SRITAs MIHIR SYMPHONY
SRITA PROJECTS · Medchal-Malkajgiri · RERA P02200007223
SRITAs MIHIR SYMPHONY is a residential apartment project in Kompally, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District. The registered promoter is SRITA PROJECTS. The project comprises one residential building on 424.96 sq. m of land, with 1 Stilt + 5 upper floors and 10 3BHK units. Its TG-RERA registration number is P02200007223, and its proposed completion date is 10/02/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name | SRITAs MIHIR SYMPHONY RERA record |
| Project type / registered portion | Residential apartment project; the registration identifies one building and the evidence does not identify a separately named phase. RERA record RERA filing |
| TG-RERA registration | P02200007223; granted 08/11/2023; recorded validity through 10/02/2026. Registration validity is distinct from the completion deadline and from occupancy certification. Approvals record |
| Registered promoter | SRITA PROJECTS, recorded as a proprietorship. Parties record RERA filing |
| RERA status | “On-Going Project” in the RERA record. The registration certificate says it is not extended; no later extension document is supplied. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / registered site description | Kompally; Plot No. 164, Block No. 12, Jayabheri Park is identified in the title records. The RERA locality is recorded as KOMPALLY. RERA record RERA filing |
| Revenue village | Kompally Village in the title and building-permit records; the project/RERA location field says Kompally -Shivalayam. |
| Mandal / district / PIN | Dundigal Gandimaisamma; Medchal-Malkajgiri; 500014. RERA record |
| Survey number(s) | Sy.No. 120; no project subdivision is identified in the supplied project records. Land records |
| Registered extent | The RERA land details record total and net area as 424.96 sq. m and road-widening/FTL/nala-affected area as 0 sq. m. The building permit also states an extent of 424.96 Sq. Mt. RERA filing |
| Boundaries | East: Plot No. 165; West: Road; North: Plot No. 167; South: Plot No. 163. RERA filing Land records |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority / principal permission | HMDA permission recorded in a building permit order issued through Kompally Municipality / Municipal Corporation; approval 010138/BP/HMDA/2092/MED/2022, dated 10 February, 2023. Proceedings No. 002309/BP/HMDA/MED/2023. Approvals record |
| Approved building form | One residential building: 1 Stilt + 5 upper floors. |
| Built-up area | RERA fields record approved built-up area of 1146.10 sq. m. The permit extraction separately lists 1,146.10 Built-up Area and 1,379.05 Total Built up Area (In Sq.mts); these are the permit’s separately labelled figures. RERA filing |
| Building / unit counts | One building in the RERA land record; 10 RERA-filed units. The supplied extraction does not give a floor-by-floor unit schedule. RERA filing RERA unit table |
| Parking / mortgage figures in permit | Permit parameters include 120.18 Provided Mortgage area (In Sq.mts) and 114.61 Required 10% Mortgage area; the permit describes the mortgaged built-up area as in favour of MC, HMDA. These are not a count of resident parking spaces. |
Offering and status
| Item | Project record |
|---|---|
| Configuration | 3BHK; RERA-filed saleable area 110.0 sq. m. RERA unit table RERA unit details |
| Bookings / availability | 0 booked; 10 available, as carried in the TG-RERA unit record. The portal-derived booking data has no as-of date, so counts are indicative. RERA unit table RERA unit details |
| Completion dates | Proposed and revised proposed completion dates both recorded as 10/02/2026; the Form B declaration also undertakes completion within three years from permission, stated as 10 February, 2026. RERA record RERA filing |
| Construction stage | No independently verified site-progress assessment is supplied. RERA amenity fields report some infrastructure progress; details are in sections 6 and 9. RERA amenities |
| Occupancy certificate | No occupancy certificate is supplied in the reviewed documents. The building permit says an Occupancy Certificate is compulsory before occupation. Document index |
2. The project story
SRITAs MIHIR SYMPHONY is registered with TG-RERA as a residential apartment project on Plot No. 164 in Sy.No. 120, Kompally Village, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District. The RERA record describes one building on a 424.96 sq. m site, with one 3BHK configuration offered across 10 units. RERA record RERA filing RERA unit table
The building permit records a residential building of 1 Stilt + 5 upper floors and specifies a proposed STP, rainwater-harvesting structures and underground and terrace water storage. These are permit requirements or parameters; the supplied information does not independently verify their completion.
