Nisaa SEZ Town
MD MAZHAR UDDIN · Mahabubnagar · RERA P01400010043
NISAA SEZ TOWN is a plotted residential layout at Polepalle Revenue Village, Jadcherla Mandal, Mahabubnagar District, Telangana 509302, developed by registered promoter MD MAZHAR UDDIN. The RERA filing records a site extent of 66,421.74 sq.m and the layout records describe 220 open residential plots; drawing-derived plot sizes range from 123.3 sq.m to 316.97 sq.m. No towers, blocks or floors are disclosed. The project is registered under TG-RERA **P01400010043**, and the promoter’s Form B declaration undertakes completion before **25th May, 2027**.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | NISAA SEZ TOWN |
| Project type | Plotted residential layout; the RERA filing classifies it as a plotted development. RERA record |
| Phase / registered portion | The available record identifies one registered project; no separate phase name or phase-wise scope is disclosed. RERA record |
| TG-RERA registration | P01400010043; registered from 26/05/2025. RERA record |
| Registration validity | The certificate states validity from 26/05/2025 to 25/05/2027, unless extended by the Authority. This is registration validity, not the same as a project completion deadline. |
| Registered promoter | MD MAZHAR UDDIN. RERA record |
| RERA status in supplied record | New Project; RERA registration is recorded. RERA record Approvals record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Polepalli locality; Polepalle Revenue Village. RERA record |
| Mandal / district / PIN | Jadcherla Mandal, Mahabubnagar District, Telangana 509302. RERA record |
| Project survey numbers | 486, 487, 488, 488/AA. RERA record Land records |
| Site extent | The RERA filing records 66,421.74 sq.m. The tentative-layout approval states Ac. 16.412 cents; 79,439.779 Sq.Yds. RERA filing |
| Layout-area figures in filed plan records | The layout-plan record states Total Layout Area 67376.22 sq.mt, Net Area of Plot 66298.18, Balance Area of Plot 66421.22, and Net Layout Area 66421.22; it separately records 955.00 as road-affected/road-widening area. Units for these plan-record entries are as printed in the document extraction. |
| Boundaries in RERA filing | North: 18 Mtr WIDE MAIN ROAD; south: 9 Mtr EXISTING 18 Mtr WIDE PROPOSED ROAD; east: remaining land of Sy. Nos. 486 and 487; west: remaining land of Sy. No. 488. RERA filing |
| Cadastral reference | A Bhu Bharati cadastral record is supplied for survey 486, with a whole-survey extent of 52,242.31 sq.m; this is a survey-level record, not a verified extent of the registered project parcel. Cadastral map |
Development identity
| Field | Project record |
|---|---|
| Principal layout approval | Tentative layout plan approval 487486/LP/GP/205292/0006/2025, dated 26-05-2025, by MUDA Urban Development Authority, delegated to Polepally Grampanchayat. |
| Other layout-plan record | TS-DTCP file TS/012690/2025; the extracted layout-plan record identifies TS-DTCP and the same project survey numbers. |
| Approved built-up area | The plan record states proposed built-up area 0.00 both excluding and including parking. This is a plotted layout; no building area is supplied. |
| Plot count | 220 plots in the tentative-layout approval and the layout-plan record. |
| Buildings / floors / parking levels | No building count, floor configuration, parking level, or building-wise sanctioned arrangement is disclosed in the supplied project record. |
Offering and status
| Field | Project record |
|---|---|
| Offering | Open residential plots. A plot schedule read from the approved layout drawing records 220 plots. Layout record |
| Drawing-derived plot sizes | Software-read plot sizes range from 123.3 sq.m to 316.97 sq.m; median 153.34 sq.m. These are drawing-derived measurements, not RERA-filed unit saleable-area figures. Layout record |
| Booked / available plots | Counts are not disclosed in the supplied evidence. Document index |
| Completion timeline | The RERA Form B declaration undertakes completion before 25th May, 2027. |
| Construction / development stage | RERA status is “New Project”; no independently verified site-progress evidence is supplied. The layout approval requires infrastructure and amenity works and later final-layout approval. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is recorded in the supplied evidence. Document index |
2. The project story
NISAA SEZ TOWN is registered as a plotted residential development at Polepalle Revenue Village, Jadcherla Mandal, Mahabubnagar District. The registered land description covers Survey Nos. 486, 487, 488 and 488/AA. The tentative layout approval and layout-plan record describe 220 plots, with land set aside for plots, roads, open space, utilities and social infrastructure. RERA record
The evidence concerns a layout, not a completed apartment or multi-building scheme. The plan record states proposed built-up area as 0.00; its principal physical components are plot sites and shared layout infrastructure. The RERA Form B is a promoter declaration that the project will be completed before 25th May, 2027. No measured or independently verified construction-progress report is supplied, and no occupancy or completion certificate is included. Document index
The registration certificate records that the promoter must enter into prescribed agreements for sale with allottees and execute and register conveyance deeds as applicable. The supplied allotment-letter document is described as partially filled, with plot and allottee particulars blank; it therefore does not establish an allotment or sale of a specific plot. Document index
3. Master plan, architecture & building design
The approved layout-plan record describes a plotted layout and gives a net layout area of 66421.22 (as printed). It allocates 35301.51 to plotted area (53.15%), 22406.26 to roads (33.73%), 6033.37 to organized open space/park (9.08%), 1889.47 to social infrastructure (2.84%), and 790.08 to utilities (1.19%). The drawing record lists these areas in square metres.
