Avanti County
SHRESHTA DEVELOPERS · Sangareddy · RERA P01100009078
AVANTI COUNTY is a residential plotted development in Zaheerabad, Zaheerabad Mandal, Sangareddy District. The registered promoter is SHRESHTA DEVELOPERS. The project covers 23909.06 sq.mts and has 85 residential plots; no tower or floor configuration is stated. It is registered under TG-RERA P01100009078, with a proposed completion date of 01/12/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | AVANTI COUNTY RERA record |
| Project type | Plotted development / residential layout RERA record RERA filing |
| Phase / registered portion | No separate phase is identified. Registration is for the project on Survey Nos. 45/P, 46/P and 47/P. |
| TG-RERA registration | P01100009078 RERA record |
| Registration validity | Certificate states valid from 02/12/2023 through 01/12/2025; no extension is recorded in the supplied certificate. Registration validity is separate from the completion deadline. |
| Registered promoter | SHRESHTA DEVELOPERS (also styled “M/s. SHRESHTA DEVELOPERS” in filed documents) RERA record Corporate record |
| RERA status | The project is recorded as a “New Project”; no current-status update beyond the supplied registration certificate is provided. RERA record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality | Zaheerabad RERA record |
| Revenue village | Pastapur Revenue Village in the layout approval and title materials; project filing also identifies Zaheerabad. |
| Mandal | Zaheerabad RERA record |
| District | Sangareddy RERA record |
| PIN | 502318 in project identity; the registration-certificate extraction gives 5023 and is truncated. RERA record |
| Project survey numbers | 45/P, 46/P and 47/P RERA record |
| Registered site extent | Approval document states 5 Acer 36.32 Gts 28595 Sq. Yds. |
| RERA land area | Total area 23909.06 sq.mts; net area 23909.06 sq.mts; affected area 0 as recorded in the filing. RERA filing |
| Drawing-derived site areas | The approved layout drawing extraction reports total site area 23908.14 sq.m and net layout area 23812.23 sq.m; these are drawing-derived figures. Layout record |
| Boundaries | North: 9 14 MT WIDE EXISTING ROAD; south, east and west: NEIGHBOURS LAND. RERA filing |
| Mortgage area recorded | 2046.84 sq.mts in the RERA land details. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Zaheerabad Municipality/Municipal Corporation Approvals record |
| Principal layout approval | Tentative layout plan No. 0010/LO/3057/2023; application No. 011887/LO/DTCP/3057/0030/2023. Application date: 19/10/2023. Approvals record |
| Approval status in supplied record | Approval document is expressly for a tentative layout plan. The document says final layout release follows completion of development works and release of mortgaged land. |
| Approved built-up area | 13399.77 sqmts, as recorded in the RERA filing; no building count or floor configuration is supplied. RERA filing |
| Building / tower count and floors | Not disclosed in the supplied RERA project record or layout approval. The development is a plotted layout, not a filed apartment-tower scheme. RERA record |
| Plot count | 85 in the tentative layout approval; drawing schedule also states 85 plots. Layout record |
Offering and status
| Field | Record |
|---|---|
| Offered product | Residential plots; the layout approval specifies detached dwelling houses for single-family occupation. |
| Plot count and sizes | Drawing-derived schedule: 85 plots; size range 113.35–236.22 sq.m (software-measured from the layout schedule). Layout record |
| Booked / available counts | Not disclosed in the supplied project data. RERA record Document index |
| Construction stage | No independently verified site progress is supplied. The tentative approval requires the applicant to carry out infrastructure and layout works. |
| Completion date | Promoter’s Form B undertaking and the registration certificate state 01/12/2025 as the completion/validity end date. |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. For a plotted layout, the provided material does not establish an OC or completion certificate for the layout. Document index |
2. The project story
AVANTI COUNTY is registered as a residential plotted development at Pastapur Revenue Village, Zaheerabad Mandal, Sangareddy District, on Survey Nos. 45/P, 46/P and 47/P. The project record identifies a site extent of 23909.06 sq.mts and a tentative municipal layout approval for 85 plots. RERA record RERA filing
The layout drawing schedule shows plots arranged within a network of internal roads, with land separately assigned to roads, park/open space, utilities and social infrastructure. The approval requires the applicant to undertake the layout’s infrastructure and other works; the supplied evidence does not independently verify construction progress or completion. Layout record
The registration certificate and the promoter’s Form B state 01/12/2025 as the completion date. The certificate’s registration validity also ends on that date; these are distinct recorded dates, and the supplied material does not show an extension or a completion certificate.
