Adi Rama Krishna Puram Phase - II
SRI TIRUMALA HOUSING PVT LTD. · Yadadri Bhuvanagiri · RERA P02000008165
ADI RAMA KRISHNA PURAM PHASE - II is a plotted development in THANGADI PALLY(OLD VILLAGE), Choutuppal Mandal, Yadadri Bhuvanagiri District, developed by the registered promoter SRI TIRUMALA HOUSING PVT LTD. The layout covers 60,596.97 sq.m. and shows 210 plots numbered 01 to 210; plot configurations and plot-by-plot sizes are not supplied. The project is registered under TG-RERA number P02000008165, with a proposed completion date of 16.08.2027.
More from Sri Tirumala Housing Pvt Ltd · 5 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | ADI RAMA KRISHNA PURAM PHASE - II RERA record |
| Project type | Plotted development; the HMDA-filed layout describes an open-plots layout RERA record RERA filing |
| Phase / registered portion | Phase II RERA record |
| TG-RERA registration | P02000008165, recorded as valid from 4 May 2024 to 16 August 2027 RERA record Approvals record |
| Registered promoter | SRI TIRUMALA HOUSING PVT LTD. RERA record Corporate record |
| RERA status | The supplied record identifies this as a registered “New Project”; the registration validity dates are stated above. RERA record RERA filing Approvals record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | THANGADPALLY / THANGADPALLY (OLD VILLAGE) RERA record RERA filing |
| Revenue village | THANGADI PALLY(OLD VILLAGE); the filed layout documents also use Thangadpally Village. RERA record RERA filing |
| Mandal / district / PIN | Choutuppal / Yadadri Bhuvanagiri / 508252 RERA record RERA filing |
| Survey number(s) / subdivision(s) | 719/PART RERA record RERA filing |
| RERA-filed site extent | 60,596.97 sq.m.; total and net site area are each recorded as 60,596.97 sq.m. RERA filing Layout record |
| Boundaries | East: EXISTING LAYOUT; West: NEIGHBOURS LAND; North: NEIGHBOURS LAND; South: EXISTING LAYOUT RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA) Approvals record |
| Principal layout approval | TS/053852/2022, dated 30-08-2022, described in the filed plan as technical approval of a draft layout Approvals record |
| Further HMDA layout proceedings | 008636/LO/HMDA/1759/GHT/2022, dated 03 February, 2023 Approvals record |
| Approved built-up area | 38371.88 sq.m. is recorded as “Approved Built up Area” in the RERA fields; the layout plan separately records proposed/net built-up area as 0.00 for this open-plots layout. RERA filing |
| Plots in filed layout | 210, numbered 01 to 210, according to the submitted layout-plan extraction. |
| Buildings / floors | No tower or building count, floor configuration, or building parking levels are disclosed in the supplied project record. The registration is for a plotted layout. RERA record |
| Layout mortgage area | 5792.18 sq.m., identified in the filed layout records as plots mortgaged to HMDA. RERA filing Layout record |
Offering and status
| Item | Project record |
|---|---|
| Offering | Open plots; plot-by-plot sizes, unit inventory counts, and booked/available counts are not supplied in the reviewed data. RERA record |
| Construction stage | An architect’s Form 1A, dated 30/09/2025, states that development work for Phase II was complete; this is a filed architect certification, not an independent site inspection. |
| Completion timeline | The promoter’s Form B undertaking states 16.08.2027 as the project completion date. |
| Final layout record | The Form 1A records final layout number 003579/HMDA/01038/SWFL/GTK/2025, completed by HMDA on 03.07.2025. |
| Occupancy / completion certificate status | The supplied completion document is an architect’s Form 1A and does not itself provide an occupancy certificate. No occupancy certificate is identified in the supplied record. |
2. The project story
- Adi Rama Krishna Puram Phase II is registered as a plotted development on 719/PART, in THANGADI PALLY(OLD VILLAGE), Choutuppal Mandal, Yadadri Bhuvanagiri District. The RERA-filed layout records a total/net site area of 60,596.97 sq.m. and 210 plots numbered 01–210. It allocates land to plots, roads, open space/park, social infrastructure and utilities. RERA record RERA filing
- The project record contains HMDA draft-layout approval documents and a later final-layout number. The architect’s Form 1A dated 30/09/2025 certifies completion of development work and refers to HMDA completion on 03.07.2025. This is a promoter-filed professional certificate; the supplied materials do not include an occupancy certificate or independent site verification. The promoter’s Form B separately undertakes completion by 16.08.2027.
