Sri Nidhi Homes
SRI NIDHI HOMES · Nalgonda · RERA P01800009054
SRI NIDHI HOMES is a plotted development with open plots in Nalgonda, Nalgonda Mandal, Nalgonda District. The registered promoter developing it is SRI NIDHI HOMES, identified as a partnership. The TG-RERA land area is 78,157.00 sq. m, and the approved-layout documents state 268 plots; no towers, floors or home configurations are stated. It is registered under TG-RERA number P01800009054, and the promoter’s Form-B affidavit undertakes completion by 07/10/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | SRI NIDHI HOMES RERA record |
| Project type | Plotted development / residential layout with open plots RERA record |
| Phase or registered portion | A standalone phase is not identified in the supplied record; TG-RERA registration covers the project identified by survey numbers 1597, 1598 and 1602 |
| TG-RERA registration | P01800009054; registration certificate states validity from 08/10/2024 through 07/10/2026, unless extended by the Authority. This is the registration-validity period, not a statement of project completion or occupancy status. Approvals record |
| Registered promoter | SRI NIDHI HOMES, identified in the record as a partnership RERA record RERA filing Parties record |
| RERA status | Recorded as “New Project”; registration certificate issued RERA record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality | Nalgonda; the title report and approval documents further identify the land with Panagal / Aarjala Bavi (Arjalabai) RERA record |
| Revenue village(s) stated in project documents | PANAGAL Revenue Village in the tentative-layout approval; AARJALA BAVI VILLAGE in the layout-plan record; the title report describes Panagal Village and Panagal, Arjalabai area. These are the village descriptions appearing in the respective supplied records. |
| Mandal / district / PIN | Nalgonda Mandal; Nalgonda District; 508001 RERA record |
| All project survey numbers / subdivisions | Survey Nos. 1597, 1598 and 1602; layout and title records also identify 1597/P, 1598/P and 1602/P. RERA record Land records |
| Registered site area | TG-RERA land details state 78,157.00 sq. m total and net area RERA filing Land records |
| Layout-drawing area statement | The drawing states Total Layout Area 78,154.84 sq. mt, Net Layout Area 77,289.15 sq. mt, and Road Affected Area / Road Widening Area 865.69 sq. mt. |
| Boundaries on the RERA record | East: other land; west: 10 05 MT WIDE EXISTING ROAD; north: other land; south: other land. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority / principal approval | Nalgonda Municipality/Municipal Corporation, approval for tentative layout plan 0025/LO/3048/2024, dated 08 October 2024 Approvals record |
| Application / drawing reference | Application 009986/LO/NALG/3048/0045/2024; drawing file TS/047076/2024 Approvals record |
| Development form | Open-plot residential layout; the layout record identifies 268 individual sub-plots. |
| Approved built-up area | The layout record states proposed built-up area 0.00, both excluding and including parking; it does not provide a building or floor configuration for homes. |
| Building/tower count and floors | Not disclosed in the supplied project record; this is a plotted layout, and no residential building-floor schedule is provided. |
| Plot-area totals in the records | Layout drawing: plotted area 44,411.59 sq. m; tentative approval: 10 Acer 38.98 Gts 53118 Sq. Yds. |
Offering and status
| Field | Record |
|---|---|
| Product offered | Residential plots; the layout schedule is software-read as 267 plots with size information, while the approved-layout documents state 268 plots. Layout record |
| Plot-size range from drawing | Software-read range: 102.29–354.68 sq. m (122.3–424.2 sq. yd); drawing-derived figures should be checked against the approved drawing. Layout record |
| Booked / available plots | Not provided in the supplied evidence. RERA filing Layout record |
| Construction / development stage | No independently verified site-progress status is supplied. The RERA Form-B affidavit records the promoter’s undertaking to complete by 07/10/2026; the layout approval requires infrastructure and amenities within two years of approval, by 08 October 2026. These are separate recorded timelines. |
| Occupancy / completion certificate | No occupancy or completion certificate is identified in the supplied project documents. The layout is recorded as a tentative layout approval; no building-level OC scope applies in the supplied evidence. |
2. The project story
- SRI NIDHI HOMES is registered with TG-RERA as a plotted residential development on land identified by survey numbers 1597, 1598 and 1602, including the 1597/P, 1598/P and 1602/P subdivisions appearing in layout and title records. The official project documents locate the land in Nalgonda Mandal and District, describing the revenue location as Panagal and/or Aarjala Bavi (Arjalabai).