The project’s RERA completion date is 10/02/2026, while the registration certificate records validity through that same date and states no extension. No occupancy certificate or independent construction-progress inspection is included in the supplied evidence. The RERA progress record lists water supply and sewerage as available at 70%; these are filed progress entries, not an independent site verification. RERA record RERA amenities
3. Master plan, architecture & building design
The project record identifies a single residential building on 424.96 sq. m of land. The sanctioned configuration in the permit extraction is 1 Stilt + 5 upper floors. No basement, podium, floor-by-floor apartment schedule, building footprint, tower arrangement, lift or stair details, internal-road plan, or landscaped-area plan is supplied. RERA filing Document index
The RERA field for approved built-up area is 1146.10 sq. m. The building permit separately lists 1,146.10 Built-up Area and 1,379.05 Total Built up Area (In Sq.mts). The evidence does not define the latter figure further, so these labels are retained as recorded rather than treated as interchangeable area measures. RERA filing
The building permit states a minimum 4.5mts. width for entry and exit, 5mts. height clearance, and a minimum width of 4.5mts. in its road-width field. It also requires the stilt/cellar to be used exclusively for vehicle parking without partition walls or rolling shutters. The permit lists 25, 000 lts. underground static water storage and 25,000 lts. terrace tank.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 110.0 sq. m | Software-measured median 92.7 sq. m; range 92.4–93.2 sq. m | 16% |
RERA records the 3BHK saleable area as 110.0 sq. m. Software measurement from the approved floor-plan drawing records carpet area across four measured flat designs, with a median of 92.7 sq. m (998 sq. ft) and a range of 92.4–93.2 sq. m (994–1003 sq. ft). The drawing-derived measurements are not RERA-filed carpet-area disclosures and are identified as requiring review against the drawing. Saleable area and carpet area are different measures; the supplied floor-plan note says saleable area also counts the home’s share of common areas. RERA unit details Floor plans
The measured typical-plan unit includes three bedrooms, a living/dining area, kitchen, wash area, three toilets and a utility area. The utility is identified as excluded from the software-measured carpet area. The supplied room schedule gives, among other dimensions, living/dining 3.18 × 8.11 m, kitchen 2.11 × 3.27 m, and utility 3.18 × 1.5 m. These are drawing-based measurements, not RERA area declarations. RERA unit details
5. Parking & vehicle circulation
The permit requires the stilt/cellar to be used exclusively for vehicle parking and records entry/exit width of 4.5mts. minimum and 5mts. height clearance. It does not provide a car-space or two-wheeler-space count in the supplied extraction. The permit records 120.18 sq. m as provided mortgage area, not as a parking-space allocation. No resident, visitor or accessible-space counts, EV charging provision, parking-allocation schedule, or legally documented exclusive allocation to individual units is supplied. A vendor listing mentions covered car parking, but the supplied project record does not establish its count or allocation. Promoter website
6. Amenities, recreation & open spaces
The following progress figures are RERA-filed entries, not independent verification of completion. A 0% figure is retained as recorded; the supplied data does not explain whether it means work has not started or is not applicable. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip/TOT LOT/Park | Facility listed; no size supplied | RERA amenities | Available: YES; 0% recorded; not independently verified |
| Community Buildings | Listed; no description or size supplied | RERA amenities | 0% recorded; not independently verified |
| Aggregate area of recreational Open Space | Listed; no area supplied | RERA amenities | 0% recorded; not independently verified |
| Indoor games, swimming pool, gym, clubhouse and children’s play area | Vendor-listed amenities; no sizes or capacities supplied | Promoter website | Marketing/vendor listing only; no RERA progress or independent completion evidence supplied |
7. Utilities, building services & safety
| Service | Evidence and recorded status |
|---|---|