- The layout approval documents identify 32 plots, including the listed mortgage plots, as mortgaged to HMDA pending infrastructure obligations; the layout extraction gives the mortgage area as 5792.18 sq.m. Layout record
3. Master plan, architecture & building design
This is a plotted layout rather than a tower or apartment scheme. The approved-layout extraction records 60,596.97 sq.m. total and net layout area, with land use as follows. These are figures extracted from the filed layout drawing; plot sizes and plot-by-plot measurements are not available in the supplied data. Layout record
| Layout use | Area | Share recorded in layout |
|---|---|---|
| Plotted area | 38371.88 sq.m. | 63.32% |
| Roads | 15536.27 sq.m. | 25.64% |
| Organized open space/park | 4552.37 sq.m. | 7.51% |
| Social infrastructure | 1518.97 sq.m. | 2.51% |
| Utilities | 617.35 sq.m. | 1.02% |
| Amenity area | 0.00 sq.m. | 0.00% |
The RERA fields record 38371.88 sq.m. as approved built-up area, while the layout-plan extraction describes the proposed/net built-up area as 0.00 for the open-plots layout. No building arrangement, floor plans, tower heights, or residential/commercial building distribution is evidenced in the supplied project documents. RERA filing
4. Homes, configurations & floor plans
The registered offering is plotted development. Plot sizes, plot-by-plot inventory, and booked/available counts are not supplied. The available drawing set comprises two layout sheets; the floor-plan record reports no measured drawings and no flats, so no carpet-area or room-configuration measurements can be stated. RERA record Floor plans
| Units | 210 plots are shown in the filed layout; plot-by-plot size and inventory status not supplied |
|---|---|
| Booked | Not supplied |
| Available | Not supplied |
| RERA saleable area | Not supplied |
| Measured carpet area | Not applicable / not supplied |
| Loading | Not supplied |
5. Parking & vehicle circulation
The filed layout records Proposed Number of Parkings: 0 and Common Parking Area: 0.00. It does not provide a separate resident or visitor parking allocation, plot-level parking entitlement, or an exclusive parking ownership schedule. The layout approval refers to roads and access but the supplied material does not establish a vehicle-circulation plan beyond the recorded road area.
6. Amenities, recreation & open spaces
The RERA-filed amenity disclosure marks several layout infrastructure items as available at 100%. The approval documents also identify infrastructure and land intended for transfer to the local body before release of final layout plans. The supplied evidence does not independently verify completed delivery of each facility. RERA amenities
| Description / size | No clubhouse or community-building provision is identified; community buildings are recorded at 0%. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Not declared available in the RERA amenity record. |
| Description / size | No specific sports facility is listed. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Not supplied. |
| Description / size | Organized open space/park: 4552.37 sq.m. (7.51%). “Green Strip/TOT LOT/Park” and aggregate recreational open space are each marked YES / 100% in the RERA amenity record. |
|---|---|
| Evidence source | Layout record RERA amenities |
| Declared progress / verified status | RERA-listed as available; independent completion verification not supplied. |
| Description / size | Social infrastructure land: 1518.97 sq.m. (2.51%); utilities land: 617.35 sq.m. |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Land allocation appears in the filed layout; facility-level construction or operation status is not supplied. |
| Description / size | Internal roads and footpaths; water supply; sewerage; storm-water drains; street lighting; water conservation/rainwater harvesting; electrical meter room/sub-station/receiving station. Each is marked YES / 100% in the amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-declared; independent verification not supplied. |
7. Utilities, building services & safety
The RERA amenity record marks water supply, sewerage, storm-water drains, rainwater harvesting, electrical meter room/sub-station/receiving station, internal roads and footpaths, and street lighting as available at 100%. The HMDA draft-layout document lists common septic tank/STP, overhead tank, transformer, rainwater-harvesting pits and bio-compost unit among layout facilities. These are filed or listed provisions; the supplied material does not state capacities or independently verify operation. RERA amenities
The RERA amenity record lists solid-waste management and disposal, energy management, and fire-protection/fire-safety requirements at 0%; treatment and disposal of sewage and sullage water is also recorded at 0%. No lift, accessibility, CCTV, security-system, backup-power, or EV-charging specifications are supplied. RERA amenities
