Platinum City

M/s SRI SIDDI VINAYAKA DEVELOPERS · Mahabubnagar · RERA P01400006299

PLATINUM CITY is a plotted development in Macharam Revenue Village, Balanagar Mandal, Mahabubnagar District. The registered promoter is M/s SRI SIDDI VINAYAKA DEVELOPERS. The registered site extent is 74769.31 sq m, and the tentative layout provides for 351 plots; no building or floor configuration is disclosed. The project is registered with TG-RERA under P01400006299, with a proposed completion date of 18/04/2025.

More from Sri Siddi Vinayaka Developers · 9 projects →

01What we found

Period endedTG-RERA registration ran to 18 Apr 2025 - check its extension on TG-RERA
15documents on file - each fact links to its page
0court cases on this project's land in the court records searched
6items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

ItemProject record
Registered namePLATINUM CITY RERA record
Project typePlotted development; the filed approval is for a tentative layout plan RERA record
Phase / registered portionNo phase name or separate phase designation disclosed; registration is for the project identified by the survey numbers below RERA record
TG-RERA registrationP01400006299
Registration validity07/07/2023–18/04/2025; the supplied certificate records these validity dates. Registration validity is distinct from the completion deadline.
RERA status in supplied recordFiled as a “New Project”; no extension is recorded in the supplied certificate extract. Current registration status should be checked with TG-RERA. RERA record
Registered promoterM/s SRI SIDDI VINAYAKA DEVELOPERS RERA record

Land and geographic identity

ItemProject record
Locality / revenue villageMacharam; the approval identifies Macharam Revenue Village RERA record
Mandal / district / PINBalanagar Mandal; Mahabubnagar District; PIN 539301 RERA record
Project survey numbers and subdivisions31/P, 35/P, 36/P, 37/P & 49 RERA record
Registered site extentThe RERA land record states 74769.31 sq m total and net area RERA filing
Drawing-derived area statementLayout drawing area statement totals 74768.72 sq m; it allocates 42583.44 sq m to plots, 22738.76 sq m to roads, 6777.38 sq m to parks/open space, 750.58 sq m to utilities and 1918.56 sq m to social infrastructure. These are drawing-derived figures. Layout record
Road-widening areaRERA land record: 0 sq m affected; the layout record separately identifies 447.23 sq m road-widening area. RERA filing Layout record
BoundariesEast, west, north and south: “OTHERS LAND” in the RERA land record; named adjoining properties are not disclosed. RERA filing

Development identity

ItemProject record
Sanctioning authorityMUDA Urban Development Authority; the filed tentative layout approval records delegation to Macharam Grampanchayat. Approvals record
Principal approval255005/LP/GP/280120/0001/2023, approved 18-04-2023; described in the filed approval as an APPROVAL FOR TENTATIVE LAYOUT PLAN. Approvals record
Development scale351 plots in the approval and layout schedule Layout record
Approved built-up areaNot stated in the supplied layout approval. The RERA form lists 42583.79 sq m as “Approved Built up Area”; this is a filed figure, not a building-area or plot-area measurement. RERA filing
Building / floor configurationNot applicable as a multi-storey building schedule in the supplied evidence; no building, floor or parking-level configuration is disclosed for this plotted layout.
Approval statusTentative layout approval is on file. The approval requires development works, a work-completion certificate and a final layout plan; no final layout approval is supplied.

Offering and status

ItemProject record
OfferingPlots; 351 shown in the approved layout schedule Layout record
Plot-size rangeSoftware-measured from the approved layout drawing: 66.1–235.64 sq m (79.1–281.8 sq yd); median 122.63 sq m (146.7 sq yd). Verify against the drawing before relying on an individual plot measurement. Layout record
Booked / available countsNot disclosed in the supplied RERA record. RERA filing
Construction / development stageRERA-filed progress reports list internal roads and footpaths at 65%, green strip/tot lot/park at 45%, street lighting at 30%, and rainwater harvesting at 25%; several other listed items show 0%. These are reported percentages, not independently verified site progress. RERA amenities
Completion datesRERA registration certificate and Form B declaration state 18/04/2025 as the end date / undertaking; no revised completion date is supplied.
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The filed approval is tentative and calls for completion certification and final-layout approval.