- The layout approval describes 268 plots and requires the developer to provide layout infrastructure and amenities. The drawing-based schedule extraction identifies 267 plots with sizes; this is a software-read drawing result, not a RERA inventory of plots currently available for sale. The supplied evidence does not state which plots have been booked or are available, nor independently establish current construction progress. Layout record
- The approval sets a two-year period from 08 October 2024 for infrastructure and amenities, while the promoter’s Form-B affidavit undertakes project completion by 07/10/2026. Neither timeline establishes that the works have been completed. No completion or occupancy certificate is present in the supplied evidence.
3. Master plan, architecture & building design
This is a plotted layout rather than a documented apartment or villa scheme. The layout plan identifies 268 individual sub-plots, with proposed built-up area recorded as 0.00 both excluding and including parking. Accordingly, the supplied plan data does not establish a home-building count, building footprint, height, floor configuration or tower arrangement.
The drawing’s land-use statement gives a net layout area of 77,289.09 sq. m and allocates it as follows. These are drawing-extracted figures, not independently surveyed measurements.
| Layout use | Area (sq. m) | Share |
|---|---|---|
| Plotted area | 44,411.59 | 57.46% |
| Roads | 23,210.70 | 30.03% |
| Organized open space / park | 6,961.29 | 9.01% |
| Social infrastructure | 1,932.51 | 2.50% |
| Utility area | 773.00 | 1.00% |
| Total net layout | 77,289.09 | 100.00% |
The layout drawing identifies 10.05 m existing road width, 18.00 m proposed road, a 4.12 m road-widening area, 12.00 m and 9.00 m internal roads, and a 150'-0" WIDE ROAD. The supplied records do not identify which road segments correspond to each width beyond these drawing labels.
4. Homes, configurations & floor plans
- No apartment or villa configuration schedule is supplied. The offering identified in the RERA and layout records is residential plots. RERA record
- The drawing-based plot schedule reports 267 plots with size information, while the approved-layout documents state 268 plots. The plot count and areas below are software-read from the drawing and should be verified against the approved layout; they are not RERA-filed booked/available inventory figures. Layout record
| Plot information | Drawing-derived record |
|---|---|
| Plot count in schedule | 267 |
| Plots with size information | 267 |
| Smallest plot | 102.29 sq. m / 122.3 sq. yd |
| Median plot | 153.29 sq. m / 183.3 sq. yd |
| Largest plot | 354.68 sq. m / 424.2 sq. yd |
| Size band | Plot count |
|---|---|
| 100–150 sq. yd | 8 |
| 150–200 sq. yd | 153 |
| 200–250 sq. yd | 85 |
| 250–300 sq. yd | 11 |
| 300–400 sq. yd | 7 |
| 400–500 sq. yd | 3 |
The floor-plan extraction reports two layout sheets and no residential flat plans measured. Carpet-area, room-dimension and apartment saleable-area figures are therefore not available. Floor plans
5. Parking & vehicle circulation
- The layout drawing records 0.00 proposed built-up area including parking and 0.00 common parking area in its land-use schedule; no parking-space count, visitor or accessible parking provision, parking allocation to individual plots, or vehicle-storage arrangement is supplied.
- Roads are shown in the layout records, including 12.00 Mts wide Internal Road, 9.00 Mts wide Internal Road, 18.00 MT WIDE PROPOSED ROAD, and 150'-0" WIDE ROAD. The records do not establish a parking plan, driveway/entry arrangement, pedestrian-vehicle separation or EV-charging provision.