| Water | The permit lists 25, 000 lts. underground static water storage and 25,000 lts. terrace tank. RERA lists Water Supply as available: YES, 70%; no source, treatment system or independent verification is supplied. RERA amenities |
| Sewerage / drainage | The permit requires an STP. RERA lists “Sewerage (Chamber, Lines, Septic Tank, STP)” as available: YES, 70%. Storm Water Drains are recorded at 0%; no STP capacity or reuse details are supplied. RERA amenities |
| Rainwater harvesting | The permit requires rainwater-harvesting structures. RERA lists Water Conservation, Rain water Harvesting as available: YES, 0%. No completed-status verification is supplied. RERA amenities |
| Electrical | Electrical Meter Room, Sub-Station, Receiving Station is listed at 0% in the RERA progress record. No electrical capacity, backup-system details or completed status are supplied. RERA amenities |
| Vertical transportation | A vendor listing mentions a lift; the supplied permit extraction and project documents do not specify lift count, type or capacity. Promoter website Document index |
| Fire and life safety | Fire Protection and Fire Safety Requirements is listed at 0% in the RERA progress record. No fire-system specification or clearance document is supplied. RERA amenities |
| Waste / security / accessibility | Solid Waste Management and Disposal is recorded at 0%. The vendor lists security and CCTV, but no project-filed specification or verification is supplied. No accessibility details are provided. RERA amenities Promoter website |
8. Location, access & connectivity
The registered project location is Kompally, recorded as Kompally -Shivalayam, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District, PIN 500014. The title and permit records identify Kompally Village and Plot No. 164 in Sy.No. 120. RERA record RERA filing
The location record supplies one approximate connectivity measurement: the nearest sampled Outer Ring Road interchange is 42.8 km from the project’s cadastral parcel centroid. No approach-road route, public-transport service, travel time or additional measured landmark distances are supplied. Location record
9. Developer & development status
The TG-RERA registered promoter is SRITA PROJECTS, recorded as a proprietorship. The RERA party record names SHIVNATH NAMALA as authorized signatory; the filed Form B identifies him as proprietor and declarant for SRITA PROJECTS. The registration certificate lists the promoter office as Village: Olb Bowenpally, Mandal: Balanagar, District: Medchal-Malkajgiri, PIN 500011. No corporate registration identifier or official project contact details are supplied. Parties record RERA filing
Form B declares completion within three years from the permission date, stated as 10 February, 2026. The RERA certificate states validity through 10/02/2026 and no extension. No independently verified construction percentage or occupancy certificate is included; the RERA infrastructure progress entries are listed in sections 6 and 7. RERA amenities
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | FORM ‘C’ records registration of SRITAs MIHIR SYMPHONY, registration no. P02200007223, under section 5, issued 08/11/2023 and valid through 10/02/2026. |
| Building permit | Permit order 010138/BP/HMDA/2092/MED/2022, dated 10 February, 2023, with proceedings no. 002309/BP/HMDA/MED/2023; records HMDA permission and a residential building of 1 Stilt + 5 upper floors. |
| Title and land records filed with RERA | Title report and sale-deed materials identify Plot No. 164, Block No. 12, Sy.No. 120, Kompally Village; the development agreement/GPA and title-report materials are in the RERA file. |
| Promoter declaration | Form B affidavit by SHIVANATH NAMALA for SRITA PROJECTS, dated March 2023, includes promoter declarations concerning title, encumbrances, project funds and completion. |
| Occupancy / completion certificate | No OC or completion certificate is supplied among the reviewed documents. The building permit states an Occupancy Certificate is compulsory before occupation. Document index |
| Layout approval and floor-plan files | RERA document entries include layout-plan and building-floor-plan categories; the layout-plan item is not extracted, and the supplied floor-plan evidence includes drawing document 310132. Document index |
1. Project at a glance
Project identity
Registered name: SRITAs MIHIR SYMPHONY
Project type / registered portion: Residential apartment project; the registration identifies one building and the evidence does not identify a separately named phase.
