Mallikarjuna infra developers phase-2
Medabolna · Yadadri Bhuvanagiri · RERA P02000009150
Mallikarjuna infra developers phase-2 is a plotted development in Yadagiripally village, Yadagirigutta Mandal, Yadadri Bhuvanagiri District, developed by registered promoter Medabolna. The site extent is 10305.01 sq.mt., and the approval states 24 plots; plot-by-plot sizes are not supplied. The TG-RERA registration is P02000009150, and the stated completion date is 20/03/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | Mallikarjuna infra developers phase-2 RERA record |
| Project type | Plotted development; the RERA filing describes a “New Project” RERA record RERA filing |
| Phase / registered portion | Phase-2; the certificate registers this project under that name |
| TG-RERA registration | P02000009150; granted under section 5, valid from 22/03/2022 to 20/03/2025. The certificate says it may be extended by the Authority; the supplied record does not show an extension |
| Registered promoter | Medabolna; the registration certificate names “Mr./Ms. Medabolna Katama Raju” RERA record |
| RERA status | The registration certificate records its stated validity through 20/03/2025. Current registration status is not established by the supplied evidence |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Yadagiripally village; also described in the approval as Yadagiripally Revenue Village |
| Mandal | Yadagirigutta RERA record |
| District | Yadadri Bhuvanagiri RERA record. The approval document uses “Yadadri-Bhuvanagiri District” |
| PIN | 508115 RERA record |
| Survey number(s) | Sy. No. 26; the registration certificate also lists survey no. 26 RERA filing |
| Registered site extent | 10305.01 sq.mt. RERA filing |
| Area affected / net area | Road widening/affected area: 786.34 sq.mt.; net area: 9518.67 sq.mt. RERA filing |
| Boundaries | East, west, north and south: “others land” RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | YADAGIRIGUTTA Municipality/Municipal Corporation |
| Principal approval | Tentative layout approval No. 0002/LO/3104/2022, dated 22 March 2022 Approvals record |
| Other approval reference | G1/195/2020; the layout-plan record also lists inward No. TS/059975/2021 Approvals record |
| Layout area / approved built-up area | Layout plan states 10305.01 sq.mt. site area. RERA filing gives approved built-up area of 9518.69 sq.mt.; this is a plotted layout, and no building-level floor configuration is supplied RERA filing |
| Plots | Approval document states 24 plots |
| Building, floors and parking levels | Not disclosed in the supplied project evidence; the approval is for a plotted layout, not a multi-storey building scheme |
| Authority mortgage area | RERA filing gives 1354.36 sq.mt.; the approval identifies the municipal mortgage plots as Nos. 21–28 RERA filing |
Offering and status
| Field | Project record |
|---|---|
| Unit type | Plots; no plot-by-plot sizes or saleable-size range are established in the supplied records Layout record |
| Booked / available | Not disclosed in the supplied evidence RERA filing |
| Construction / development stage | No independently verified site-progress information is supplied. The tentative-layout approval requires the applicant to carry out infrastructure and amenity works |
| Completion deadline | RERA certificate and Form B state 20/03/2025 as the stated completion date |
| Occupancy / completion certificate | Not supplied. No building- or phase-specific occupancy/completion certificate status is established Document index |
2. The project story
This is a registered plotted-development project in Yadagiripally village, Yadagirigutta Mandal, Yadadri Bhuvanagiri District. The municipal approval describes a tentative residential layout in Sy. No. 26, with 24 plots and reserved land for roads, open space, social infrastructure and utilities. It also states that only detached dwelling houses designed for single-family occupation are to be built on the sites.
The layout approval assigns 67.64% of its stated land-use schedule to plotted area, 18.69% to roads and 9.12% to open space/park. Separate portions are identified for social infrastructure and utilities. The approval places responsibility for the layout’s infrastructure and amenity works on the applicant and calls for roads to remain open for access to neighbouring sites. These are approval-document provisions, not evidence that the works have been completed.
