Century Condominium Block - B

EDVENSWA EPC PRIVATE LIMITED · Karimnagar · RERA P02700006270

CENTURY CONDOMINIUM BLOCK - B is a residential apartments project in Vavilalapally, Karimnagar urban mandal, Karimnagar district, developed by EDVENSWA EPC PRIVATE LIMITED. The registered site area is 3036.74 sq. m., with one residential building and one tower comprising 1 Cellar + 1 Stilt + 5 upper floors. The RERA-filed offering comprises 55 apartments: 20 2BHK units with saleable area of 118.28 sq. m. and 35 3BHK units with saleable area of 148.29 sq. m. Its TG-RERA registration number is P02700006270, and the proposed completion date is 30/11/2026.

More from Edvenswa Epc Pvt Ltd · 2 projects →

01What we found

Period endedTG-RERA registration ran to 16 May 2026 - check its extension on TG-RERA
13documents on file - each fact links to its page
1court case on this project's land (survey 1324, Vavilalapally)
6items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameCENTURY CONDOMINIUM BLOCK - B RERA record
Project typeResidential apartments RERA record RERA filing
Phase / registered portionBlock B; the certificate identifies this registered project by that name. No further phase description is disclosed.
TG-RERA registrationP02700006270, granted under section 5; issued 07/07/2023.
Registration validityCertificate states 07/07/2023 to 16/05/2026; no extension is shown in the supplied certificate. This is registration validity, not the construction-completion date or an occupancy certificate.
Registered promoterEDVENSWA EPC PRIVATE LIMITED, a company. RERA record Corporate record
RERA statusThe supplied certificate records registration. The project is labelled “New Project” in the RERA project information. RERA filing

Land and geographic identity

ItemProject record
LocalityVavilalapally RERA record Land records
Revenue villageVavilalapally RERA record Land records
Mandal / district / PINKarimnagar urban / Karimnagar / 505001 RERA record RERA filing
Project survey number(s)Sy. No. 1324; no subdivision is stated in the supplied project identity. Land records
Plot / site reference10-4-166/6/1/B RERA filing
Registered site area3036.74 sq. m. RERA filing
Total / net areaTotal area 3036.74 sq. m.; net area 3036.74 sq. m.; road-affected area recorded as 0 sq. m. RERA filing
BoundariesEast: House of Srikanth and Road; West: 30 Feet Wide Road and Land of V Jalapathi Reddy; North: House of M Sunitha and J Nirmala; South: Land of Ummenthala Ramachandra Reddy. RERA filing

Development identity

ItemProject record
Sanctioning authorityKarimnagar Municipal Corporation Approvals record
Principal building approval0096/BP/3011/2023, approved 16 May, 2023; file no. 008423/BP/DTCP/3011/0117/2022. Approvals record
Approved built-up area7,026.35 sq. m. recorded as residential built-up area. Cellar parking: 2,082.95 sq. m.; stilt parking: 1,407.75 sq. m. These are separately recorded components. RERA filing
Building countOne residential building / one block and one tower are recorded. RERA unit table
Sanctioned floors1 Cellar + 1 Stilt + 5 upper floors.
Approved versus RERA-declared unitsRERA project fields record 1 total building unit and 1 proposed building unit; the RERA unit schedule records 55 apartments. The supplied approval extraction does not state a dwelling-unit count. RERA filing RERA unit table
Sanctioned parking levelsCellar and stilt are designated for parking in the approval. No parking-space count is supplied.
Other area stated in approvalTot-lot: 152.94 sq. m.

Offering and status

ItemProject record
RERA-filed configurations2BHK: 20 units; 3BHK: 35 units. RERA unit table
RERA-filed saleable area2BHK: 118.28 sq. m.; 3BHK: 148.29 sq. m. RERA unit table
Booked / availableRERA portal snapshot records 7 booked and 48 available: 2BHK 0 / 20, 3BHK 7 / 28. The snapshot has no supplied as-of date, so these counts are indicative. RERA unit table
Construction stageRERA amenity records show different progress percentages for listed infrastructure items, but no overall construction-completion percentage or independently verified site-progress report is supplied. RERA amenities
Completion dateRERA project information states proposed completion 30/11/2026. The promoter’s Form B declaration states completion by 16thMay2026. RERA filing
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The building approval says an Occupancy Certificate is required before occupation. Document index

2. The project story

CENTURY CONDOMINIUM BLOCK - B is registered as a residential apartment project at Vavilalapally, Karimnagar, on Sy. No. 1324. The RERA record identifies one residential building, with the sanctioned building form described as one cellar, one stilt and five upper floors. The registered offering lists 55 apartments: 20 two-bedroom units and 35 three-bedroom units. RERA record Land records RERA unit table

The supplied record does not establish an overall construction stage or independently verified site progress. RERA’s amenity progress entries are item-specific, not a certified overall completion percentage. The project’s proposed completion date, promoter-declared completion undertaking and registration validity are distinct records; none is evidence that an Occupancy Certificate has been issued. No Occupancy Certificate is included in the supplied documents. RERA amenities RERA filing Document index