6. Amenities, recreation & open spaces
The layout approval requires infrastructure and amenities to be completed within two years of its 08 October 2024 approval date. The drawing identifies open space, social infrastructure and utility land; the listed facilities below are approval or drawing records, not confirmation of completion. No independently verified completion status is supplied.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / open space | Approval: 1 Acer 28.81 Gts 8326 Sq. Yds, 9.01%; drawing: 6,961.29 sq. m, 9.01% | Reserved/provided for in approval and drawing; completion not verified | |
| Tot-lot | Identified on layout drawing | Drawing label; completion not verified | |
| Social infrastructure | Drawing: 1,932.51 sq. m, 2.50% | Reserved in layout; specific facility and completion status not supplied | |
| Utility land | Approval: 0 Acer 7.64 Gts 925 Sq. Yds, 1%; drawing: 773.00 sq. m, 1.00% | Reserved in layout; completion not verified |
The promoter/vendor amenity list also names a clubhouse, swimming pool, gym and children’s play area, but the supplied layout evidence does not establish these as sanctioned or delivered facilities. Promoter website
7. Utilities, building services & safety
The tentative-layout approval describes required development works that include road formation with black top, storm-water drains, underground drainage lines and a common septic tank / STP, internal water-supply pipelines, an overhead tank, assured water-supply source, electrical supply lines and street lights, transformer, avenue plantation, park development and rainwater-harvesting pits. These are approval-condition descriptions; the evidence does not confirm installation, capacity or operating status.
The approval also lists a water reservoir, septic tank, sewerage treatment plant, solid-waste management, storm-water drains, underground drainage, internal water pipelines, overhead tank, street lighting and rainwater-harvesting pits. The supplied documents do not state water source yield, storage capacity, STP capacity, treatment/reuse volumes, electrical load, backup provision, fire-safety systems, CCTV, accessibility works or utility commissioning status.
8. Location, access & connectivity
- The project documents identify the land in Nalgonda Mandal, Nalgonda District, with the layout approval describing PANAGAL Revenue Village and the drawing describing AARJALA BAVI VILLAGE. The title report also uses Panagal / Arjalabai descriptions. The RERA-recorded western boundary is a 10 05 MT WIDE EXISTING ROAD. RERA filing
- The location dataset supplies one mapped connectivity point: Financial District (Nanakramguda), 1.2 km. This is a supplied mapped distance; no public-transport details, journey times or other nearby landmarks are provided. Location record
9. Developer & development status
- The registered promoter is SRI NIDHI HOMES, identified as a partnership in the RERA project record. The supplied corporate identifier is GSTIN 36AFKFS6710E1ZY. The recorded office address is B, V T COLONY, PANAGAL, NALGONDA, Nalgonda, Nalgonda, 508001. RERA record RERA filing Corporate record Parties record
- The Form-B affidavit is a promoter declaration signed by authorized signatory PALAKURI VENKATESHAM; it records the promoter’s undertaking to complete by 07/10/2026. The evidence provides no verified site-progress percentage, booked/available plot inventory or completed-works certification.
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C registration certificate for SRI NIDHI HOMES, registration P01800009054; validity stated as 08/10/2024–07/10/2026, unless extended. |
| Principal tentative-layout approval | Nalgonda Municipality/Municipal Corporation approval 0025/LO/3048/2024, dated 08 October 2024, for survey numbers 1597, 1598 and 1602 at Panagal Revenue Village. |
| Layout drawing / layout-plan record | TS-DTCP file TS/047076/2024; layout records identify 1597/P, 1598/P and 1602/P, and describe Aarjala Bavi Village, Nalgonda Mandal and District. |
| Title scrutiny report | Advocate’s report dated 03-09-2024, identifying the landowners and discussing title records, layout permission and the 2024 gift and mortgage deeds. |
| Form-B promoter declaration | Affidavit by authorized signatory PALAKURI VENKATESHAM, including the promoter’s completion undertaking and other declarations. |
| Registration certificate conditions | The certificate states that conveyance deeds are to be executed and registered in favour of allottees or the association, as applicable. |
| Completion / occupancy records | No completion or occupancy certificate is identified in the supplied evidence. Document index |
1. Project at a glance
Project identity
Registered project name: SRI NIDHI HOMES
Project type: Plotted development / residential layout with open plots
Phase or registered portion: A standalone phase is not identified in the supplied record; TG-RERA registration covers the project identified by survey numbers 1597, 1598 and 1602
TG-RERA registration: P01800009054; registration certificate states validity from 08/10/2024 through 07/10/2026, unless extended by the Authority. This is the registration-validity period, not a statement of project completion or occupancy status.