TG-RERA registration: P02200007223; granted 08/11/2023; recorded validity through 10/02/2026. Registration validity is distinct from the completion deadline and from occupancy certification.
Registered promoter: SRITA PROJECTS, recorded as a proprietorship.
RERA status: “On-Going Project” in the RERA record. The registration certificate says it is not extended; no later extension document is supplied.
Land and geographic identity
Locality / registered site description: Kompally; Plot No. 164, Block No. 12, Jayabheri Park is identified in the title records. The RERA locality is recorded as KOMPALLY.
Revenue village: Kompally Village in the title and building-permit records; the project/RERA location field says Kompally -Shivalayam.
Mandal / district / PIN: Dundigal Gandimaisamma; Medchal-Malkajgiri; 500014.
Survey number(s): Sy.No. 120; no project subdivision is identified in the supplied project records.
Registered extent: The RERA land details record total and net area as 424.96 sq. m and road-widening/FTL/nala-affected area as 0 sq. m. The building permit also states an extent of 424.96 Sq. Mt.
Boundaries: East: Plot No. 165; West: Road; North: Plot No. 167; South: Plot No. 163.
Development identity
Sanctioning authority / principal permission: HMDA permission recorded in a building permit order issued through Kompally Municipality / Municipal Corporation; approval 010138/BP/HMDA/2092/MED/2022, dated 10 February, 2023. Proceedings No. 002309/BP/HMDA/MED/2023.
Approved building form: One residential building: 1 Stilt + 5 upper floors.
Built-up area: RERA fields record approved built-up area of 1146.10 sq. m. The permit extraction separately lists 1,146.10 Built-up Area and 1,379.05 Total Built up Area (In Sq.mts); these are the permit’s separately labelled figures.
Building / unit counts: One building in the RERA land record; 10 RERA-filed units. The supplied extraction does not give a floor-by-floor unit schedule.
Parking / mortgage figures in permit: Permit parameters include 120.18 Provided Mortgage area (In Sq.mts) and 114.61 Required 10% Mortgage area; the permit describes the mortgaged built-up area as in favour of MC, HMDA. These are not a count of resident parking spaces.
Offering and status
Configuration: 3BHK; RERA-filed saleable area 110.0 sq. m.
Bookings / availability: 0 booked; 10 available, as carried in the TG-RERA unit record. The portal-derived booking data has no as-of date, so counts are indicative.
Completion dates: Proposed and revised proposed completion dates both recorded as 10/02/2026; the Form B declaration also undertakes completion within three years from permission, stated as 10 February, 2026.
Construction stage: No independently verified site-progress assessment is supplied. RERA amenity fields report some infrastructure progress; details are in sections 6 and 9.
Occupancy certificate: No occupancy certificate is supplied in the reviewed documents. The building permit says an Occupancy Certificate is compulsory before occupation.
2. The project story
SRITAs MIHIR SYMPHONY is registered with TG-RERA as a residential apartment project on Plot No. 164 in Sy.No. 120, Kompally Village, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District. The RERA record describes one building on a 424.96 sq. m site, with one 3BHK configuration offered across 10 units.
The building permit records a residential building of 1 Stilt + 5 upper floors and specifies a proposed STP, rainwater-harvesting structures and underground and terrace water storage. These are permit requirements or parameters; the supplied information does not independently verify their completion.