3. Master plan, architecture & building design
This is a plotted layout rather than a multi-storey building project in the supplied approval. The tentative approval identifies 85 plots and a layout extent of 5 Acer 36.32 Gts 28595 Sq. Yds.
The layout drawing’s software-measured area statement gives a net layout area of 23812.23 sq.m and reports the following allocation: Layout record
| Layout use | Area | Share of drawing’s net layout area |
|---|---|---|
| Plots | 13399.59 sq.m | 56.3% |
| Roads | 7428.09 sq.m | 31.2% |
| Parks / open space | 2149.19 sq.m | 9.0% |
| Utilities | 239.15 sq.m | 1.0% |
| Social infrastructure | 596.24 sq.m | 2.5% |
| Amenities | 0.0 sq.m | 0.0% |
The layout approval separately records 0 Acer 21.24 Gts 2570 Sq. Yds for open space, 0 Acer 5.89 Gts 713 Sq. Yds for social infrastructure, 0 Acer 2.36 Gts 286 Sq. Yds for utilities, 1 Acer 33.42 Gts 8884 Sq. Yds for roads and 3 Acer 12.45 Gts 16026 Sq. Yds as plotted area.
The RERA filing lists approved built-up area as 13399.77 sqmts; it does not provide a building-level schedule, floor configuration or building footprint. The layout approval says only detached dwelling houses designed for single-family occupation are to be built on sites. RERA filing
The approved-plan extraction lists water, sewerage and other infrastructure works as layout-development requirements. The approval also requires roads to remain accessible to neighbouring sites and prohibits a compound wall or fencing around the site.
4. Homes, configurations & floor plans
The project’s RERA-filed offering is plotted land. The supplied drawing schedule states 85 plots, with plot areas software-measured from the layout drawing; no plot-by-plot booking or availability schedule is provided. Layout record
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading |
|---|---|---|---|---|---|---|
| Residential plot | 85 (layout schedule) | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not disclosed |
Drawing-derived plot-size bands are: Layout record
| Size band | Number of plots |
|---|---|
| 100–150 sq yd (84–125 sq.m) | 1 |
| 150–200 sq yd (125–167 sq.m) | 59 |
| 200–250 sq yd (167–209 sq.m) | 22 |
| 250–300 sq yd (209–251 sq.m) | 3 |
The drawing extraction reports the smallest plot as 113.35 sq.m, median as 145.96 sq.m, and largest as 236.22 sq.m. These are software-measured from the drawing’s plot schedule, not RERA-filed saleable-area figures; the extraction notes that the plot-area sum matches the drawing’s plotted-area statement. Layout record
Two layout sheets are recorded, with 85 of 85 plot sizes measured by software. No apartment floor plans or room dimensions are supplied. Floor plans Layout record
5. Parking & vehicle circulation
The supplied project record does not establish a parking-space count, visitor or accessible parking provision, or plot-specific parking allocation. The tentative layout approval identifies internal roads and requires them to remain open for accessibility to neighbouring sites. It does not provide a separate parking plan or parking allotment schedule. Document index
The approval refers to detached single-family dwelling houses on plots, but the supplied layout materials do not establish individual driveway or vehicle-entry arrangements for each plot.
6. Amenities, recreation & open spaces
The tentative layout approval lists infrastructure and amenity works for the layout. The RERA amenity record marks several categories as available (“YES”) but records 0% progress for the listed items; that filing status does not establish completed or independently verified facilities. RERA amenities
| Facility | Park / green strip / TOT LOT |
|---|---|
| Description / size | Layout drawing: 2149.19 sq.m parks/open space; approval: 0 Acer 21.24 Gts 2570 Sq. Yds open space |
| Evidence source | Layout record |
| Declared progress / verified status | RERA amenity entry “Green Strip/TOT LOT/Park” marked YES, 0%; completion not independently verified RERA amenities |
| Facility | Avenue plantation |
|---|---|
| Description / size | Listed as a required layout work; no area or quantity supplied |
| Declared progress / verified status | Completion not established |
| Facility | Social infrastructure land |
|---|---|
| Description / size | Drawing: 596.24 sq.m; approval: 0 Acer 5.89 Gts 713 Sq. Yds |
| Evidence source | Layout record |
| Declared progress / verified status | No specific community facility or completion status supplied |
| Facility | Utility land |
|---|---|
| Description / size | Drawing: 239.15 sq.m; approval: 0 Acer 2.36 Gts 286 Sq. Yds |
| Evidence source | Layout record |
| Declared progress / verified status | Land allocation shown; facility completion not established |
The approval’s list of works includes park development. No clubhouse, swimming pool, gym or other indoor recreation facility is established by the supplied RERA-filed layout approval.