Registered promoter: SRI NIDHI HOMES, identified in the record as a partnership
RERA status: Recorded as “New Project”; registration certificate issued
Land and geographic identity
Locality: Nalgonda; the title report and approval documents further identify the land with Panagal / Aarjala Bavi (Arjalabai)
Revenue village(s) stated in project documents: PANAGAL Revenue Village in the tentative-layout approval; AARJALA BAVI VILLAGE in the layout-plan record; the title report describes Panagal Village and Panagal, Arjalabai area. These are the village descriptions appearing in the respective supplied records.
Mandal / district / PIN: Nalgonda Mandal; Nalgonda District; 508001
All project survey numbers / subdivisions: Survey Nos. 1597, 1598 and 1602; layout and title records also identify 1597/P, 1598/P and 1602/P.
Registered site area: TG-RERA land details state 78,157.00 sq. m total and net area
Layout-drawing area statement: The drawing states Total Layout Area 78,154.84 sq. mt, Net Layout Area 77,289.15 sq. mt, and Road Affected Area / Road Widening Area 865.69 sq. mt.
Boundaries on the RERA record: East: other land; west: 10 05 MT WIDE EXISTING ROAD; north: other land; south: other land.
Development identity
Sanctioning authority / principal approval: Nalgonda Municipality/Municipal Corporation, approval for tentative layout plan 0025/LO/3048/2024, dated 08 October 2024
Application / drawing reference: Application 009986/LO/NALG/3048/0045/2024; drawing file TS/047076/2024
Development form: Open-plot residential layout; the layout record identifies 268 individual sub-plots.
Approved built-up area: The layout record states proposed built-up area 0.00, both excluding and including parking; it does not provide a building or floor configuration for homes.
Building/tower count and floors: Not disclosed in the supplied project record; this is a plotted layout, and no residential building-floor schedule is provided.
Plot-area totals in the records: Layout drawing: plotted area 44,411.59 sq. m; tentative approval: 10 Acer 38.98 Gts 53118 Sq. Yds.
Offering and status
Product offered: Residential plots; the layout schedule is software-read as 267 plots with size information, while the approved-layout documents state 268 plots.
Plot-size range from drawing: Software-read range: 102.29–354.68 sq. m (122.3–424.2 sq. yd); drawing-derived figures should be checked against the approved drawing.
Booked / available plots: Not provided in the supplied evidence.
Construction / development stage: No independently verified site-progress status is supplied. The RERA Form-B affidavit records the promoter’s undertaking to complete by 07/10/2026; the layout approval requires infrastructure and amenities within two years of approval, by 08 October 2026. These are separate recorded timelines.
Occupancy / completion certificate: No occupancy or completion certificate is identified in the supplied project documents. The layout is recorded as a tentative layout approval; no building-level OC scope applies in the supplied evidence.
2. The project story
- SRI NIDHI HOMES is registered with TG-RERA as a plotted residential development on land identified by survey numbers 1597, 1598 and 1602, including the 1597/P, 1598/P and 1602/P subdivisions appearing in layout and title records. The official project documents locate the land in Nalgonda Mandal and District, describing the revenue location as Panagal and/or Aarjala Bavi (Arjalabai).