8. Location, access & connectivity
The registered location is THANGADI PALLY(OLD VILLAGE), Choutuppal Mandal, Yadadri Bhuvanagiri District, PIN 508252, with the project identified in 719/PART. The cadastral parcel centroid is recorded at 17.25009200865051, 78.87363224626145. RERA record RERA filing Cadastral map
The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 28.0 km. No additional measured distances or verified public-transport information are supplied. Location record
9. Developer & development status
The registered promoter is SRI TIRUMALA HOUSING PVT LTD., a company. The corporate identifier supplied is GSTIN 36AAECS9038B1ZF. The project record gives the promoter’s address as SRI BALAJI HOUSE, MAIN ROAD, SY NO 719/PART, THANGADPALLY, Choutuppal, Yadadri Bhuvanagiri, 508252. RERA record Corporate record Parties record
The RERA record identifies ASHOK KUMAR N as Managing Director and authorized signatory. Parties record
10. Approvals, official records & documents
| Details | Form C registration certificate; project P02000008165; registered promoter Sri Tirumala Housing Pvt Ltd. |
|---|
| Details | TS/053852/2022, dated 30-08-2022; filed plan identifies 210 plots and layout land-use figures. |
|---|---|
| Evidence | Approvals record |
| Details | 008636/LO/HMDA/1759/GHT/2022, dated 03 February, 2023; document identifies survey 719/PART, Choutuppal Mandal, and HMDA conditions for layout infrastructure and mortgaged plots. |
|---|---|
| Evidence | Approvals record |
| Details | Document No. 407/2023, dated 20 January, 2023; HMDA mortgage area recorded as 5792.18 sq.m. |
|---|
| Details | 003579/HMDA/01038/SWFL/GTK/2025, recorded as completed by HMDA on 03.07.2025. |
|---|---|
| Evidence | Approvals record |
| Details | Form 1A dated 30/09/2025, certifying development-work completion for Phase II; the supplied document is not an occupancy certificate. |
|---|
| Details | Dated 1 April 2024; includes the promoter’s completion undertaking and project-account declarations. |
|---|
| Details | Revenue location and survey recorded as THANGADI PALLY(OLD VILLAGE), Choutuppal, Yadadri Bhuvanagiri, 719/PART. |
|---|
The promoter’s Form B, dated 1 April 2024, declares a completion undertaking of 16.08.2027. Separately, the architect’s Form 1A dated 30/09/2025 certifies completion of development work for Phase II and refers to the final layout record dated 03.07.2025. The latter is a filed professional certification, not an independent site verification. Parties record
The supplied materials do not include an occupancy certificate, building floor plans, or a plot-by-plot area schedule.
1. Project at a glance
Project identity
Registered project name: ADI RAMA KRISHNA PURAM PHASE - II
Project type: Plotted development; the HMDA-filed layout describes an open-plots layout
Phase / registered portion: Phase II
TG-RERA registration: P02000008165, recorded as valid from 4 May 2024 to 16 August 2027
Registered promoter: SRI TIRUMALA HOUSING PVT LTD.
RERA status: The supplied record identifies this as a registered “New Project”; the registration validity dates are stated above.
Land and geographic identity
Locality: THANGADPALLY / THANGADPALLY (OLD VILLAGE)
Revenue village: THANGADI PALLY(OLD VILLAGE); the filed layout documents also use Thangadpally Village.
Mandal / district / PIN: Choutuppal / Yadadri Bhuvanagiri / 508252
Survey number(s) / subdivision(s): 719/PART
RERA-filed site extent: 60,596.97 sq.m.; total and net site area are each recorded as 60,596.97 sq.m.
Boundaries: East: EXISTING LAYOUT; West: NEIGHBOURS LAND; North: NEIGHBOURS LAND; South: EXISTING LAYOUT
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA)
Principal layout approval: TS/053852/2022, dated 30-08-2022, described in the filed plan as technical approval of a draft layout
Further HMDA layout proceedings: 008636/LO/HMDA/1759/GHT/2022, dated 03 February, 2023
Approved built-up area: 38371.88 sq.m. is recorded as “Approved Built up Area” in the RERA fields; the layout plan separately records proposed/net built-up area as 0.00 for this open-plots layout.
Plots in filed layout: 210, numbered 01 to 210, according to the submitted layout-plan extraction.
Buildings / floors: No tower or building count, floor configuration, or building parking levels are disclosed in the supplied project record. The registration is for a plotted layout.
Layout mortgage area: 5792.18 sq.m., identified in the filed layout records as plots mortgaged to HMDA.
Offering and status
Offering: Open plots; plot-by-plot sizes, unit inventory counts, and booked/available counts are not supplied in the reviewed data.