7. Utilities, building services & safety
The tentative layout approval requires infrastructure works, including a water reservoir, internal water-supply pipelines, overhead tank/sump, common septic tank, septic tank, sewerage treatment plant, underground drainage lines, storm-water drains, electric transformer, solid-waste management, street lights and rainwater-harvesting pits. These are listed as works to be undertaken; the supplied record does not verify their completion, capacities or operational status.
The RERA amenity record marks water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station as “YES”, with 0% progress shown for the entries. Fire-protection requirements and energy management appear in the amenity record without a “YES” entry or a supplied progress percentage. RERA amenities
No water-source details, storage capacities, treatment specifications, electrical backup, EV charging, security systems, accessibility features or fire-system design details are supplied. Document index RERA amenities
8. Location, access & connectivity
The registered location is Zaheerabad, Sangareddy District, Telangana, with Pastapur Revenue Village identified in the tentative layout approval and title materials. The site is recorded in Zaheerabad Mandal, on Survey Nos. 45/P, 46/P and 47/P. RERA record
The layout approval describes the north boundary as 9 14 MT WIDE EXISTING ROAD and requires the internal roads to remain open for access to neighbouring sites. The supplied project evidence does not identify public-transport services, measured distances to landmarks or travel times. RERA filing
9. Developer & development status
The registered promoter is SHRESHTA DEVELOPERS, recorded as a partnership. Its supplied GSTIN is 36AEUFS0547J1ZG. The RERA filing lists the promoter address as B, GANESH NAGAR, PASTAPUR, ZAHEERABAD, ZAHEERABAD, Sangareddy, 502318. Corporate record RERA filing RERA filing
The RERA record identifies KULKARNI SUSHANTH as authorized signatory and MEGHAVATH RAGHUVEER NAIK, MUNNUR KAPU MANJULA and GONGULURI SHIVAKANTH as partners. Parties record
The promoter’s Form B affidavit, dated 28* day of September 2024 in the extraction, undertakes to complete the project by 01/12/2025 and states that the land is free from encumbrances. These are promoter declarations in the filed affidavit.
No independent construction-progress inspection, booked/available plot schedule, or completion certificate is provided. The approval makes the applicant responsible for the layout development works and states that the Municipality/Municipal Corporation will not undertake those works.
10. Approvals, official records & documents
| Identifier / date | P01100009078; issued 28/11/2024; validity 02/12/2023–01/12/2025 |
|---|---|
| What the supplied record establishes | Registration of AVANTI COUNTY under section 5; certificate includes a 70% separate-account condition. |
| Identifier / date | 0010/LO/3057/2023; application 011887/LO/DTCP/3057/0030/2023 |
|---|---|
| What the supplied record establishes | Tentative residential layout approval for 85 plots on Survey Nos. 45/P, 46/P and 47/P at Pastapur Revenue Village. |
| Identifier / date | Document 490939, two layout sheets |
|---|---|
| What the supplied record establishes | Drawing-derived plot schedule and land-use allocation; extraction notes measurements should be verified against the drawing. Layout record |
| Identifier / date | Document 491028; dated 28* day of September 2024 in extraction |
|---|---|
| What the supplied record establishes | Promoter declaration covering title, encumbrances, completion date and project-fund obligations. |
| Identifier / date | Document 493542, dated 4-10-2024 |
|---|---|
| What the supplied record establishes | Search report concerning the project land at Pastapur Revenue Village, described as Ac 5-36.32 Gts in Sy. Nos. 45/P, 46/P and 47/P. |
| Identifier / date | 10067/2023, dated 22 November, 2023 |
|---|---|
| What the supplied record establishes | The tentative layout approval identifies a mortgage over Plots 74, 73, 79, 72, 80, 71, 81, 70, 82, 69, 83, 68, 67 and 84, in favour of Zaheerabad Municipality/Municipal Corporation, pending layout-development and release requirements. |
| Identifier / date | TS/30542/2023, TS/30543/2023 (26 October, 2023); TS/30886/2023 (28 November, 2023) |
|---|---|
| What the supplied record establishes | Receipt numbers recorded in the tentative layout approval. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No certificate is included in the provided project documents. Document index |
1. Project at a glance
Project identity
Registered project name: AVANTI COUNTY
Project type: Plotted development / residential layout
Phase / registered portion: No separate phase is identified. Registration is for the project on Survey Nos. 45/P, 46/P and 47/P.