- The layout approval describes 268 plots and requires the developer to provide layout infrastructure and amenities. The drawing-based schedule extraction identifies 267 plots with sizes; this is a software-read drawing result, not a RERA inventory of plots currently available for sale. The supplied evidence does not state which plots have been booked or are available, nor independently establish current construction progress.
- The approval sets a two-year period from 08 October 2024 for infrastructure and amenities, while the promoter’s Form-B affidavit undertakes project completion by 07/10/2026. Neither timeline establishes that the works have been completed. No completion or occupancy certificate is present in the supplied evidence.
3. Master plan, architecture & building design
This is a plotted layout rather than a documented apartment or villa scheme. The layout plan identifies 268 individual sub-plots, with proposed built-up area recorded as 0.00 both excluding and including parking. Accordingly, the supplied plan data does not establish a home-building count, building footprint, height, floor configuration or tower arrangement.
The drawing’s land-use statement gives a net layout area of 77,289.09 sq. m and allocates it as follows. These are drawing-extracted figures, not independently surveyed measurements.
| Layout use | Area (sq. m) | Share |
|---|---|---|
| Plotted area | 44,411.59 | 57.46% |
| Roads | 23,210.70 | 30.03% |
| Organized open space / park | 6,961.29 | 9.01% |
| Social infrastructure | 1,932.51 | 2.50% |
| Utility area | 773.00 | 1.00% |
| Total net layout | 77,289.09 | 100.00% |
The layout drawing identifies 10.05 m existing road width, 18.00 m proposed road, a 4.12 m road-widening area, 12.00 m and 9.00 m internal roads, and a 150'-0" WIDE ROAD. The supplied records do not identify which road segments correspond to each width beyond these drawing labels.
4. Homes, configurations & floor plans
- No apartment or villa configuration schedule is supplied. The offering identified in the RERA and layout records is residential plots.
- The drawing-based plot schedule reports 267 plots with size information, while the approved-layout documents state 268 plots. The plot count and areas below are software-read from the drawing and should be verified against the approved layout; they are not RERA-filed booked/available inventory figures.
Plot count in schedule: 267
Plots with size information: 267
Smallest plot: 102.29 sq. m / 122.3 sq. yd
Median plot: 153.29 sq. m / 183.3 sq. yd
Largest plot: 354.68 sq. m / 424.2 sq. yd
100–150 sq. yd: 8
150–200 sq. yd: 153
200–250 sq. yd: 85
250–300 sq. yd: 11
300–400 sq. yd: 7
400–500 sq. yd: 3
The floor-plan extraction reports two layout sheets and no residential flat plans measured. Carpet-area, room-dimension and apartment saleable-area figures are therefore not available.
5. Parking & vehicle circulation
- The layout drawing records 0.00 proposed built-up area including parking and 0.00 common parking area in its land-use schedule; no parking-space count, visitor or accessible parking provision, parking allocation to individual plots, or vehicle-storage arrangement is supplied.
- Roads are shown in the layout records, including 12.00 Mts wide Internal Road, 9.00 Mts wide Internal Road, 18.00 MT WIDE PROPOSED ROAD, and 150'-0" WIDE ROAD. The records do not establish a parking plan, driveway/entry arrangement, pedestrian-vehicle separation or EV-charging provision.
6. Amenities, recreation & open spaces
The layout approval requires infrastructure and amenities to be completed within two years of its 08 October 2024 approval date. The drawing identifies open space, social infrastructure and utility land; the listed facilities below are approval or drawing records, not confirmation of completion. No independently verified completion status is supplied.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Park / open space | Approval: 1 Acer 28.81 Gts 8326 Sq. Yds, 9.01%; drawing: 6,961.29 sq. m, 9.01% | Reserved/provided for in approval and drawing; completion not verified | |
| Tot-lot | Identified on layout drawing | Drawing label; completion not verified | |
| Social infrastructure | Drawing: 1,932.51 sq. m, 2.50% | Reserved in layout; specific facility and completion status not supplied | |
| Utility land | Approval: 0 Acer 7.64 Gts 925 Sq. Yds, 1%; drawing: 773.00 sq. m, 1.00% | Reserved in layout; completion not verified |
The promoter/vendor amenity list also names a clubhouse, swimming pool, gym and children’s play area, but the supplied layout evidence does not establish these as sanctioned or delivered facilities.