Construction stage: An architect’s Form 1A, dated 30/09/2025, states that development work for Phase II was complete; this is a filed architect certification, not an independent site inspection.
Completion timeline: The promoter’s Form B undertaking states 16.08.2027 as the project completion date.
Final layout record: The Form 1A records final layout number 003579/HMDA/01038/SWFL/GTK/2025, completed by HMDA on 03.07.2025.
Occupancy / completion certificate status: The supplied completion document is an architect’s Form 1A and does not itself provide an occupancy certificate. No occupancy certificate is identified in the supplied record.
2. The project story
- Adi Rama Krishna Puram Phase II is registered as a plotted development on 719/PART, in THANGADI PALLY(OLD VILLAGE), Choutuppal Mandal, Yadadri Bhuvanagiri District. The RERA-filed layout records a total/net site area of 60,596.97 sq.m. and 210 plots numbered 01–210. It allocates land to plots, roads, open space/park, social infrastructure and utilities.
- The project record contains HMDA draft-layout approval documents and a later final-layout number. The architect’s Form 1A dated 30/09/2025 certifies completion of development work and refers to HMDA completion on 03.07.2025. This is a promoter-filed professional certificate; the supplied materials do not include an occupancy certificate or independent site verification. The promoter’s Form B separately undertakes completion by 16.08.2027.
- The layout approval documents identify 32 plots, including the listed mortgage plots, as mortgaged to HMDA pending infrastructure obligations; the layout extraction gives the mortgage area as 5792.18 sq.m.
3. Master plan, architecture & building design
This is a plotted layout rather than a tower or apartment scheme. The approved-layout extraction records 60,596.97 sq.m. total and net layout area, with land use as follows. These are figures extracted from the filed layout drawing; plot sizes and plot-by-plot measurements are not available in the supplied data.
| Layout use | Area | Share recorded in layout |
|---|---|---|
| Plotted area | 38371.88 sq.m. | 63.32% |
| Roads | 15536.27 sq.m. | 25.64% |
| Organized open space/park | 4552.37 sq.m. | 7.51% |
| Social infrastructure | 1518.97 sq.m. | 2.51% |
| Utilities | 617.35 sq.m. | 1.02% |
| Amenity area | 0.00 sq.m. | 0.00% |
The RERA fields record 38371.88 sq.m. as approved built-up area, while the layout-plan extraction describes the proposed/net built-up area as 0.00 for the open-plots layout. No building arrangement, floor plans, tower heights, or residential/commercial building distribution is evidenced in the supplied project documents.
4. Homes, configurations & floor plans
The registered offering is plotted development. Plot sizes, plot-by-plot inventory, and booked/available counts are not supplied. The available drawing set comprises two layout sheets; the floor-plan record reports no measured drawings and no flats, so no carpet-area or room-configuration measurements can be stated.
| Units | 210 plots are shown in the filed layout; plot-by-plot size and inventory status not supplied |
|---|---|
| Booked | Not supplied |
| Available | Not supplied |
| RERA saleable area | Not supplied |
| Measured carpet area | Not applicable / not supplied |
| Loading | Not supplied |
5. Parking & vehicle circulation
The filed layout records Proposed Number of Parkings: 0 and Common Parking Area: 0.00. It does not provide a separate resident or visitor parking allocation, plot-level parking entitlement, or an exclusive parking ownership schedule. The layout approval refers to roads and access but the supplied material does not establish a vehicle-circulation plan beyond the recorded road area.
6. Amenities, recreation & open spaces
The RERA-filed amenity disclosure marks several layout infrastructure items as available at 100%. The approval documents also identify infrastructure and land intended for transfer to the local body before release of final layout plans. The supplied evidence does not independently verify completed delivery of each facility.