3. Master plan, architecture & building design

The building approval records a site and net area of 3036.74 sq. m., residential built-up area of 7,026.35 sq. m., and a building configuration of 1 Cellar + 1 Stilt + 5 upper floors. It separately records 2,082.95 sq. m. of cellar parking and 1,407.75 sq. m. of stilt parking, and identifies a 152.94 sq. m. tot-lot. These are approval-record areas; they should not be read as apartment carpet or saleable areas. RERA filing

The approval extraction does not provide a floor-by-floor apartment schedule, building footprint, flats per floor, lift or stair details, internal circulation drawings, or a quantified residential/common-area breakdown. A layout-plan document is listed in the RERA file but is not extracted in the supplied record. Document index

4. Homes, configurations & floor plans

RERA records 20 2BHK and 35 3BHK apartments. The saleable areas below are RERA-filed. Carpet areas are software-measured from the supplied approved floor-plan drawing geometry, not RERA disclosures; the supplied measurement notes say the geometry needs review and that carpet area is distinct from saleable area, which includes the home’s share of common areas. RERA unit table Floor plans RERA unit details

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK20020118.28 sq. m.67.7–112.9 sq. m.; median 91.3 sq. m.23%
3BHK35728148.29 sq. m.92.1–108.8 sq. m.; median 92.3 sq. m.38%

The measurement exercise covered 9 2BHK and 10 3BHK flat designs from drawing document 333931. A sample 3BHK drawing identifies bedrooms, living/dining, kitchen, toilets, a utility and a 1.00 m-wide balcony; a sample 2BHK drawing identifies bedrooms, living/dining, kitchen and a toilet. These are drawing-derived measurements and room labels, not a guarantee of the dimensions or layout of every unit. RERA unit details Floor plans

Balcony and utility areas are identified separately in the drawing measurements as excluded from carpet area. The supplied record does not provide unit-specific allocations of common-area loading or a complete apartment-by-apartment schedule. RERA unit details Floor plans

5. Parking & vehicle circulation

The sanctioned approval designates the cellar and stilt for vehicle parking and records their areas as 2,082.95 sq. m. and 1,407.75 sq. m., respectively. Its conditions state that those areas are to be used exclusively for parking and not partitioned or converted to another use.

No sanctioned parking-space count, resident or visitor allocation, accessible-parking count, bay dimensions, ramp or driveway arrangement, EV-charging provision, or unit-specific parking allocation is available in the supplied records. A parking bay shown or described in the project record does not, by itself, establish an exclusive legal allocation to a particular apartment.

6. Amenities, recreation & open spaces

The following are the RERA amenity-progress entries supplied for the project. Percentages are recorded progress fields, not independent verification of delivery. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Electrical meter room, sub-station, receiving stationNo size statedRERA amenity record RERA amenities80%; independent completion verification not supplied
Aggregate recreational open spaceNo area stated in this entryRERA amenity record RERA amenities0%; independent verification not supplied
Internal roads and footpathsNo dimensions statedRERA amenity record RERA amenities0%; independent verification not supplied
Water supplyNo source, capacity or storage details statedRERA amenity record RERA amenities100%; independent verification not supplied
Sewerage (chamber, lines, septic tank, STP)No capacity statedRERA amenity record RERA amenities60%; independent verification not supplied
Storm-water drainsNo dimensions statedRERA amenity record RERA amenities60%; independent verification not supplied
Green strip / tot-lot / parkApproval records tot-lot of 152.94 sq. m.RERA amenity record RERA amenities; building approvalRERA entry 0%; independent completion verification not supplied
Street lightingNo details statedRERA amenity record RERA amenities0%; independent verification not supplied
Community buildingsNo facility or size statedRERA amenity record RERA amenities0%; independent verification not supplied
Treatment and disposal of sewage and sullage waterNo system capacity statedRERA amenity record RERA amenities50%; independent verification not supplied
Solid-waste management and disposalNo system details statedRERA amenity record RERA amenities60%; independent verification not supplied
Water conservation / rainwater harvestingNo capacity stated; approval requires a rainwater-harvesting structure (percolation pit) and records 7 rainwater-harvesting pitsRERA amenity record RERA amenities; building approvalRERA entry 60%; independent verification not supplied
Energy managementNo details statedRERA amenity record RERA amenities0%; independent verification not supplied
Fire protection and fire-safety requirementsNo systems or capacity statedRERA amenity record RERA amenities0%; independent verification not supplied

The approval also requires tree plantation and maintenance of the tot-lot as greenery before an Occupancy Certificate is issued. No separate sanctioned or verified clubhouse, indoor recreation facility, sports facility, or community-building specification is provided in the supplied records.

