Global Village
M/s. VEDANT SPA & RESORTS PRIVATE LIMITED AND M/s. INFINITY SECURITY PAPERS LIMITED · Rangareddy · RERA P02400008378
GLOBAL VILLAGE is a plotted development in Karkalpahad, Kadthal Mandal, Ranga Reddy District, developed by M/s. VEDANT SPA & RESORTS PRIVATE LIMITED AND M/s. INFINITY SECURITY PAPERS LIMITED. The RERA-filed land extent is 29,339.70 sq. metres, and the draft layout records 88 plots; building or tower count and floors are not disclosed. TG-RERA registration number P02400008378 was registered from 22 June 2024 to 5 April 2025, and the Form B declaration states a completion date of 5th April 2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | GLOBAL VILLAGE RERA record |
| Project type | Plotted development; the RERA filing identifies it as a plotted development. RERA record RERA filing |
| Phase / registered portion | Phase is not disclosed. The registered land is identified as Survey Nos. 52/P, 102/P & 103/P. RERA record RERA filing |
| TG-RERA registration | P02400008378. RERA record Approvals record |
| Registration validity | 22 June 2024 to 5 April 2025, unless extended by the Authority. No extension record is supplied here. Registration validity is distinct from the promoter’s completion commitment. Approvals record |
| Registered promoters | M/s. VEDANT SPA & RESORTS PRIVATE LIMITED AND M/s. INFINITY SECURITY PAPERS LIMITED. RERA record Corporate record |
| RERA status in supplied record | RERA classifies the project as New Project. Registration is shown as valid from 22 June 2024 to 5 April 2025; current registration status is not established by the supplied record. RERA record Approvals record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Karkalpahad; the layout documents also identify Govindaipally Thanda. RERA record RERA filing |
| Revenue village | Karkalpahad (also printed as “Karakalpahad” or “Karkalpahad Revenue Village” in filed documents). RERA record |
| Mandal / district / PIN | Kadthal / Ranga Reddy / 509358. RERA record RERA filing |
| Project survey numbers | 52/P, 102/P & 103/P. No further project subdivision is specified in the RERA identity record. RERA record RERA filing |
| RERA-filed land extent | 29,339.70 sq. metres total and net area; affected area is recorded as 0. RERA filing |
| Layout-plan extent | The filed draft-layout documents state Ac. 7.25 Cents; one approval extraction also records 35090.00 Sq. Yds. |
| Boundaries in RERA land details | East: Road; West, North and South: Owners Land. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Principal layout authority / approval | Director of Town and Country Planning draft technical layout pattern, T.L.P.No. 128/2021/H, dated 03-05-2021; the record refers to delegation to Govindaipally Thanda Gram Panchayat. Approvals record |
| RERA-filed approval date | 05/04/2023 is recorded as the approved date in the RERA project information. RERA filing |
| Approved built-up area | 16,102.44 sq. metres, as recorded in the RERA land/build-up details. RERA filing |
| Buildings / floors | Building or tower count and floor configuration are not disclosed. This is a plotted layout, not an apartment-building configuration in the supplied project record. RERA record RERA filing |
| Layout plot count | The draft layout approval records 88 plots. |
| Mortgage area | 2,492.86 sq. metres is recorded in RERA built-up area details; the layout approval separately identifies Plot Nos. 2 to 11, stated as Ac.0.616 cents or 2981.44 Sq. Yards, for mortgage to Govindaipally Thanda Gram Panchayat. RERA filing |
Offering and status
| Field | Project record |
|---|---|
| Unit type | Plots; plot-size range is not disclosed in the supplied RERA unit data. RERA record RERA filing |
| Booked / available counts | Not available in the supplied unit inventory. A promoter reply reproduced in a filed document reports 16 plots sold as of 24/05/2023; this is a dated promoter statement, not a current inventory. |
| Construction / development stage | No current, independently verified site-progress record is supplied. The layout approval sets out development works, but does not establish their completion. RERA amenities |
| Completion commitment | The Form B declaration states a completion date of 5th April 2025. |
| Occupancy / completion certificate | No occupancy certificate or completion certificate is identified in the supplied documents. For a plotted layout, the supplied record does not establish a building-specific OC scope. Document index Approvals record |
2. The project story
- GLOBAL VILLAGE is registered with TG-RERA as a plotted development on land identified as Survey Nos. 52/P, 102/P & 103/P in Karkalpahad Revenue Village, Kadthal Mandal, Ranga Reddy District. The layout documents place it at Govindaipally Thanda and describe a residential plotted layout. RERA record RERA filing
- The draft technical layout pattern records 88 plots across a stated layout extent of Ac. 7.25 Cents. Its area statement allocates land to plotted area, roads and open space, and identifies Plot Nos. 2 to 11 as the area to be mortgaged to the Gram Panchayat. The approval documents specify that the developer is responsible for layout development works, including roads, drains, greenery, street lighting, electricity facilities, sewerage disposal and protected water supply. These are approval requirements, not evidence that the works have been completed.