TG-RERA registration: P01100009078
Registration validity: Certificate states valid from 02/12/2023 through 01/12/2025; no extension is recorded in the supplied certificate. Registration validity is separate from the completion deadline.
Registered promoter: SHRESHTA DEVELOPERS (also styled “M/s. SHRESHTA DEVELOPERS” in filed documents)
RERA status: The project is recorded as a “New Project”; no current-status update beyond the supplied registration certificate is provided.
Land and geographic identity
Locality: Zaheerabad
Revenue village: Pastapur Revenue Village in the layout approval and title materials; project filing also identifies Zaheerabad.
Mandal: Zaheerabad
District: Sangareddy
PIN: 502318 in project identity; the registration-certificate extraction gives 5023 and is truncated.
Project survey numbers: 45/P, 46/P and 47/P
Registered site extent: Approval document states 5 Acer 36.32 Gts 28595 Sq. Yds.
RERA land area: Total area 23909.06 sq.mts; net area 23909.06 sq.mts; affected area 0 as recorded in the filing.
Drawing-derived site areas: The approved layout drawing extraction reports total site area 23908.14 sq.m and net layout area 23812.23 sq.m; these are drawing-derived figures.
Boundaries: North: 9 14 MT WIDE EXISTING ROAD; south, east and west: NEIGHBOURS LAND.
Mortgage area recorded: 2046.84 sq.mts in the RERA land details.
Development identity
Sanctioning authority: Zaheerabad Municipality/Municipal Corporation
Principal layout approval: Tentative layout plan No. 0010/LO/3057/2023; application No. 011887/LO/DTCP/3057/0030/2023. Application date: 19/10/2023.
Approval status in supplied record: Approval document is expressly for a tentative layout plan. The document says final layout release follows completion of development works and release of mortgaged land.
Approved built-up area: 13399.77 sqmts, as recorded in the RERA filing; no building count or floor configuration is supplied.
Building / tower count and floors: Not disclosed in the supplied RERA project record or layout approval. The development is a plotted layout, not a filed apartment-tower scheme.
Plot count: 85 in the tentative layout approval; drawing schedule also states 85 plots.
Offering and status
Offered product: Residential plots; the layout approval specifies detached dwelling houses for single-family occupation.
Plot count and sizes: Drawing-derived schedule: 85 plots; size range 113.35–236.22 sq.m (software-measured from the layout schedule).
Booked / available counts: Not disclosed in the supplied project data.
Construction stage: No independently verified site progress is supplied. The tentative approval requires the applicant to carry out infrastructure and layout works.
Completion date: Promoter’s Form B undertaking and the registration certificate state 01/12/2025 as the completion/validity end date.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. For a plotted layout, the provided material does not establish an OC or completion certificate for the layout.
2. The project story
AVANTI COUNTY is registered as a residential plotted development at Pastapur Revenue Village, Zaheerabad Mandal, Sangareddy District, on Survey Nos. 45/P, 46/P and 47/P. The project record identifies a site extent of 23909.06 sq.mts and a tentative municipal layout approval for 85 plots.
The layout drawing schedule shows plots arranged within a network of internal roads, with land separately assigned to roads, park/open space, utilities and social infrastructure. The approval requires the applicant to undertake the layout’s infrastructure and other works; the supplied evidence does not independently verify construction progress or completion.
The registration certificate and the promoter’s Form B state 01/12/2025 as the completion date. The certificate’s registration validity also ends on that date; these are distinct recorded dates, and the supplied material does not show an extension or a completion certificate.
3. Master plan, architecture & building design
This is a plotted layout rather than a multi-storey building project in the supplied approval. The tentative approval identifies 85 plots and a layout extent of 5 Acer 36.32 Gts 28595 Sq. Yds.
