Sign in

Skyline

DHAMANSH GLOBAL LLP · Vikarabad · RERA P02100004247

SKYLINE is a plotted development at Yenkepally, Bommaraspet Mandal, Vikarabad District. The registered promoter is DHAMANSH GLOBAL LLP. The RERA project fields state a total area of 38,951 sq mts and a net area of 38,457.29 sq mts; the draft layout records 123 plots, with no plot configurations stated. It is registered under TG-RERA number P02100004247, with proposed completion on 20/02/2027.

01What we found

Period endedTG-RERA registration ran to 20 Oct 2026 - check its extension on TG-RERA
9documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Yenkepally, Bommaraspet, Vikarabad · geocoded — approximate.

1. Project at a glance

Project identity

FieldProject record
Registered nameSKYLINE
Project typePlotted development RERA record
Registered phase / portionNot separately identified in the supplied record; the registration identifies the project against Survey Nos. 174/P and 175/P.
TG-RERA registration numberP02100004247
Registration validity14 March 2022 to 20 October 2026; the certificate says four years and states validity may be extended by the Authority. This is the registration period, not the project completion deadline.
Registered promoterDHAMANSH GLOBAL LLP
RERA status in supplied recordRegistered; the certificate records registration under section 5. A current status check is not included.

Land and geographic identity

FieldProject record
LocalityYenkepally / YENKEPALLY RERA record
Revenue villageYenkepally (also rendered “Yenkepalle” in land-record material) RERA record
MandalBommaraspet RERA record
DistrictVikarabad RERA record
PIN509338
Project survey numbers and subdivisions174/P and 175/P; no further project subdivision is stated in the registration certificate or supplied layout approval.
Site area stated in RERA project fieldsTotal area 38,951 sq mts; affected area 493.71 sq mts; net area 38,457.29 sq mts. RERA filing
Layout approval areaThe filed Draft Technical Layout Pattern records layout area Ac. 9.625 Cents; 46,585.00 Sq. Yds., road-affected area Ac. 0.122 Cents; 590.48 Sq. Yds, and net layout area Ac. 9.503 Cents; 45,994.52 Sq. Yds.
Boundaries in RERA fieldsEast: ROAD; west, north and south: OTHERS LAND. RERA filing

Development identity

FieldProject record
Sanctioning authorityDirector of Town and Country Planning; delegated to Yenkepally Gram Panchayat.
Principal approvalDraft Technical Layout Pattern Draft-TLP.No.304/2021/H, approved 21-10-2021; file Lr.Roc.No.12166/2382/2021/e-Panchayat.
Layout scale and land-use splitDraft layout for 123 plots. It records open space Ac. 0.950 Cents; 10.00 %, roads Ac. 2.887 Cents; 30.37 %, plotted area Ac. 5.666 Cents; 59.63 %, and mortgage area Ac. 0.879 Cents; 15.51 %.
Approved built-up areaNot disclosed in the supplied layout approval. The RERA project fields separately report approved built-up area 22,930 sq mts; the supporting measurement/drawing is not supplied here. RERA filing
Buildings, floors and parking levelsNot applicable to the supplied approval’s plotted-layout description; building or parking-level particulars are not disclosed.
Plot countsThe approval records 123 plots. Plot-size schedule and plot-wise availability are not supplied.

Offering and status

FieldProject record
Unit typePlots; no apartment or villa configuration is evidenced in the registration record. RERA record
RERA-recorded project area38,457.29 sq mts net area in the project fields. RERA filing
Booked / available plotsNot disclosed in the supplied data.
Construction or development stageRERA amenity records show internal roads and footpaths at 20%; the other listed progress entries shown are 0%. These are filed progress figures, not independent site verification. RERA amenities
Completion deadlineThe project header records proposed completion 20/02/2027. The Form B declaration separately gives an undertaking date of 23-01-2026; the supplied evidence does not clarify its relationship to the header’s proposed date. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied documents. Document index

2. The project story

SKYLINE is registered as a plotted development at Yenkepally, Bommaraspet Mandal, Vikarabad District, on Survey Nos. 174/P and 175/P. The filed DTCP Draft Technical Layout Pattern describes a 123-plot layout, with land identified for plots, roads, open space and mortgage. Its land-use schedule records 10.00 % open space and 30.37 % roads; the approval also requires development works and subsequent release of a final layout. RERA record

