recorded as 0% in that amenities data; no project-specific fire-system design, clearance, security-system specification, or accessibility details are provided.
8. Location, access & connectivity
The registered location is RAMAYAMPET A, RAMAYAMPET, Medak district, PIN 502101; the layout approval describes the site as being in Ramayanpet Revenue Village, Ramayanpet Mandal.
The supplied location data gives the cadastral parcel centroid as 18.121186546964918, 78.41945737259556 and lists the nearest sampled Outer Ring Road interchange at approximately 55.0 km. This is a supplied approximate distance, not a travel-time estimate.
The RERA evidence does not provide a detailed approach-road description, public-transport information or project-specific nearby-landmark distances.
9. Developer & development status
The registered promoter is Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS. The filing identifies the organization type as “Others” and describes it as “JOINT DEVELOPMENT”; the entity’s legal form is not otherwise established in the supplied material.
A RERA-filed authorization letter names Sri. PEDDABAGOLLA MALLESHAM as authorized to act for the project and handle registration-related work.
The RERA header records 70% completeness; no independent site verification is supplied.
The tentative-layout approval dated 16 March, 2024 required infrastructure and amenities to be completed within 2 years, stated as 16 March, 2026. It also provides for a possible one-year extension on specific request and payment of 20% of the total fee paid at tentative-layout approval. Separately, the RERA project information lists 30/11/2026 as the proposed and revised proposed completion date.
10. Approvals, official records & documents
| What it establishes | Registration of PRIME INFRA under P01000011078; certificate states validity from 16/03/2024 to 16/03/2026 and is dated 21/07/2026. |
|---|
| What it establishes | Approval No. 0006/LO/3115/2024, dated 16 March, 2024, for a 44-plot tentative layout; includes land-use allocation and conditions. |
|---|
| What it establishes | Application No. 005361/LO/DTCP/3115/0009/2023 |
|---|
| What it establishes | Promoter’s authorized-signatory declaration, including the stated land-title basis, encumbrance declaration, project-account undertakings and completion undertaking by 16th March 2026. |
|---|
| What it establishes | Deed No. 608/2024, dated 26 February, 2024, identified in the layout approval for the eight mortgaged plots securing development conditions. |
|---|
| What it establishes | Advocate’s title opinion dated 10th November 2025, concerning the tentative layout; it recites six sale deeds and the layout gift/mortgage instruments. |
|---|
| What it establishes | Two RERA-filed encumbrance statements for searches stated to cover 01-01-1983 to 03-07-2026; extracted transaction rows are incomplete or garbled. |
|---|
| What it establishes | Orders for specified agricultural survey lands; the document states that conversion permission does not confer title or ownership. |
|---|
| What it establishes | Partially completed RERA-form documents; the supplied extracts have blank plot/allottee and transaction particulars. |
|---|
| What it establishes | Public lookup was unavailable in the supplied evidence; no HMDA DPMS confirmation is established here. |
|---|
The supplied project documents do not identify an occupancy or completion certificate or establish final-layout release.
Frequently asked questions
Is PRIME INFRA registered with Telangana RERA?
Yes. PRIME INFRA is registered with the Telangana Real Estate Regulatory Authority as P01000011078; the registration status is On-Going Project.
Who is the developer of PRIME INFRA?
The promoter named in the RERA registration is Sri. PEDDA BAGOLLA MALLESHAM AND OTHERS.
Where is PRIME INFRA located?
PRIME INFRA is in Ramayampet, RAMAYAMPET A, Medak, Telangana (502101).
When will PRIME INFRA be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.