The registration certificate records a completion date of 20/03/2025. The supplied evidence does not establish actual completion, current on-site progress, plot-by-plot availability or an occupancy/completion certificate. Document index
3. Master plan, architecture & building design
The project is a land layout rather than a tower or apartment scheme. The tentative approval covers land in Sy. No. 26 at Yadagiripally Revenue Village and states an extent of 2 Acer 21.86 Gts (12325 Sq. Yds) and 24 plots. The RERA filing identifies the site as 10305.01 sq.mt., with 786.34 sq.mt. affected by road widening and a net area of 9518.67 sq.mt. RERA filing
The drawing-derived land-use schedule is:
| Use | Area | Share shown in the approval |
|---|---|---|
| Plotted area | 6438.88 sq.mt. | 67.64% |
| Road area | 1779.36 sq.mt. | 18.69% |
| Organized open space/park | 867.87 sq.mt. | 9.12% |
| Social infrastructure | 339.14 sq.mt. | 3.56% |
| Utility area | 97.53 sq.mt. | 1.02% |
| Amenity area | 0.00 sq.mt. | 0.00% |
The layout record lists a 9.14 M internal road, a proposed 30'-0" wide road and a 50.0 M wide road. The supplied evidence does not establish the precise road alignment or frontage for an individual plot.
The approval identifies municipal mortgage plots Nos. 21, 22, 23, 24, 25, 26, 27 and 28, totalling 0 Acer 13.39 Gts (1620 Sq. Yds), recorded as 21.02% of the plotted area. The RERA filing separately reports a mortgage area of 1354.36 sq.mt. The approval states that development in the mortgaged area is not to be permitted until development works are completed, the mortgaged land is released and the final layout is released. RERA filing
No building footprints, floor configuration, tower heights, plot-by-plot dimensions or building plans are established in the supplied evidence. The RERA filing’s 9518.69 sq.mt. “Approved Built up Area” is reported as filed and is not a measurement of an individual plot or dwelling. RERA filing
4. Homes, configurations & floor plans
The project offers plots, not apartments. The approval document states 24 plots, but the supplied evidence does not provide a complete plot schedule, plot-size bands, plot-wise saleable areas or booked/available counts. Layout record
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 24 (approval document) | Not disclosed | Not disclosed | Not established plot by plot | Not applicable / not supplied | Not supplied |
The layout sheets are not apartment floor plans; no software-measured home or room areas are supplied. The approval states that only detached, single-family dwelling houses may be built on a site. Floor plans
5. Parking & vehicle circulation
The layout land-use schedule lists 0.00 sq.mt. for common parking area. No parking-space count, visitor or accessible parking provision, plot-specific parking allocation, EV provision, parking levels or vehicle-entry arrangement is established in the supplied records. RERA amenities
The approval identifies internal roads and requires roads to remain open for access to neighbouring sites. This does not establish the parking rights or parking facilities of an individual plot.
6. Amenities, recreation & open spaces
The approval and RERA-filed amenity fields identify the following provisions. The supplied evidence does not certify that any item is complete or independently inspected.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Organized open space / park | 867.87 sq.mt.; 9.12% of the layout schedule | Shown in the approval; completion not established | |
| Social infrastructure | 339.14 sq.mt.; 3.56% | Reserved area shown; facility or completion not established | |
| Tot-lot | Named in the layout-plan extraction; no separate size supplied | Shown as a layout feature; completion not established | |
| Internal roads and footpaths | Road area 1779.36 sq.mt.; approval lists internal roads | Required/provided for in layout records; completion not established | |
| Street lighting | Listed in RERA amenity fields and approval extraction | RERA amenities | Listed; completion not established |
| Avenue plantation / green strip | Avenue plantation listed in the approval extraction; no area or quantity supplied | Listed; completion not established |
The approval also requires open space, utilities and roads to be handed over to the Municipality by registered gift deed before release of the tentative layout. The supplied evidence does not establish that this handover or final-layout release has occurred.