- The promoter’s Form B declaration commits to completion by 5th April 2025. The supplied evidence does not establish current construction or infrastructure progress, current plot availability, final layout release, or a completion certificate. The draft approval’s stated period for execution and its conditions are matters for the approvals and risk review; this Overview does not treat them as proof of completion.
3. Master plan, architecture & building design
The project is a residential plotted layout. Its draft-layout area allocation is shown below; these figures are the layout document’s recorded allocations, not software-measured areas.
| Layout component | Filed draft-layout figure |
|---|---|
| Total layout area | Ac. 7.25 Cents; 35090.00 Sq. Yds. |
| Plotted area | Ac. 3.979 Cents; 19258.36 Sq. Yds.; 54.89 % |
| Road area | Ac. 2.546 Cents; 12322.64 Sq. Yds.; 35.11 % |
| Open space | Ac. 0.725 Cents; 3509.00 Sq. Yds.; 10.00 % |
| Mortgage area | Ac. 0.616 Cents; 2981.44 Sq. Yds.; 15.48 % of the plotted area, identified as Plot Nos. 2 to 11 |
- The layout approval mentions a 33-0° wide road in the extracted record. No reliable plot-by-plot dimensions, individual plot-size bands, building footprints, building heights, floor configuration, or apartment/common-area plans are supplied.
- A separate RERA field records approved built-up area of 16,102.44 sq. metres. The record does not explain the area basis or provide a drawing-based breakdown; it should not be read as plot saleable area or carpet area. RERA filing
4. Homes, configurations & floor plans
This is a plotted project; the supplied RERA record does not provide a plot-size schedule, plot-wise saleable areas, or current booked and available inventory. The draft layout approval records 88 plots. A promoter reply filed with RERA reports 16 plots sold as of 24/05/2023, but current inventory is not established. RERA record
No software-measured carpet areas are available. The supplied drawing review reports three drawings, all with scans pending and none measured; no plot dimensions can therefore be stated from those drawings. Floor plans
5. Parking & vehicle circulation
The supplied project record does not establish a parking-space count, dedicated visitor or accessible parking, parking allocation to individual plots, or a separate parking area. The layout approval identifies road area and refers to roads being opened for access to neighbouring sites; it does not establish parking entitlements. RERA filing
6. Amenities, recreation & open spaces
The layout approval identifies open space and lists layout infrastructure works. The RERA amenities record marks several infrastructure categories “YES,” but records 0 progress for the listed items; it does not establish that any facility is complete. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Open space / park | 10.00 %; Ac. 0.725 Cents; 3509.00 Sq. Yds. in the draft-layout approval | Reserved in draft plan; completion not verified | |
| Internal roads and footpaths | Layout approval allocates 35.11 %; Ac. 2.546 Cents; 12322.64 Sq. Yds. to road area | RERA amenities | Listed in RERA amenities; progress recorded as 0 |
| Greenery / avenue planting | Required as a layout development work; no area or quantity stated | Required work; completion not verified | |
| Community buildings | No specific facility or size disclosed | RERA amenities | No completed facility established |
| Sports, clubhouse, gym or pool | No project-specific RERA evidence of these facilities in the supplied project record | RERA amenities | Not established as sanctioned or delivered |
7. Utilities, building services & safety
The draft layout approval lists development works that include drains and nala channelization, greenery, rainwater-harvesting pits, street lighting and electricity facilities, sewerage disposal, and protected water supply. The RERA amenities record marks water supply, sewerage, storm-water drains, street lighting, treatment/disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, and an electrical meter room/sub-station/receiving station as “YES”; it records 0 progress for those entries. These are filed declarations or approval-related provisions, not independently verified completed services. RERA amenities
| Service | Evidence and scope |
|---|---|