| Description / size | No clubhouse or community-building provision is identified; community buildings are recorded at 0%. |
|---|---|
| Declared progress / verified status | Not declared available in the RERA amenity record. |
| Description / size | No specific sports facility is listed. |
|---|---|
| Declared progress / verified status | Not supplied. |
| Description / size | Organized open space/park: 4552.37 sq.m. (7.51%). “Green Strip/TOT LOT/Park” and aggregate recreational open space are each marked YES / 100% in the RERA amenity record. |
|---|---|
| Declared progress / verified status | RERA-listed as available; independent completion verification not supplied. |
| Description / size | Social infrastructure land: 1518.97 sq.m. (2.51%); utilities land: 617.35 sq.m. |
|---|---|
| Declared progress / verified status | Land allocation appears in the filed layout; facility-level construction or operation status is not supplied. |
| Description / size | Internal roads and footpaths; water supply; sewerage; storm-water drains; street lighting; water conservation/rainwater harvesting; electrical meter room/sub-station/receiving station. Each is marked YES / 100% in the amenity record. |
|---|---|
| Declared progress / verified status | RERA-declared; independent verification not supplied. |
7. Utilities, building services & safety
The RERA amenity record marks water supply, sewerage, storm-water drains, rainwater harvesting, electrical meter room/sub-station/receiving station, internal roads and footpaths, and street lighting as available at 100%. The HMDA draft-layout document lists common septic tank/STP, overhead tank, transformer, rainwater-harvesting pits and bio-compost unit among layout facilities. These are filed or listed provisions; the supplied material does not state capacities or independently verify operation.
The RERA amenity record lists solid-waste management and disposal, energy management, and fire-protection/fire-safety requirements at 0%; treatment and disposal of sewage and sullage water is also recorded at 0%. No lift, accessibility, CCTV, security-system, backup-power, or EV-charging specifications are supplied.
8. Location, access & connectivity
The registered location is THANGADI PALLY(OLD VILLAGE), Choutuppal Mandal, Yadadri Bhuvanagiri District, PIN 508252, with the project identified in 719/PART. The cadastral parcel centroid is recorded at 17.25009200865051, 78.87363224626145.
The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 28.0 km. No additional measured distances or verified public-transport information are supplied.
9. Developer & development status
The registered promoter is SRI TIRUMALA HOUSING PVT LTD., a company. The corporate identifier supplied is GSTIN 36AAECS9038B1ZF. The project record gives the promoter’s address as SRI BALAJI HOUSE, MAIN ROAD, SY NO 719/PART, THANGADPALLY, Choutuppal, Yadadri Bhuvanagiri, 508252.
The RERA record identifies ASHOK KUMAR N as Managing Director and authorized signatory.
10. Approvals, official records & documents
| Details | Form C registration certificate; project P02000008165; registered promoter Sri Tirumala Housing Pvt Ltd. |
|---|
| Details | TS/053852/2022, dated 30-08-2022; filed plan identifies 210 plots and layout land-use figures. |
|---|
| Details | 008636/LO/HMDA/1759/GHT/2022, dated 03 February, 2023; document identifies survey 719/PART, Choutuppal Mandal, and HMDA conditions for layout infrastructure and mortgaged plots. |
|---|
| Details | Document No. 407/2023, dated 20 January, 2023; HMDA mortgage area recorded as 5792.18 sq.m. |
|---|
| Details | 003579/HMDA/01038/SWFL/GTK/2025, recorded as completed by HMDA on 03.07.2025. |
|---|
| Details | Form 1A dated 30/09/2025, certifying development-work completion for Phase II; the supplied document is not an occupancy certificate. |
|---|
| Details | Dated 1 April 2024; includes the promoter’s completion undertaking and project-account declarations. |
|---|
| Details | Revenue location and survey recorded as THANGADI PALLY(OLD VILLAGE), Choutuppal, Yadadri Bhuvanagiri, 719/PART. |
|---|
The promoter’s Form B, dated 1 April 2024, declares a completion undertaking of 16.08.2027. Separately, the architect’s Form 1A dated 30/09/2025 certifies completion of development work for Phase II and refers to the final layout record dated 03.07.2025. The latter is a filed professional certification, not an independent site verification.
The supplied materials do not include an occupancy certificate, building floor plans, or a plot-by-plot area schedule.
Frequently asked questions
Is ADI RAMA KRISHNA PURAM PHASE - II registered with Telangana RERA?
Yes. ADI RAMA KRISHNA PURAM PHASE - II is registered with the Telangana Real Estate Regulatory Authority as P02000008165; the registration status is New Project.
Who is the developer of ADI RAMA KRISHNA PURAM PHASE - II?
The promoter named in the RERA registration is SRI TIRUMALA HOUSING PVT LTD..
Where is ADI RAMA KRISHNA PURAM PHASE - II located?
ADI RAMA KRISHNA PURAM PHASE - II is in THANGADPALLY, THANGADI PALLY(OLD VILLAGE), Choutuppal, Yadadri Bhuvanagiri, Telangana (508252).
When will ADI RAMA KRISHNA PURAM PHASE - II be completed?
The promoter's proposed date of completion filed with RERA is 16/08/2027. This is the promoter's declaration, not a guarantee.
More projects in Thangadi Pally