7. Utilities, building services & safety

The RERA amenity record lists water supply at 100%, sewerage and storm-water drains at 60%, sewage/sullage treatment and disposal at 50%, solid-waste management at 60%, rainwater conservation/harvesting at 60%, and electrical meter-room/sub-station/receiving-station infrastructure at 80%. These are declared progress entries; the evidence pack does not identify water sources, storage or treatment capacity, STP capacity, reuse arrangements, electrical supply capacity, backup generation, or completed commissioning. RERA amenities

The building approval requires rainwater harvesting, space for a transformer, and a garbage house within the premises. It also requires services including sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical supervision, and makes structural and fire-safety requirements the responsibility of the owner, builder/developer and technical personnel. These approval conditions do not establish that the systems have been installed or independently certified.

No lift number or capacity, service-lift provision, fire-system specification, escape-stair configuration, emergency access details, CCTV, access control, accessibility features, or fire-clearance certificate is supplied. The building approval states that an Occupancy Certificate is compulsory before occupation and that public utility connections will be provided only on production of that certificate.

8. Location, access & connectivity

The registered project location is Vavilalapally, Karimnagar urban mandal, Karimnagar district, PIN 505001, on Sy. No. 1324. The RERA-filed site boundaries identify a road on the east and a 30 Feet Wide Road on the west. The building approval also refers to an 18M road width in its conditions; no road-access drawing or independent road-width verification is supplied here. RERA record Land records

The supplied location record lists Financial District (Nanakramguda) — 1.2 km as a connectivity anchor. It does not provide supporting route details or travel times. Location record

9. Developer & development status

The registered promoter is EDVENSWA EPC PRIVATE LIMITED, a company; the project record gives GSTIN 36AAFCE0995A1ZU. Corporate record RERA filing

The promoter’s RERA-filed Form B is an affidavit-cum-declaration by authorized signatory Uppuluri Krishna Murthy. It names Ummenthala Srinivas Reddy and Ummenthala Vishnu Reddy as landowners, cites Development Agreement-cum-General Power of Attorney No. 11450/2021, and declares completion by 16thMay2026.

No official contact details or company website for the registered promoter are supplied in the evidence for this section. The RERA amenity progress figures are the available project-specific progress disclosures; no overall construction percentage or independent site verification is supplied. The registration certificate records validity through 16/05/2026 and does not show an extension; the project information separately states proposed completion 30/11/2026. No Occupancy Certificate is provided. RERA amenities RERA filing Document index

10. Approvals, official records & documents

TG-RERA registration certificate
Supplied evidenceP02700006270, Form C, issued 07/07/2023; validity stated through 16/05/2026.
What it establishesRegistration of CENTURY CONDOMINIUM BLOCK - B under section 5; certificate includes the separate-account condition.
Building construction approval
Supplied evidenceKarimnagar Municipal Corporation approval 0096/BP/3011/2023, dated 16 May 2023; file no. 008423/BP/DTCP/3011/0117/2022.
What it establishesApproval extraction describes one cellar, one stilt and five upper floors, the project site and recorded built-up, parking and tot-lot areas, with conditions including an Occupancy Certificate before occupation.
RERA land-title search report
Supplied evidenceAdvocate’s report dated 21-05-2023, document 333930.
What it establishesA project-filed title-search document concerning Sy. No. 1324; the underlying title matters are addressed in the Land & Title section.
Development agreement-cum-GPA
Supplied evidenceDocument 334355; registered as No. 11450/2021.
What it establishesProject-filed development-rights document identified in the supplied extraction.
Form B declaration
Supplied evidenceDocument 334361, dated 13 June 2023.
What it establishesPromoter-filed declarations, including landowner names, separate-account undertakings and the stated completion undertaking.
Layout plan
Supplied evidenceDocument 333931 is listed as a layout-plan document but is not extracted as a layout approval in the supplied record. Document index
What it establishesA complete approved-layout description cannot be established from the supplied extraction.
Occupancy / completion certificate
Supplied evidenceNot supplied. Document index
What it establishesNo occupancy or completion certification is evidenced in this document set.

The RERA certificate identifies survey number 1324. The evidence supplied for this Overview does not include a separate occupancy or completion certificate, or an extracted approved-layout plan.

Other registrations of Century Condominium

Frequently asked questions

Is CENTURY CONDOMINIUM BLOCK - B registered with Telangana RERA?

Yes. CENTURY CONDOMINIUM BLOCK - B is registered with the Telangana Real Estate Regulatory Authority as P02700006270; the registration status is New Project.

Who is the developer of CENTURY CONDOMINIUM BLOCK - B?

The promoter named in the RERA registration is EDVENSWA EPC PRIVATE LIMITED.

Where is CENTURY CONDOMINIUM BLOCK - B located?

CENTURY CONDOMINIUM BLOCK - B is in Vavilalapally, Karimnagar urban, Karimnagar, Telangana (505001).

When will CENTURY CONDOMINIUM BLOCK - B be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.

More projects in Vavilalapally