The project’s RERA completion date is 10/02/2026, while the registration certificate records validity through that same date and states no extension. No occupancy certificate or independent construction-progress inspection is included in the supplied evidence. The RERA progress record lists water supply and sewerage as available at 70%; these are filed progress entries, not an independent site verification.
3. Master plan, architecture & building design
The project record identifies a single residential building on 424.96 sq. m of land. The sanctioned configuration in the permit extraction is 1 Stilt + 5 upper floors. No basement, podium, floor-by-floor apartment schedule, building footprint, tower arrangement, lift or stair details, internal-road plan, or landscaped-area plan is supplied.
The RERA field for approved built-up area is 1146.10 sq. m. The building permit separately lists 1,146.10 Built-up Area and 1,379.05 Total Built up Area (In Sq.mts). The evidence does not define the latter figure further, so these labels are retained as recorded rather than treated as interchangeable area measures.
The building permit states a minimum 4.5mts. width for entry and exit, 5mts. height clearance, and a minimum width of 4.5mts. in its road-width field. It also requires the stilt/cellar to be used exclusively for vehicle parking without partition walls or rolling shutters. The permit lists 25, 000 lts. underground static water storage and 25,000 lts. terrace tank.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 110.0 sq. m | Software-measured median 92.7 sq. m; range 92.4–93.2 sq. m | 16% |
RERA records the 3BHK saleable area as 110.0 sq. m. Software measurement from the approved floor-plan drawing records carpet area across four measured flat designs, with a median of 92.7 sq. m (998 sq. ft) and a range of 92.4–93.2 sq. m (994–1003 sq. ft). The drawing-derived measurements are not RERA-filed carpet-area disclosures and are identified as requiring review against the drawing. Saleable area and carpet area are different measures; the supplied floor-plan note says saleable area also counts the home’s share of common areas.
The measured typical-plan unit includes three bedrooms, a living/dining area, kitchen, wash area, three toilets and a utility area. The utility is identified as excluded from the software-measured carpet area. The supplied room schedule gives, among other dimensions, living/dining 3.18 × 8.11 m, kitchen 2.11 × 3.27 m, and utility 3.18 × 1.5 m. These are drawing-based measurements, not RERA area declarations.
5. Parking & vehicle circulation
The permit requires the stilt/cellar to be used exclusively for vehicle parking and records entry/exit width of 4.5mts. minimum and 5mts. height clearance. It does not provide a car-space or two-wheeler-space count in the supplied extraction. The permit records 120.18 sq. m as provided mortgage area, not as a parking-space allocation. No resident, visitor or accessible-space counts, EV charging provision, parking-allocation schedule, or legally documented exclusive allocation to individual units is supplied. A vendor listing mentions covered car parking, but the supplied project record does not establish its count or allocation.
6. Amenities, recreation & open spaces
The following progress figures are RERA-filed entries, not independent verification of completion. A 0% figure is retained as recorded; the supplied data does not explain whether it means work has not started or is not applicable.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip/TOT LOT/Park | Facility listed; no size supplied | Available: YES; 0% recorded; not independently verified | |
| Community Buildings | Listed; no description or size supplied | 0% recorded; not independently verified | |
| Aggregate area of recreational Open Space | Listed; no area supplied | 0% recorded; not independently verified | |
| Indoor games, swimming pool, gym, clubhouse and children’s play area | Vendor-listed amenities; no sizes or capacities supplied | Marketing/vendor listing only; no RERA progress or independent completion evidence supplied |
7. Utilities, building services & safety
Water: The permit lists 25, 000 lts. underground static water storage and 25,000 lts. terrace tank. RERA lists Water Supply as available: YES, 70%; no source, treatment system or independent verification is supplied.
Sewerage / drainage: The permit requires an STP. RERA lists “Sewerage (Chamber, Lines, Septic Tank, STP)” as available: YES, 70%. Storm Water Drains are recorded at 0%; no STP capacity or reuse details are supplied.