The supplied records establish the layout approval and RERA registration, but do not provide a verified plot inventory, plot-size schedule, plot-wise booking status, or independently inspected construction stage. RERA’s amenity entries report 20% for internal roads and footpaths and 0% for the other listed progress entries; these figures are filing-reported, not independently verified. No occupancy or completion certificate is supplied. RERA amenities Document index

3. Master plan, architecture & building design

The project is a plotted layout rather than a building scheme in the supplied approval. DTCP’s Draft Technical Layout Pattern records 123 plots across Survey Nos. 174/P and 175/P, with the following land-use schedule:

Layout componentFiled area / share
Layout areaAc. 9.625 Cents; 46,585.00 Sq. Yds.
Road-affected areaAc. 0.122 Cents; 590.48 Sq. Yds
Net layout areaAc. 9.503 Cents; 45,994.52 Sq. Yds.
Open spaceAc. 0.950 Cents; 4,598.00 Sq. Yds.; 10.00 %
RoadsAc. 2.887 Cents; 13,973.08 Sq. Yds; 30.37 %
Plotted areaAc. 5.666 Cents; 27,423.44 Sq. Yds.; 59.63 %
Mortgage areaAc. 0.879 Cents; 4,254.36 Sq. Yds.; 15.51 %

The approval identifies mortgage plots as Plot Nos. 1 to 7, 114 to 116, and 119 to 123, in favour of Yenkepally Gram Panchayat. It also specifies that open space and roads are to be handed over to the Gram Panchayat by registered gift deed before release of the final layout.

No plot-wise drawing or dimension schedule, building footprint, floor configuration, or apartment floor plan is included in the supplied records. The RERA fields report approved built-up area of 22,930 sq mts, but the supplied layout approval does not explain the basis or scope of that figure. RERA filing Document index

4. Homes, configurations & floor plans

The registration identifies a plotted development and the filed layout approval records 123 plots. Plot-size bands, plot-wise saleable areas, booked and available counts, and individual plot dimensions are not disclosed in the supplied data. RERA record

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Plots123 in the draft layoutNot disclosedNot disclosedPlot-wise area not disclosedNot applicableNot supplied

The available floor-plan set consists of three scans pending measurement, with no completed software-measured carpet-area results. Apartment carpet-area or loading figures therefore cannot be reported for this plotted project. Floor plans

5. Parking & vehicle circulation

The supplied layout approval describes roads and plots but does not state parking-space counts, parking allocation by plot, visitor or accessible parking, EV charging, or dedicated parking areas. It requires that all roads be opened for accessibility to neighbouring sites and prohibits constructing a compound wall or fencing around the site. This is an approval condition, not evidence of completed roads or verified access.

No exclusive parking entitlement can be established from the supplied records. Document index

6. Amenities, recreation & open spaces

The DTCP draft layout approval specifies layout works and facilities. RERA progress entries are included where supplied; they are filed progress figures and not independent completion verification. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Open spaceAc. 0.950 Cents; 10.00 % of the layoutDTCP draft layout approvalRERA lists aggregate recreational open space as available; progress entry 0%. Not independently verified complete. RERA amenities
Internal roads and footpathsLayout roads area Ac. 2.887 Cents; 30.37 %DTCP draft layout approval; RERA amenity recordRERA-declared progress 20%; not independently verified complete. RERA amenities
Greenery and avenue plantationRequired in the layoutDTCP draft layout approvalNo completion evidence supplied.
Fencing of open spacesRequiredDTCP draft layout approvalNo completion evidence supplied.
Community buildingsNo size or facility detail suppliedRERA amenity recordProgress entry 0%; no completion evidence supplied. RERA amenities
Park / green strip / tot lotNo size or quantity suppliedRERA amenity recordListed as available; progress entry 0%; no independent verification. RERA amenities

A third-party listing names a clubhouse, swimming pool, gym and children’s play area, but the supplied TG-RERA layout approval and amenity data do not establish these as sanctioned or delivered project facilities. Promoter website