The project story

PLATINUM CITY is a proposed plotted layout in Macharam Revenue Village, Balanagar Mandal, Mahabubnagar District, covering the registered survey identification 31/P, 35/P, 36/P, 37/P & 49. Its filed tentative layout approval provides for 351 plots, with land also allocated to roads, parks/open space, utilities and social infrastructure. RERA record Layout record

The approval describes a road network and open-space and infrastructure works to be completed by the developer. It also identifies plots reserved as mortgage security in favour of the Grampanchayat until the layout-development conditions are fulfilled and the final layout is obtained. The approval is therefore evidence of a tentative layout permission, not evidence in this pack that all development works are complete or that final-layout approval has issued.

The RERA-filed amenity progress figures indicate reported, partial progress on internal roads and footpaths, parks/green areas, street lighting and rainwater harvesting. They also record 0% for several listed services and facilities. These percentages are filing data; the supplied evidence does not independently verify current site conditions. No occupancy certificate is supplied for this plotted project. RERA amenities

Master plan, architecture & building design

This is a plotted layout, not a multi-tower residential building. The supplied tentative approval and drawing provide for 351 plots. The software-read plot schedule includes 351 plots with sizes; the drawing’s land-use statement allocates the site as follows. The drawing-derived measurements should be checked against the approved drawing for plot-specific decisions. Layout record

Layout useArea in drawingShare printed on drawing
Plotted area42583.44 sq m56.95%
Roads22738.76 sq m30.41%
Parks / open space6777.38 sq m9.06%
Utilities750.58 sq m1.00%
Social infrastructure1918.56 sq m2.57%
Amenities0.00 sq m0.00%

The RERA form separately lists an approved built-up area of 42583.79 sq m; it does not define this as carpet area, saleable area or a building floor area. No building footprint, floor configuration, tower height, floor-by-floor arrangement or building count is established in the supplied evidence. RERA filing

The tentative approval identifies 58 plots as mortgaged to the Grampanchayat, totalling 7768.678 sq yd (also stated in the approval as Ac 1.605 cents). The approval says the mortgaged area is to be released after final-layout approval; it also requires the applicant to hand over specified open-space, social-infrastructure, utility and road areas by registered gift deed before release of the final layout.

Homes, configurations & floor plans

This is a plotted offering; no apartment configurations or RERA-filed apartment saleable areas are supplied. The approved drawing’s plot schedule contains 351 plots. The size statistics below are software-measured from the drawing, not a substitute for checking the approved plot schedule for a specific plot. Layout record

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Plots351Not disclosedNot disclosedNot disclosed per plot in supplied RERA dataNot applicableNot supplied
Drawing-based plot-size measureSupplied measurement
Smallest66.1 sq m (79.1 sq yd)
Median122.63 sq m (146.7 sq yd)
Largest235.64 sq m (281.8 sq yd)

The plot-size distribution read from the layout drawing is: 9 plots at 0–100 sq yd; 324 at 100–150 sq yd; 8 at 150–200 sq yd; 4 at 200–250 sq yd; and 6 at 250–300 sq yd. The most common printed plot sizes are 122.63 sq m (237 plots) and 117.80 sq m (42 plots). These are drawing-derived counts and measurements. Layout record

Parking & vehicle circulation

The supplied evidence does not state a sanctioned parking count, visitor or accessible parking provision, parking arrangement for individual plots, or any parking-allotment terms. The layout drawing identifies roads and plot access, but the record supplied here does not establish driveway dimensions, separate pedestrian routes, vehicle entry/exit arrangements or EV charging. Layout record

The approval lists 58 mortgaged plots as security for completion of layout works; these are not identified as parking spaces.