| Water | “Protected water supply” appears among the layout development works; the RERA amenities field records water supply as “YES.” Source, capacity, storage and treatment details are not supplied. RERA amenities |
| Sewerage and drainage | Approval refers to drains, nala channelization and sewerage disposal; RERA records sewerage and storm-water drains as “YES.” STP capacity, reuse arrangements and completion status are not established. RERA amenities |
| Rainwater management | Approval lists rainwater-harvesting pits; RERA records water conservation/rainwater harvesting as “YES.” Quantity and delivery status are not established. RERA amenities |
| Electricity and lighting | Approval lists street lighting and electricity facilities; RERA records these and an electrical meter room/sub-station/receiving station as “YES.” Capacity and completion status are not established. RERA amenities |
| Fire and life safety | No project-specific fire system, clearance, or fire-safety facility is established in the supplied record. RERA amenities |
| Waste and security | RERA records solid-waste management and disposal as “YES”; operating details and completion are not supplied. The project-specific record does not establish security systems. RERA amenities |
| Lifts, accessibility and backup power | No project-specific evidence of lifts, accessible circulation, or backup-power capacity is supplied. RERA amenities |
8. Location, access & connectivity
The RERA land details identify the eastern boundary as a road and the other three boundaries as owners’ land. The draft approval refers to roads being opened for access to neighbouring sites and records a 33-0° wide road. The supplied location data contains a cadastral parcel centroid of 17.41528, 78.35459; it does not provide verified road-route distances, public-transport details or project-specific landmark distances. RERA filing Location record
9. Developer & development status
The registered promoters are M/s. VEDANT SPA & RESORTS PRIVATE LIMITED and M/s. INFINITY SECURITY PAPERS LIMITED, identified in the RERA filing as joint developers. Their entity type is recorded as private limited company, and the supplied corporate identifier is GSTIN 36AABCO1399L1Z1. RERA record RERA filing Corporate record
The registration certificate lists both promoters at Hyderabad, PIN 500034. The supplied project record does not provide a verified official project website or project contact details.
The Form B declaration by Manoj Malpani, authorized by the promoters, states a completion commitment of 5th April 2025 and declares the land free from encumbrances. These are promoter declarations. No current construction-progress certificate, current inventory schedule, or independently verified completion status is supplied.
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for GLOBAL VILLAGE, registration P02400008378, naming both promoters and stating validity from 22/06/2024 to 05/04/2025. |
| Principal layout approval | Director of Town and Country Planning draft technical layout pattern, T.L.P.No. 128/2021/H, dated 03-05-2021, for Survey Nos. 52/P, 102/P & 103/P; the record specifies 88 plots and conditions for development and mortgage of Plot Nos. 2 to 11. |
| Gram Panchayat layout reference | Layout reference E.P.No. 20061 / 1367 / 2021/E.P., with the document stating that the layout is legally valid only upon release or approval by the concerned Gram Panchayat and fulfillment of layout conditions. |
| Mortgage and gift-deed submission | Letter dated 24.03.2023 records submission of Mortgage Deed 4397/2023 and Gift Deed 4396/2023 to the Panchayat Executive Officer; the letter itself is not an approval. |
| Occupancy / completion certificate | No project occupancy or completion certificate is identified in the supplied documents. Document index Approvals record |
| Project declaration | Form B affidavit-cum-declaration dated June 2024, including the promoters’ title and encumbrance declarations, 70% separate-account undertaking, and completion commitment. |
| Encumbrance statements / filed reply | Filed material includes encumbrance statements and a promoter reply dated 24/05/2023 that reports 16 plots sold. These documents are not a current inventory or a completion certificate. |
1. Project at a glance
Project identity
Registered project name: GLOBAL VILLAGE
Project type: Plotted development; the RERA filing identifies it as a plotted development.