7. Utilities, building services & safety
The tentative-layout approval lists the following proposed infrastructure: water reservoir, overhead tank/sump, internal water-supply pipelines, septic tank, sewerage treatment plant, underground drainage lines, storm-water drains, rainwater-harvesting pits, electric transformer, street lights and solid-waste management. The project’s RERA amenity fields also list water supply, sewerage, storm-water drainage, sewage/sullage treatment and disposal, solid-waste management, rainwater harvesting, energy management, fire protection and an electrical meter room/sub-station/receiving station. RERA amenities
These records identify listed or proposed services; they do not establish installed capacities, operating status, completion, statutory clearances or independent verification. No lift, backup-power, CCTV, security, accessibility or fire-system specifications are supplied. Document index RERA amenities
8. Location, access & connectivity
The registered project location is Yadagiripally village, Yadagirigutta Mandal, Yadadri Bhuvanagiri District, Telangana, PIN 508115. The approval identifies the land as being in Sy. No. 26 and names Yadagiripally Revenue Village. RERA record
The layout records internal roads and a requirement that roads remain open to provide access to neighbouring sites. The supplied location evidence does not provide verified public-transport details or measured distances to local landmarks. Location record
9. Developer & development status
The registered project promoter is identified as Medabolna; the TG-RERA certificate names “Mr./Ms. Medabolna Katama Raju.” The legal entity type, corporate registration identifiers, official contacts and website are not established in the supplied evidence. RERA record Corporate record
The registration certificate records the project’s stated completion date as 20/03/2025. A Form B affidavit dated 15 May 2024 also states that date, but its completion undertaking contains the name “SIRI, HAPPY HOMES”; the supplied evidence does not clarify that reference.
No independent construction-progress report, current plot inventory, completion certificate or occupancy certificate is supplied. The tentative-layout approval places responsibility for infrastructure and amenity works on the applicant. Document index
10. Approvals, official records & documents
| What the supplied document establishes | Project name Mallikarjuna infra developers phase-2; registration P02000009150; stated validity 22/03/2022–20/03/2025; survey no. 26; PIN 508115 |
|---|
| What the supplied document establishes | Approval No. 0002/LO/3104/2022, dated 22 March 2022, issued by YADAGIRIGUTTA Municipality/Municipal Corporation; 24 plots and listed land-use reservations |
|---|
| What the supplied document establishes | Sy. No. 26; layout-plan area and land-use schedule; reference G1/195/2020 and inward No. TS/059975/2021 |
|---|
| What the supplied document establishes | Promoter disclosures and undertakings, including separate-account and completion-date declarations; verified at Hyderabad on 15 May 2024 |
|---|
| What the supplied document establishes | Not supplied in the reviewed project documents |
|---|---|
| Reference | Document index |
| What the supplied document establishes | No building-level certificate or building plan is established; the supplied approval document is for a tentative plotted layout |
|---|
The tentative approval requires infrastructure and amenity works and specifies that open space, utilities and roads are to be handed over to the Municipality by registered gift deed before release of the tentative layout. The supplied records do not establish final-layout release or completion of those works.
1. Project at a glance
Project identity
Registered project name: Mallikarjuna infra developers phase-2
Project type: Plotted development; the RERA filing describes a “New Project”
Phase / registered portion: Phase-2; the certificate registers this project under that name
TG-RERA registration: P02000009150; granted under section 5, valid from 22/03/2022 to 20/03/2025. The certificate says it may be extended by the Authority; the supplied record does not show an extension
Registered promoter: Medabolna; the registration certificate names “Mr./Ms. Medabolna Katama Raju”
RERA status: The registration certificate records its stated validity through 20/03/2025. Current registration status is not established by the supplied evidence
Land and geographic identity
Locality / revenue village: Yadagiripally village; also described in the approval as Yadagiripally Revenue Village
Mandal: Yadagirigutta
District: Yadadri Bhuvanagiri. The approval document uses “Yadadri-Bhuvanagiri District”
PIN: 508115
Survey number(s): Sy. No. 26; the registration certificate also lists survey no. 26
Registered site extent: 10305.01 sq.mt.
Area affected / net area: Road widening/affected area: 786.34 sq.mt.; net area: 9518.67 sq.mt.
Boundaries: East, west, north and south: “others land”
Development identity
Sanctioning authority: YADAGIRIGUTTA Municipality/Municipal Corporation
Principal approval: Tentative layout approval No. 0002/LO/3104/2022, dated 22 March 2022
Other approval reference: G1/195/2020; the layout-plan record also lists inward No. TS/059975/2021
Layout area / approved built-up area: Layout plan states 10305.01 sq.mt. site area. RERA filing gives approved built-up area of 9518.69 sq.mt.; this is a plotted layout, and no building-level floor configuration is supplied
Plots: Approval document states 24 plots
Building, floors and parking levels: Not disclosed in the supplied project evidence; the approval is for a plotted layout, not a multi-storey building scheme
Authority mortgage area: RERA filing gives 1354.36 sq.mt.; the approval identifies the municipal mortgage plots as Nos. 21–28
Offering and status
Unit type: Plots; no plot-by-plot sizes or saleable-size range are established in the supplied records
Booked / available: Not disclosed in the supplied evidence
Construction / development stage: No independently verified site-progress information is supplied. The tentative-layout approval requires the applicant to carry out infrastructure and amenity works
Completion deadline: RERA certificate and Form B state 20/03/2025 as the stated completion date
Occupancy / completion certificate: Not supplied. No building- or phase-specific occupancy/completion certificate status is established
2. The project story
This is a registered plotted-development project in Yadagiripally village, Yadagirigutta Mandal, Yadadri Bhuvanagiri District. The municipal approval describes a tentative residential layout in Sy. No. 26, with 24 plots and reserved land for roads, open space, social infrastructure and utilities. It also states that only detached dwelling houses designed for single-family occupation are to be built on the sites.