7. Utilities, building services & safety
The tentative-layout approval describes required development works that include road formation with black top, storm-water drains, underground drainage lines and a common septic tank / STP, internal water-supply pipelines, an overhead tank, assured water-supply source, electrical supply lines and street lights, transformer, avenue plantation, park development and rainwater-harvesting pits. These are approval-condition descriptions; the evidence does not confirm installation, capacity or operating status.
The approval also lists a water reservoir, septic tank, sewerage treatment plant, solid-waste management, storm-water drains, underground drainage, internal water pipelines, overhead tank, street lighting and rainwater-harvesting pits. The supplied documents do not state water source yield, storage capacity, STP capacity, treatment/reuse volumes, electrical load, backup provision, fire-safety systems, CCTV, accessibility works or utility commissioning status.
8. Location, access & connectivity
- The project documents identify the land in Nalgonda Mandal, Nalgonda District, with the layout approval describing PANAGAL Revenue Village and the drawing describing AARJALA BAVI VILLAGE. The title report also uses Panagal / Arjalabai descriptions. The RERA-recorded western boundary is a 10 05 MT WIDE EXISTING ROAD.
- The location dataset supplies one mapped connectivity point: Financial District (Nanakramguda), 1.2 km. This is a supplied mapped distance; no public-transport details, journey times or other nearby landmarks are provided.
9. Developer & development status
- The registered promoter is SRI NIDHI HOMES, identified as a partnership in the RERA project record. The supplied corporate identifier is GSTIN 36AFKFS6710E1ZY. The recorded office address is B, V T COLONY, PANAGAL, NALGONDA, Nalgonda, Nalgonda, 508001.
- The Form-B affidavit is a promoter declaration signed by authorized signatory PALAKURI VENKATESHAM; it records the promoter’s undertaking to complete by 07/10/2026. The evidence provides no verified site-progress percentage, booked/available plot inventory or completed-works certification.
10. Approvals, official records & documents
TG-RERA registration: Form C registration certificate for SRI NIDHI HOMES, registration P01800009054; validity stated as 08/10/2024–07/10/2026, unless extended.
Principal tentative-layout approval: Nalgonda Municipality/Municipal Corporation approval 0025/LO/3048/2024, dated 08 October 2024, for survey numbers 1597, 1598 and 1602 at Panagal Revenue Village.
Layout drawing / layout-plan record: TS-DTCP file TS/047076/2024; layout records identify 1597/P, 1598/P and 1602/P, and describe Aarjala Bavi Village, Nalgonda Mandal and District.
Title scrutiny report: Advocate’s report dated 03-09-2024, identifying the landowners and discussing title records, layout permission and the 2024 gift and mortgage deeds.
Form-B promoter declaration: Affidavit by authorized signatory PALAKURI VENKATESHAM, including the promoter’s completion undertaking and other declarations.
Registration certificate conditions: The certificate states that conveyance deeds are to be executed and registered in favour of allottees or the association, as applicable.
Completion / occupancy records: No completion or occupancy certificate is identified in the supplied evidence.
Frequently asked questions
Is SRI NIDHI HOMES registered with Telangana RERA?
Yes. SRI NIDHI HOMES is registered with the Telangana Real Estate Regulatory Authority as P01800009054; the registration status is New Project.
Who is the developer of SRI NIDHI HOMES?
The promoter named in the RERA registration is SRI NIDHI HOMES.
Where is SRI NIDHI HOMES located?
SRI NIDHI HOMES is in NALGONDA, Telangana (508001).
When will SRI NIDHI HOMES be completed?
The promoter's proposed date of completion filed with RERA is 07/02/2027. This is the promoter's declaration, not a guarantee.