Phase / registered portion: Phase is not disclosed. The registered land is identified as Survey Nos. 52/P, 102/P & 103/P.
TG-RERA registration: P02400008378.
Registration validity: 22 June 2024 to 5 April 2025, unless extended by the Authority. No extension record is supplied here. Registration validity is distinct from the promoter’s completion commitment.
Registered promoters: M/s. VEDANT SPA & RESORTS PRIVATE LIMITED AND M/s. INFINITY SECURITY PAPERS LIMITED.
RERA status in supplied record: RERA classifies the project as New Project. Registration is shown as valid from 22 June 2024 to 5 April 2025; current registration status is not established by the supplied record.
Land and geographic identity
Locality: Karkalpahad; the layout documents also identify Govindaipally Thanda.
Revenue village: Karkalpahad (also printed as “Karakalpahad” or “Karkalpahad Revenue Village” in filed documents).
Mandal / district / PIN: Kadthal / Ranga Reddy / 509358.
Project survey numbers: 52/P, 102/P & 103/P. No further project subdivision is specified in the RERA identity record.
RERA-filed land extent: 29,339.70 sq. metres total and net area; affected area is recorded as 0.
Layout-plan extent: The filed draft-layout documents state Ac. 7.25 Cents; one approval extraction also records 35090.00 Sq. Yds.
Boundaries in RERA land details: East: Road; West, North and South: Owners Land.
Development identity
Principal layout authority / approval: Director of Town and Country Planning draft technical layout pattern, T.L.P.No. 128/2021/H, dated 03-05-2021; the record refers to delegation to Govindaipally Thanda Gram Panchayat.
RERA-filed approval date: 05/04/2023 is recorded as the approved date in the RERA project information.
Approved built-up area: 16,102.44 sq. metres, as recorded in the RERA land/build-up details.
Buildings / floors: Building or tower count and floor configuration are not disclosed. This is a plotted layout, not an apartment-building configuration in the supplied project record.
Layout plot count: The draft layout approval records 88 plots.
Mortgage area: 2,492.86 sq. metres is recorded in RERA built-up area details; the layout approval separately identifies Plot Nos. 2 to 11, stated as Ac.0.616 cents or 2981.44 Sq. Yards, for mortgage to Govindaipally Thanda Gram Panchayat.
Offering and status
Unit type: Plots; plot-size range is not disclosed in the supplied RERA unit data.
Booked / available counts: Not available in the supplied unit inventory. A promoter reply reproduced in a filed document reports 16 plots sold as of 24/05/2023; this is a dated promoter statement, not a current inventory.
Construction / development stage: No current, independently verified site-progress record is supplied. The layout approval sets out development works, but does not establish their completion.
Completion commitment: The Form B declaration states a completion date of 5th April 2025.
Occupancy / completion certificate: No occupancy certificate or completion certificate is identified in the supplied documents. For a plotted layout, the supplied record does not establish a building-specific OC scope.
2. The project story
- GLOBAL VILLAGE is registered with TG-RERA as a plotted development on land identified as Survey Nos. 52/P, 102/P & 103/P in Karkalpahad Revenue Village, Kadthal Mandal, Ranga Reddy District. The layout documents place it at Govindaipally Thanda and describe a residential plotted layout.