7. Utilities, building services & safety

The layout approval specifies proposed utility and site works, while the RERA amenity data reports their progress. No capacities, engineering designs, completion certificates or independent inspections are supplied. RERA amenities

ServiceSupplied record
WaterDraft layout conditions specify protected water supply. RERA lists water supply as available with progress 0%. Source, storage, treatment and capacity are not disclosed. RERA amenities
Sewerage and drainageThe approval specifies a sewerage disposal system and construction of drains and channelization of nalas. RERA lists sewerage and storm-water drains as available, each with progress 0%. System design and capacity are not disclosed. RERA amenities
Rainwater managementThe approval specifies rainwater harvesting pits; RERA lists water conservation/rainwater harvesting as available with progress 0%. RERA amenities
Electricity and lightingThe approval specifies electricity facilities and street lighting. RERA lists street lighting as available with progress 0%; a substation or electrical receiving-station detail is not supplied. RERA amenities
Waste managementRERA lists solid-waste management and disposal with progress 0%. The collection, treatment and disposal arrangements are not described. RERA amenities
Fire and life safetyRERA lists fire-protection and fire-safety requirements with progress 0%. No project-specific fire-system design or clearance is supplied. RERA amenities
Power backup, CCTV and securityThese are named in a third-party listing, but project-specific RERA or approval details and verified status are not supplied. Promoter website
Lifts and accessibilityNo lift or accessibility design is established by the supplied plotted-layout approval.

8. Location, access & connectivity

The registered location is Yenkepally, Bommaraspet Mandal, Vikarabad District, Telangana, PIN 509338; the registered survey identity is 174/P and 175/P. RERA record

The layout approval states that roads are to be opened for access to neighbouring sites. A supplied location record measures the nearest sampled Outer Ring Road interchange at approximately 78.2 km; this is a mapped distance, not a travel-time estimate. The third-party listing says the project is close to schools, airports and restaurants but gives no distances, so those proximity claims are not quantified here. Location record Promoter website

9. Developer & development status

The registered promoter is DHAMANSH GLOBAL LLP, an LLP, with GSTIN 36AASFD2253N1ZY. The supplied promoter information names Shravan Kumar Reddy P, Neha Nair and Dhan Srinivas Kumar Raja Tadicherla as partners; all three are also listed as authorized signatories. Corporate record Parties record

The RERA record gives proposed completion as 20/02/2027. The Form B declaration states a completion undertaking of 23-01-2026; the supplied documents do not explain the relationship between these dates. The registration certificate’s validity ends 20/10/2026, which is a separate registration-validity date. No extension order or completion/occupancy certificate is supplied. RERA record Document index

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C registration certificate for SKYLINE, P02100004247, issued 14/03/2022, valid through 20/10/2026 as stated in the certificate.
Principal layout approvalDTCP Draft Technical Layout Pattern Draft-TLP.No.304/2021/H, dated 21-10-2021, for Survey Nos. 174/P and 175/P; file Lr.Roc.No.12166/2382/2021/e-Panchayat; delegated to Yenkepally Gram Panchayat.
Form B declarationPromoter-filed declaration concerning title basis, encumbrances, completion and fund-management undertakings. The declaration’s verification date is partly illegible.
Layout plan and conditionsThe supplied approval extraction records 123 plots, land-use areas, mortgage plots, proposed utilities and conditions for development and final layout release.
Completion / occupancy documentationNo completion or occupancy certificate is included in the supplied documents. Document index
Project-specific building plansNo building-plan drawing or plot-wise schedule is included in the supplied documents. Document index

The supplied layout approval expressly states that it is not proof of land title.

Frequently asked questions

Is SKYLINE registered with Telangana RERA?

Yes. SKYLINE is registered with the Telangana Real Estate Regulatory Authority as P02100004247; the registration status is New Project.

Who is the developer of SKYLINE?

The promoter named in the RERA registration is DHAMANSH GLOBAL LLP.

Where is SKYLINE located?

SKYLINE is in YENKEPALLY, Bommaraspet, Vikarabad, Telangana (509338).

When will SKYLINE be completed?

The promoter's proposed date of completion filed with RERA is 20/02/2027. This is the promoter's declaration, not a guarantee.

More projects in Bommaraspet