The layout approval assigns 67.64% of its stated land-use schedule to plotted area, 18.69% to roads and 9.12% to open space/park. Separate portions are identified for social infrastructure and utilities. The approval places responsibility for the layout’s infrastructure and amenity works on the applicant and calls for roads to remain open for access to neighbouring sites. These are approval-document provisions, not evidence that the works have been completed.
The registration certificate records a completion date of 20/03/2025. The supplied evidence does not establish actual completion, current on-site progress, plot-by-plot availability or an occupancy/completion certificate.
3. Master plan, architecture & building design
The project is a land layout rather than a tower or apartment scheme. The tentative approval covers land in Sy. No. 26 at Yadagiripally Revenue Village and states an extent of 2 Acer 21.86 Gts (12325 Sq. Yds) and 24 plots. The RERA filing identifies the site as 10305.01 sq.mt., with 786.34 sq.mt. affected by road widening and a net area of 9518.67 sq.mt.
The drawing-derived land-use schedule is:
| Use | Area | Share shown in the approval |
|---|---|---|
| Plotted area | 6438.88 sq.mt. | 67.64% |
| Road area | 1779.36 sq.mt. | 18.69% |
| Organized open space/park | 867.87 sq.mt. | 9.12% |
| Social infrastructure | 339.14 sq.mt. | 3.56% |
| Utility area | 97.53 sq.mt. | 1.02% |
| Amenity area | 0.00 sq.mt. | 0.00% |
The layout record lists a 9.14 M internal road, a proposed 30'-0" wide road and a 50.0 M wide road. The supplied evidence does not establish the precise road alignment or frontage for an individual plot.
The approval identifies municipal mortgage plots Nos. 21, 22, 23, 24, 25, 26, 27 and 28, totalling 0 Acer 13.39 Gts (1620 Sq. Yds), recorded as 21.02% of the plotted area. The RERA filing separately reports a mortgage area of 1354.36 sq.mt. The approval states that development in the mortgaged area is not to be permitted until development works are completed, the mortgaged land is released and the final layout is released.
No building footprints, floor configuration, tower heights, plot-by-plot dimensions or building plans are established in the supplied evidence. The RERA filing’s 9518.69 sq.mt. “Approved Built up Area” is reported as filed and is not a measurement of an individual plot or dwelling.
4. Homes, configurations & floor plans
The project offers plots, not apartments. The approval document states 24 plots, but the supplied evidence does not provide a complete plot schedule, plot-size bands, plot-wise saleable areas or booked/available counts.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 24 (approval document) | Not disclosed | Not disclosed | Not established plot by plot | Not applicable / not supplied | Not supplied |
The layout sheets are not apartment floor plans; no software-measured home or room areas are supplied. The approval states that only detached, single-family dwelling houses may be built on a site.
5. Parking & vehicle circulation
The layout land-use schedule lists 0.00 sq.mt. for common parking area. No parking-space count, visitor or accessible parking provision, plot-specific parking allocation, EV provision, parking levels or vehicle-entry arrangement is established in the supplied records.
The approval identifies internal roads and requires roads to remain open for access to neighbouring sites. This does not establish the parking rights or parking facilities of an individual plot.