Amenities, recreation & open spaces

The tentative approval identifies open space, social infrastructure and utilities in the layout and describes infrastructure works to be undertaken. The table distinguishes those approval provisions from RERA-filed progress figures; no independent completion verification is supplied. RERA amenities

Landscape / open space
FacilityPark / organized open space
Description / sizeDrawing-derived 6777.38 sq m; approval states Ac 1.675 cents / 8105.746 sq yd
Evidence sourceLayout record
Declared progress / verified statusRERA filing reports green strip/tot lot/park at 45%; not independently verified. RERA amenities
Sports / recreation
FacilityRecreational open space
Description / sizeAggregate area listed as available; no progress percentage stated in the supplied record
Evidence sourceRERA amenities
Declared progress / verified statusRERA filing shows 0%; not independently verified.
Convenience / community
FacilitySocial infrastructure
Description / sizeDrawing-derived 1918.56 sq m; approval describes this allocation as including pharmacy, clinic, school, play school, crèche, dispensary and convenient shops
Evidence sourceLayout record
Declared progress / verified statusApproval allocation; no supplied evidence of construction or delivery. RERA filing lists community buildings at 0%. RERA amenities
Convenience / community
FacilityUtilities area
Description / sizeDrawing-derived 750.58 sq m; the approval lists water reservoir, septic tank, sewerage treatment plant, electric transformer and solid-waste management among utility provisions
Evidence sourceLayout record
Declared progress / verified statusApproval provision; no supplied evidence of completion. Relevant RERA progress entries are listed separately below.
Landscape / open space
FacilityRoads and access
Description / sizeDrawing-derived roads area 22738.76 sq m
Evidence sourceLayout record
Declared progress / verified statusRERA filing reports internal roads and footpaths at 65%; not independently verified. RERA amenities
Landscape / open space
FacilityStreet lighting
Description / sizeNo quantity or size stated
Evidence sourceRERA amenities
Declared progress / verified statusRERA filing reports 30%; not independently verified.
Landscape / open space
FacilityRainwater harvesting
Description / sizeNo quantity or capacity stated
Evidence sourceRERA amenities
Declared progress / verified statusRERA filing reports 25%; not independently verified.

The approval also calls for avenue planting and rainwater-harvesting pits, fencing of open spaces, street lighting, sewerage disposal and protected water supply as development works. These are approval conditions/provisions, not evidence that the works have been completed.

Utilities, building services & safety

The tentative layout approval describes required works and identifies a utilities allocation; it does not establish that these systems are operational. The RERA-filed progress schedule reports the following status, which has not been independently verified. RERA amenities

Water
Supplied evidenceApproval calls for protected water supply and an overhead tank or sump; the utilities list includes a water reservoir. No source, storage capacity or treatment details are supplied.
Declared progress / limitationWater supply: 0% in the RERA filing. RERA amenities
Sewerage and drainage
Supplied evidenceApproval calls for sewerage disposal, septic tank and sewerage treatment plant; it also requires drains and nala channelization for storm-water runoff. No capacity, design or reuse details are supplied.
Declared progress / limitationSewerage (chambers, lines, septic tank, STP), storm-water drains, and treatment/disposal of sewage and sullage each show 0% in the RERA filing. RERA amenities
Electrical
Supplied evidenceApproval lists an electric transformer and calls for street lighting and electricity facilities. Substation or supply capacity is not disclosed.
Declared progress / limitationElectrical meter room/substation/receiving station: 0%; street lighting: 30% in the RERA filing. RERA amenities
Solid waste
Supplied evidenceSolid-waste management is listed among the approval’s utility provisions; no system or capacity is specified.
Declared progress / limitationSolid-waste management and disposal: 0% in the RERA filing. RERA amenities
Water conservation
Supplied evidenceApproval calls for rainwater-harvesting pits. No number, size or storage capacity is supplied.
Declared progress / limitationWater conservation/rainwater harvesting: 25% in the RERA filing. RERA amenities
Fire and life safety
Supplied evidenceNo project-specific fire-system details or clearance are supplied.
Declared progress / limitationFire protection/fire safety: 0% in the RERA filing. RERA amenities
Energy management
Supplied evidenceNo system details are supplied.
Declared progress / limitationEnergy management: 0% in the RERA filing. RERA amenities
Accessibility and circulation
Supplied evidenceApproval requires roads to be opened for access to neighbouring sites; no accessible-route or pedestrian-separation details are supplied.
Declared progress / limitationInternal roads and footpaths: 65% in the RERA filing; not independently verified. RERA amenities