- The draft technical layout pattern records 88 plots across a stated layout extent of Ac. 7.25 Cents. Its area statement allocates land to plotted area, roads and open space, and identifies Plot Nos. 2 to 11 as the area to be mortgaged to the Gram Panchayat. The approval documents specify that the developer is responsible for layout development works, including roads, drains, greenery, street lighting, electricity facilities, sewerage disposal and protected water supply. These are approval requirements, not evidence that the works have been completed.
- The promoter’s Form B declaration commits to completion by 5th April 2025. The supplied evidence does not establish current construction or infrastructure progress, current plot availability, final layout release, or a completion certificate. The draft approval’s stated period for execution and its conditions are matters for the approvals and risk review; this Overview does not treat them as proof of completion.
3. Master plan, architecture & building design
The project is a residential plotted layout. Its draft-layout area allocation is shown below; these figures are the layout document’s recorded allocations, not software-measured areas.
Total layout area: Ac. 7.25 Cents; 35090.00 Sq. Yds.
Plotted area: Ac. 3.979 Cents; 19258.36 Sq. Yds.; 54.89 %
Road area: Ac. 2.546 Cents; 12322.64 Sq. Yds.; 35.11 %
Open space: Ac. 0.725 Cents; 3509.00 Sq. Yds.; 10.00 %
Mortgage area: Ac. 0.616 Cents; 2981.44 Sq. Yds.; 15.48 % of the plotted area, identified as Plot Nos. 2 to 11
- The layout approval mentions a 33-0° wide road in the extracted record. No reliable plot-by-plot dimensions, individual plot-size bands, building footprints, building heights, floor configuration, or apartment/common-area plans are supplied.
- A separate RERA field records approved built-up area of 16,102.44 sq. metres. The record does not explain the area basis or provide a drawing-based breakdown; it should not be read as plot saleable area or carpet area.
4. Homes, configurations & floor plans
This is a plotted project; the supplied RERA record does not provide a plot-size schedule, plot-wise saleable areas, or current booked and available inventory. The draft layout approval records 88 plots. A promoter reply filed with RERA reports 16 plots sold as of 24/05/2023, but current inventory is not established.
No software-measured carpet areas are available. The supplied drawing review reports three drawings, all with scans pending and none measured; no plot dimensions can therefore be stated from those drawings.
5. Parking & vehicle circulation
The supplied project record does not establish a parking-space count, dedicated visitor or accessible parking, parking allocation to individual plots, or a separate parking area. The layout approval identifies road area and refers to roads being opened for access to neighbouring sites; it does not establish parking entitlements.
6. Amenities, recreation & open spaces
The layout approval identifies open space and lists layout infrastructure works. The RERA amenities record marks several infrastructure categories “YES,” but records 0 progress for the listed items; it does not establish that any facility is complete.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Open space / park | 10.00 %; Ac. 0.725 Cents; 3509.00 Sq. Yds. in the draft-layout approval | Reserved in draft plan; completion not verified | |
| Internal roads and footpaths | Layout approval allocates 35.11 %; Ac. 2.546 Cents; 12322.64 Sq. Yds. to road area | Listed in RERA amenities; progress recorded as 0 | |
| Greenery / avenue planting | Required as a layout development work; no area or quantity stated | Required work; completion not verified | |
| Community buildings | No specific facility or size disclosed | No completed facility established | |
| Sports, clubhouse, gym or pool | No project-specific RERA evidence of these facilities in the supplied project record | Not established as sanctioned or delivered |
7. Utilities, building services & safety
The draft layout approval lists development works that include drains and nala channelization, greenery, rainwater-harvesting pits, street lighting and electricity facilities, sewerage disposal, and protected water supply. The RERA amenities record marks water supply, sewerage, storm-water drains, street lighting, treatment/disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, and an electrical meter room/sub-station/receiving station as “YES”; it records 0 progress for those entries. These are filed declarations or approval-related provisions, not independently verified completed services.
Water: “Protected water supply” appears among the layout development works; the RERA amenities field records water supply as “YES.” Source, capacity, storage and treatment details are not supplied.