6. Amenities, recreation & open spaces
The approval and RERA-filed amenity fields identify the following provisions. The supplied evidence does not certify that any item is complete or independently inspected.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Organized open space / park | 867.87 sq.mt.; 9.12% of the layout schedule | Shown in the approval; completion not established | |
| Social infrastructure | 339.14 sq.mt.; 3.56% | Reserved area shown; facility or completion not established | |
| Tot-lot | Named in the layout-plan extraction; no separate size supplied | Shown as a layout feature; completion not established | |
| Internal roads and footpaths | Road area 1779.36 sq.mt.; approval lists internal roads | Required/provided for in layout records; completion not established | |
| Street lighting | Listed in RERA amenity fields and approval extraction | Listed; completion not established | |
| Avenue plantation / green strip | Avenue plantation listed in the approval extraction; no area or quantity supplied | Listed; completion not established |
The approval also requires open space, utilities and roads to be handed over to the Municipality by registered gift deed before release of the tentative layout. The supplied evidence does not establish that this handover or final-layout release has occurred.
7. Utilities, building services & safety
The tentative-layout approval lists the following proposed infrastructure: water reservoir, overhead tank/sump, internal water-supply pipelines, septic tank, sewerage treatment plant, underground drainage lines, storm-water drains, rainwater-harvesting pits, electric transformer, street lights and solid-waste management. The project’s RERA amenity fields also list water supply, sewerage, storm-water drainage, sewage/sullage treatment and disposal, solid-waste management, rainwater harvesting, energy management, fire protection and an electrical meter room/sub-station/receiving station.
These records identify listed or proposed services; they do not establish installed capacities, operating status, completion, statutory clearances or independent verification. No lift, backup-power, CCTV, security, accessibility or fire-system specifications are supplied.
8. Location, access & connectivity
The registered project location is Yadagiripally village, Yadagirigutta Mandal, Yadadri Bhuvanagiri District, Telangana, PIN 508115. The approval identifies the land as being in Sy. No. 26 and names Yadagiripally Revenue Village.
The layout records internal roads and a requirement that roads remain open to provide access to neighbouring sites. The supplied location evidence does not provide verified public-transport details or measured distances to local landmarks.
9. Developer & development status
The registered project promoter is identified as Medabolna; the TG-RERA certificate names “Mr./Ms. Medabolna Katama Raju.” The legal entity type, corporate registration identifiers, official contacts and website are not established in the supplied evidence.
The registration certificate records the project’s stated completion date as 20/03/2025. A Form B affidavit dated 15 May 2024 also states that date, but its completion undertaking contains the name “SIRI, HAPPY HOMES”; the supplied evidence does not clarify that reference.
No independent construction-progress report, current plot inventory, completion certificate or occupancy certificate is supplied. The tentative-layout approval places responsibility for infrastructure and amenity works on the applicant.
10. Approvals, official records & documents
| What the supplied document establishes | Project name Mallikarjuna infra developers phase-2; registration P02000009150; stated validity 22/03/2022–20/03/2025; survey no. 26; PIN 508115 |
|---|
| What the supplied document establishes | Approval No. 0002/LO/3104/2022, dated 22 March 2022, issued by YADAGIRIGUTTA Municipality/Municipal Corporation; 24 plots and listed land-use reservations |
|---|
| What the supplied document establishes | Sy. No. 26; layout-plan area and land-use schedule; reference G1/195/2020 and inward No. TS/059975/2021 |
|---|
| What the supplied document establishes | Promoter disclosures and undertakings, including separate-account and completion-date declarations; verified at Hyderabad on 15 May 2024 |
|---|
| What the supplied document establishes | Not supplied in the reviewed project documents |
|---|
| What the supplied document establishes | No building-level certificate or building plan is established; the supplied approval document is for a tentative plotted layout |
|---|
The tentative approval requires infrastructure and amenity works and specifies that open space, utilities and roads are to be handed over to the Municipality by registered gift deed before release of the tentative layout. The supplied records do not establish final-layout release or completion of those works.
Frequently asked questions
Is Mallikarjuna infra developers phase-2 registered with Telangana RERA?
Yes. Mallikarjuna infra developers phase-2 is registered with the Telangana Real Estate Regulatory Authority as P02000009150; the registration status is New Project.
Who is the developer of Mallikarjuna infra developers phase-2?
The promoter named in the RERA registration is Medabolna.
Where is Mallikarjuna infra developers phase-2 located?
Mallikarjuna infra developers phase-2 is in yadagirigutta, Yadadri Bhuvanagiri, Telangana (508115).
When will Mallikarjuna infra developers phase-2 be completed?
The promoter's proposed date of completion filed with RERA is 20/03/2025. This is the promoter's declaration, not a guarantee.
More projects in Yadagirigutta