The layout drawing’s software-measured area statement gives a net layout area of 23812.23 sq.m and reports the following allocation:
| Layout use | Area | Share of drawing’s net layout area |
|---|---|---|
| Plots | 13399.59 sq.m | 56.3% |
| Roads | 7428.09 sq.m | 31.2% |
| Parks / open space | 2149.19 sq.m | 9.0% |
| Utilities | 239.15 sq.m | 1.0% |
| Social infrastructure | 596.24 sq.m | 2.5% |
| Amenities | 0.0 sq.m | 0.0% |
The layout approval separately records 0 Acer 21.24 Gts 2570 Sq. Yds for open space, 0 Acer 5.89 Gts 713 Sq. Yds for social infrastructure, 0 Acer 2.36 Gts 286 Sq. Yds for utilities, 1 Acer 33.42 Gts 8884 Sq. Yds for roads and 3 Acer 12.45 Gts 16026 Sq. Yds as plotted area.
The RERA filing lists approved built-up area as 13399.77 sqmts; it does not provide a building-level schedule, floor configuration or building footprint. The layout approval says only detached dwelling houses designed for single-family occupation are to be built on sites.
The approved-plan extraction lists water, sewerage and other infrastructure works as layout-development requirements. The approval also requires roads to remain accessible to neighbouring sites and prohibits a compound wall or fencing around the site.
4. Homes, configurations & floor plans
The project’s RERA-filed offering is plotted land. The supplied drawing schedule states 85 plots, with plot areas software-measured from the layout drawing; no plot-by-plot booking or availability schedule is provided.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading |
|---|---|---|---|---|---|---|
| Residential plot | 85 (layout schedule) | Not disclosed | Not disclosed | Not disclosed | Not applicable | Not disclosed |
Drawing-derived plot-size bands are:
100–150 sq yd (84–125 sq.m): 1
150–200 sq yd (125–167 sq.m): 59
200–250 sq yd (167–209 sq.m): 22
250–300 sq yd (209–251 sq.m): 3
The drawing extraction reports the smallest plot as 113.35 sq.m, median as 145.96 sq.m, and largest as 236.22 sq.m. These are software-measured from the drawing’s plot schedule, not RERA-filed saleable-area figures; the extraction notes that the plot-area sum matches the drawing’s plotted-area statement.
Two layout sheets are recorded, with 85 of 85 plot sizes measured by software. No apartment floor plans or room dimensions are supplied.
5. Parking & vehicle circulation
The supplied project record does not establish a parking-space count, visitor or accessible parking provision, or plot-specific parking allocation. The tentative layout approval identifies internal roads and requires them to remain open for accessibility to neighbouring sites. It does not provide a separate parking plan or parking allotment schedule.
The approval refers to detached single-family dwelling houses on plots, but the supplied layout materials do not establish individual driveway or vehicle-entry arrangements for each plot.
6. Amenities, recreation & open spaces
The tentative layout approval lists infrastructure and amenity works for the layout. The RERA amenity record marks several categories as available (“YES”) but records 0% progress for the listed items; that filing status does not establish completed or independently verified facilities.
| Facility | Park / green strip / TOT LOT |
|---|---|
| Description / size | Layout drawing: 2149.19 sq.m parks/open space; approval: 0 Acer 21.24 Gts 2570 Sq. Yds open space |
| Declared progress / verified status | RERA amenity entry “Green Strip/TOT LOT/Park” marked YES, 0%; completion not independently verified |
| Facility | Avenue plantation |
|---|---|
| Description / size | Listed as a required layout work; no area or quantity supplied |
| Declared progress / verified status | Completion not established |
| Facility | Social infrastructure land |
|---|---|
| Description / size | Drawing: 596.24 sq.m; approval: 0 Acer 5.89 Gts 713 Sq. Yds |
| Declared progress / verified status | No specific community facility or completion status supplied |
| Facility | Utility land |
|---|---|
| Description / size | Drawing: 239.15 sq.m; approval: 0 Acer 2.36 Gts 286 Sq. Yds |
| Declared progress / verified status | Land allocation shown; facility completion not established |
The approval’s list of works includes park development. No clubhouse, swimming pool, gym or other indoor recreation facility is established by the supplied RERA-filed layout approval.
7. Utilities, building services & safety
The tentative layout approval requires infrastructure works, including a water reservoir, internal water-supply pipelines, overhead tank/sump, common septic tank, septic tank, sewerage treatment plant, underground drainage lines, storm-water drains, electric transformer, solid-waste management, street lights and rainwater-harvesting pits. These are listed as works to be undertaken; the supplied record does not verify their completion, capacities or operational status.