Sewerage and drainage: Approval refers to drains, nala channelization and sewerage disposal; RERA records sewerage and storm-water drains as “YES.” STP capacity, reuse arrangements and completion status are not established.
Rainwater management: Approval lists rainwater-harvesting pits; RERA records water conservation/rainwater harvesting as “YES.” Quantity and delivery status are not established.
Electricity and lighting: Approval lists street lighting and electricity facilities; RERA records these and an electrical meter room/sub-station/receiving station as “YES.” Capacity and completion status are not established.
Fire and life safety: No project-specific fire system, clearance, or fire-safety facility is established in the supplied record.
Waste and security: RERA records solid-waste management and disposal as “YES”; operating details and completion are not supplied. The project-specific record does not establish security systems.
Lifts, accessibility and backup power: No project-specific evidence of lifts, accessible circulation, or backup-power capacity is supplied.
8. Location, access & connectivity
The RERA land details identify the eastern boundary as a road and the other three boundaries as owners’ land. The draft approval refers to roads being opened for access to neighbouring sites and records a 33-0° wide road. The supplied location data contains a cadastral parcel centroid of 17.41528, 78.35459; it does not provide verified road-route distances, public-transport details or project-specific landmark distances.
9. Developer & development status
The registered promoters are M/s. VEDANT SPA & RESORTS PRIVATE LIMITED and M/s. INFINITY SECURITY PAPERS LIMITED, identified in the RERA filing as joint developers. Their entity type is recorded as private limited company, and the supplied corporate identifier is GSTIN 36AABCO1399L1Z1.
The registration certificate lists both promoters at Hyderabad, PIN 500034. The supplied project record does not provide a verified official project website or project contact details.
The Form B declaration by Manoj Malpani, authorized by the promoters, states a completion commitment of 5th April 2025 and declares the land free from encumbrances. These are promoter declarations. No current construction-progress certificate, current inventory schedule, or independently verified completion status is supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for GLOBAL VILLAGE, registration P02400008378, naming both promoters and stating validity from 22/06/2024 to 05/04/2025.
Principal layout approval: Director of Town and Country Planning draft technical layout pattern, T.L.P.No. 128/2021/H, dated 03-05-2021, for Survey Nos. 52/P, 102/P & 103/P; the record specifies 88 plots and conditions for development and mortgage of Plot Nos. 2 to 11.
Gram Panchayat layout reference: Layout reference E.P.No. 20061 / 1367 / 2021/E.P., with the document stating that the layout is legally valid only upon release or approval by the concerned Gram Panchayat and fulfillment of layout conditions.
Mortgage and gift-deed submission: Letter dated 24.03.2023 records submission of Mortgage Deed 4397/2023 and Gift Deed 4396/2023 to the Panchayat Executive Officer; the letter itself is not an approval.
Occupancy / completion certificate: No project occupancy or completion certificate is identified in the supplied documents.
Project declaration: Form B affidavit-cum-declaration dated June 2024, including the promoters’ title and encumbrance declarations, 70% separate-account undertaking, and completion commitment.
Encumbrance statements / filed reply: Filed material includes encumbrance statements and a promoter reply dated 24/05/2023 that reports 16 plots sold. These documents are not a current inventory or a completion certificate.
Frequently asked questions
Is GLOBAL VILLAGE registered with Telangana RERA?
Yes. GLOBAL VILLAGE is registered with the Telangana Real Estate Regulatory Authority as P02400008378; the registration status is New Project.
Who is the developer of GLOBAL VILLAGE?
The promoter named in the RERA registration is M/s. VEDANT SPA & RESORTS PRIVATE LIMITED AND M/s. INFINITY SECURITY PAPERS LIMITED.
Where is GLOBAL VILLAGE located?
GLOBAL VILLAGE is in Karkalpahad, Kadthal, Rangareddy, Telangana (509358).
When will GLOBAL VILLAGE be completed?
The promoter's proposed date of completion filed with RERA is 05/04/2025. This is the promoter's declaration, not a guarantee.