Rainwater harvesting: The permit requires rainwater-harvesting structures. RERA lists Water Conservation, Rain water Harvesting as available: YES, 0%. No completed-status verification is supplied.
Electrical: Electrical Meter Room, Sub-Station, Receiving Station is listed at 0% in the RERA progress record. No electrical capacity, backup-system details or completed status are supplied.
Vertical transportation: A vendor listing mentions a lift; the supplied permit extraction and project documents do not specify lift count, type or capacity.
Fire and life safety: Fire Protection and Fire Safety Requirements is listed at 0% in the RERA progress record. No fire-system specification or clearance document is supplied.
Waste / security / accessibility: Solid Waste Management and Disposal is recorded at 0%. The vendor lists security and CCTV, but no project-filed specification or verification is supplied. No accessibility details are provided.
8. Location, access & connectivity
The registered project location is Kompally, recorded as Kompally -Shivalayam, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District, PIN 500014. The title and permit records identify Kompally Village and Plot No. 164 in Sy.No. 120.
The location record supplies one approximate connectivity measurement: the nearest sampled Outer Ring Road interchange is 42.8 km from the project’s cadastral parcel centroid. No approach-road route, public-transport service, travel time or additional measured landmark distances are supplied.
9. Developer & development status
The TG-RERA registered promoter is SRITA PROJECTS, recorded as a proprietorship. The RERA party record names SHIVNATH NAMALA as authorized signatory; the filed Form B identifies him as proprietor and declarant for SRITA PROJECTS. The registration certificate lists the promoter office as Village: Olb Bowenpally, Mandal: Balanagar, District: Medchal-Malkajgiri, PIN 500011. No corporate registration identifier or official project contact details are supplied.
Form B declares completion within three years from the permission date, stated as 10 February, 2026. The RERA certificate states validity through 10/02/2026 and no extension. No independently verified construction percentage or occupancy certificate is included; the RERA infrastructure progress entries are listed in sections 6 and 7.
10. Approvals, official records & documents
TG-RERA registration: FORM ‘C’ records registration of SRITAs MIHIR SYMPHONY, registration no. P02200007223, under section 5, issued 08/11/2023 and valid through 10/02/2026.
Building permit: Permit order 010138/BP/HMDA/2092/MED/2022, dated 10 February, 2023, with proceedings no. 002309/BP/HMDA/MED/2023; records HMDA permission and a residential building of 1 Stilt + 5 upper floors.
Title and land records filed with RERA: Title report and sale-deed materials identify Plot No. 164, Block No. 12, Sy.No. 120, Kompally Village; the development agreement/GPA and title-report materials are in the RERA file.
Promoter declaration: Form B affidavit by SHIVANATH NAMALA for SRITA PROJECTS, dated March 2023, includes promoter declarations concerning title, encumbrances, project funds and completion.
Occupancy / completion certificate: No OC or completion certificate is supplied among the reviewed documents. The building permit states an Occupancy Certificate is compulsory before occupation.
Layout approval and floor-plan files: RERA document entries include layout-plan and building-floor-plan categories; the layout-plan item is not extracted, and the supplied floor-plan evidence includes drawing document 310132.
Frequently asked questions
Is SRITAs MIHIR SYMPHONY registered with Telangana RERA?
Yes. SRITAs MIHIR SYMPHONY is registered with the Telangana Real Estate Regulatory Authority as P02200007223; the registration status is On-Going Project.
Who is the developer of SRITAs MIHIR SYMPHONY?
The promoter named in the RERA registration is SRITA PROJECTS.
Where is SRITAs MIHIR SYMPHONY located?
SRITAs MIHIR SYMPHONY is in KOMPALLY, Kompally -Shivalayam, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana (500014).
When will SRITAs MIHIR SYMPHONY be completed?
The promoter's proposed date of completion filed with RERA is 10/02/2026. This is the promoter's declaration, not a guarantee.