Location, access & connectivity

The registered location is Macharam Revenue Village, Balanagar Mandal, Mahabubnagar District, PIN 539301, across survey numbers 31/P, 35/P, 36/P, 37/P & 49. The supplied cadastral coordinate is the parcel centroid at 16.968735832814165, 78.13726406727751. RERA record Cadastral map

The only measured connectivity point supplied is the nearest sampled Outer Ring Road interchange, approximately 42.6 km away. No approach-road description, public-transport information or other verified landmark distances are supplied. Location record

Developer & development status

The registered promoter is M/s SRI SIDDI VINAYAKA DEVELOPERS, identified in the RERA record as a partnership. Its GSTIN is 36ABQFM1135M1ZC. The listed authorized signatory is BALRAM REDDY GAVINOLLA; the supplied partner list also names ANITHA GAVINOLLA, SHARATH BABU DACHEPALLY, BALA KRISHNA REDDY G, MANJULA GAVINOLLA, LAKSHMI SHARANYA SINGARAPU, JYOTHI PASULA and SAI SPURTHI P. Corporate record Parties record

The RERA certificate gives the promoter office as Village LB Nagar, Mandal Saroornagar, District Ranga Reddy, PIN 500070; the promoter information also lists VIJAY SALES BUILDING, ABHUDHAYA NAGAR, MACHARAM G P, Balanagar, Mahabubnagar, PIN 539301. The supplied official website is https://www.ssvd.co.in/. Parties record

The promoter’s Form B affidavit declares a project completion undertaking of 18.04.2025. RERA-filed progress entries give partial percentages for selected infrastructure items, but no independent site verification or occupancy/completion certificate is included in this evidence. RERA amenities

Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for PLATINUM CITY, registration P01400006299, issued 07/07/2023, validity through 18/04/2025.
Tentative layout approvalMUDA Urban Development Authority, approval 255005/LP/GP/280120/0001/2023, dated 18-04-2023; for the 351-plot tentative layout in the stated Macharam survey numbers.
Layout drawingApproved-layout drawing record, document 333223, two sheets; plot schedule and area statement are software-read from the drawing. Layout record
Promoter declarationForm B affidavit by G. Balram Reddy on behalf of the promoter, dated 12 June 2023 as extracted; includes a declared completion deadline of 18.04.2025.
Completion / occupancy evidenceNo completion or occupancy certificate supplied. The tentative layout approval calls for a work-completion certificate and final-layout approval.
Other project recordsRERA-filed encumbrance statement document 335776; title report 333222; registered title-document extracts 332099–332103, 332109–332110. Document index

The approval record is explicitly for a tentative layout plan. The evidence supplied for this overview does not include a final layout approval or completion/occupancy certificate.

Frequently asked questions

Is PLATINUM CITY registered with Telangana RERA?

Yes. PLATINUM CITY is registered with the Telangana Real Estate Regulatory Authority as P01400006299; the registration status is New Project.

Who is the developer of PLATINUM CITY?

The promoter named in the RERA registration is M/s SRI SIDDI VINAYAKA DEVELOPERS.

Where is PLATINUM CITY located?

PLATINUM CITY is in 31/P, 35/P, 36/P, 37/P & 49, Macharam, Balanagar, Mahabubnagar, Telangana (539301).

When will PLATINUM CITY be completed?

The promoter's proposed date of completion filed with RERA is 18/04/2025. This is the promoter's declaration, not a guarantee.

More projects in Macharam