The RERA amenity record marks water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station as “YES”, with 0% progress shown for the entries. Fire-protection requirements and energy management appear in the amenity record without a “YES” entry or a supplied progress percentage.
No water-source details, storage capacities, treatment specifications, electrical backup, EV charging, security systems, accessibility features or fire-system design details are supplied.
8. Location, access & connectivity
The registered location is Zaheerabad, Sangareddy District, Telangana, with Pastapur Revenue Village identified in the tentative layout approval and title materials. The site is recorded in Zaheerabad Mandal, on Survey Nos. 45/P, 46/P and 47/P.
The layout approval describes the north boundary as 9 14 MT WIDE EXISTING ROAD and requires the internal roads to remain open for access to neighbouring sites. The supplied project evidence does not identify public-transport services, measured distances to landmarks or travel times.
9. Developer & development status
The registered promoter is SHRESHTA DEVELOPERS, recorded as a partnership. Its supplied GSTIN is 36AEUFS0547J1ZG. The RERA filing lists the promoter address as B, GANESH NAGAR, PASTAPUR, ZAHEERABAD, ZAHEERABAD, Sangareddy, 502318.
The RERA record identifies KULKARNI SUSHANTH as authorized signatory and MEGHAVATH RAGHUVEER NAIK, MUNNUR KAPU MANJULA and GONGULURI SHIVAKANTH as partners.
The promoter’s Form B affidavit, dated 28* day of September 2024 in the extraction, undertakes to complete the project by 01/12/2025 and states that the land is free from encumbrances. These are promoter declarations in the filed affidavit.
No independent construction-progress inspection, booked/available plot schedule, or completion certificate is provided. The approval makes the applicant responsible for the layout development works and states that the Municipality/Municipal Corporation will not undertake those works.
10. Approvals, official records & documents
| Identifier / date | P01100009078; issued 28/11/2024; validity 02/12/2023–01/12/2025 |
|---|---|
| What the supplied record establishes | Registration of AVANTI COUNTY under section 5; certificate includes a 70% separate-account condition. |
| Identifier / date | 0010/LO/3057/2023; application 011887/LO/DTCP/3057/0030/2023 |
|---|---|
| What the supplied record establishes | Tentative residential layout approval for 85 plots on Survey Nos. 45/P, 46/P and 47/P at Pastapur Revenue Village. |
| Identifier / date | Document 490939, two layout sheets |
|---|---|
| What the supplied record establishes | Drawing-derived plot schedule and land-use allocation; extraction notes measurements should be verified against the drawing. |
| Identifier / date | Document 491028; dated 28* day of September 2024 in extraction |
|---|---|
| What the supplied record establishes | Promoter declaration covering title, encumbrances, completion date and project-fund obligations. |
| Identifier / date | Document 493542, dated 4-10-2024 |
|---|---|
| What the supplied record establishes | Search report concerning the project land at Pastapur Revenue Village, described as Ac 5-36.32 Gts in Sy. Nos. 45/P, 46/P and 47/P. |
| Identifier / date | 10067/2023, dated 22 November, 2023 |
|---|---|
| What the supplied record establishes | The tentative layout approval identifies a mortgage over Plots 74, 73, 79, 72, 80, 71, 81, 70, 82, 69, 83, 68, 67 and 84, in favour of Zaheerabad Municipality/Municipal Corporation, pending layout-development and release requirements. |
| Identifier / date | TS/30542/2023, TS/30543/2023 (26 October, 2023); TS/30886/2023 (28 November, 2023) |
|---|---|
| What the supplied record establishes | Receipt numbers recorded in the tentative layout approval. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No certificate is included in the provided project documents. |
Frequently asked questions
Is AVANTI COUNTY registered with Telangana RERA?
Yes. AVANTI COUNTY is registered with the Telangana Real Estate Regulatory Authority as P01100009078; the registration status is New Project.
Who is the developer of AVANTI COUNTY?
The promoter named in the RERA registration is SHRESHTA DEVELOPERS.
Where is AVANTI COUNTY located?
AVANTI COUNTY is in ZAHEERABAD, Sangareddy, Telangana (502318).
When will AVANTI COUNTY be completed?
The promoter's proposed date of completion filed with RERA is 01/12/2025. This is the promoter's declaration, not a guarantee.