The tentative-layout approval gives a separate land-use schedule: plotted area Ac8.723 cents; 42220.606 Sq.Yds (53.1479%), roads Ac5.537 cents; 26797.887 Sq.Yds (33.7336%), open space Ac1.491 cents; 7215.911 Sq.Yds (9.0835%), utilities Aco. 195cents; 944.936 Sq. Yds (1.1895%), and social infrastructure Ac 0.467 cents; 2259.806 Sq. Yds (2.8447%). These are the approval document’s stated allocations.
The layout-plan record lists road widths of 9.14 MT WIDE EXISTING, 18.28 MT WIDE PROPOSED ROAD, 18.00MT WIDE MAINROAD, 12.00 mt internal road, and 10.05 mt internal road. The RERA-filed boundaries likewise refer to an 18 m main road to the north and an existing 9 m road / proposed 18 m road to the south. RERA filing
The layout drawing’s software-read schedule contains 220 plot entries; the evidence notes that the sum of plot areas matches the plotted area in the drawing’s own area statement. The plan record also identifies 31 mortgage-reserved plot numbers, while the tentative approval describes plots 161 TO 172, 176 TO 194 as mortgaged to the Grampanchayat. Layout record
No buildings, floor plans, building heights, parking levels, or apartment layouts are evidenced. The floor-plan review reports two layout sheets and no flats. Floor plans
4. Homes, configurations & floor plans
This is a plotted development, so apartment configurations and apartment carpet-area measurements are not applicable. The RERA-filed unit-level plot inventory, booked counts and available counts are not provided in the supplied evidence. RERA record Document index
The layout schedule was software-read from the approved drawing; plot sizes should be checked against the drawing before relying on them for a specific purchase. The measured plot-size range is 123.3–316.97 sq.m; the median is 153.34 sq.m. The most frequent printed sizes in the software-read schedule are 153.34 sq.m (91 plots), 168.67 sq.m (23), 138.00 sq.m (23), 151.41 sq.m (12) and 172.35 sq.m (6). These are drawing-based measurements, not RERA-filed saleable-area figures. Layout record
| Plot-size band (sq.yd) | Corresponding band (sq.m) | Plots |
|---|---|---|
| 100–150 | 84–125 | 3 |
| 150–200 | 125–167 | 161 |
| 200–250 | 167–209 | 42 |
| 250–300 | 209–251 | 5 |
| 300–400 | 251–334 | 9 |
5. Parking & vehicle circulation
The evidence does not establish a project-wide parking-space count, visitor or accessible parking provision, or individual plot parking allocation. The layout-plan record reports 0.00 for common parking area. No parking levels, ramps, vehicle-entry arrangements, EV charging provision, or exclusive parking rights are documented.
The plan record provides internal road widths of 12.00 mt and 10.05 mt, as well as the wider road entries listed in the master-plan section. The tentative approval requires roads to be formed and opened for access to neighbouring sites; this is an approval condition, not evidence that the works have been completed.
6. Amenities, recreation & open spaces
| Description / size | Approved tentative-layout schedule: Ac1.491 cents; 7215.911 Sq.Yds (9.0835%). Layout-plan record: 6033.37 (9.08%), as printed in the plan record’s square-metre schedule. |
|---|---|
| Declared progress / verified status | Included in layout records; no completion verification supplied. |
| Description / size | Tentative approval: Ac5.537 cents; 26797.887 Sq.Yds (33.7336%). Layout-plan record: 22406.26 (33.73%), as printed. |
|---|---|
| Declared progress / verified status | Approval requires formation and handover; completion is not independently verified. |
| Description / size | Tentative approval: Ac 0.467 cents; 2259.806 Sq. Yds (2.8447%). Layout-plan record: 1889.47 (2.84%), as printed. |
|---|---|
| Declared progress / verified status | Area is identified; no completed facility or specific building is verified. |
| Description / size | Tentative approval: Aco. 195cents; 944.936 Sq. Yds (1.1895%). Layout-plan record: 790.08 (1.19%), as printed. |
|---|---|
| Declared progress / verified status | Area is identified; utility installations are not verified complete. |
| Description / size | Listed among layout amenities/utilities. |
|---|---|
| Declared progress / verified status | No size or progress evidence supplied. |
| Description / size | Listed in the RERA amenity record without a facility description or size. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0; no completion verification supplied. |
| Description / size | The tentative approval lists pharmacy, clinic, school, play school, creche, dispensary and convenient shops among amenity/utilities terms. |
|---|---|
| Declared progress / verified status | No specific delivered facility or completion status is evidenced. |
The tentative approval requires developed open space, social-infrastructure and utility areas and roads to be transferred to the local authority by registered gift deed before final-layout release. It also requires specified infrastructure works, including road formation, drains, greenery, rainwater-harvesting pits, street lighting, electricity, sewerage disposal and protected water supply. These are approval requirements, not confirmation of completed facilities.
7. Utilities, building services & safety
The RERA amenity record lists water supply, sewerage (chambers, lines, septic tank/STP), storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, street lighting, and an electrical meter room/sub-station/receiving station. The entries show no supplied progress beyond 0 where a percentage is recorded; completion is not independently verified. RERA amenities
The tentative-layout approval specifically requires a protected water-supply system, sewerage-disposal system, storm-water drains and nala channelization, an overhead tank or sump and septic tank as applicable, harvesting pits, street lighting and electricity facilities. It lists a water reservoir, septic tank/STP, electric transformer and solid-waste-management area among utility provisions. No capacities, operating status, test results or completion certificates are supplied.
No evidence is supplied for building fire-safety systems, lifts, backup power, CCTV or access-control arrangements as sanctioned or completed project infrastructure. The approval document’s safety and construction responsibilities are conditions for development, not evidence of compliance or delivery.
8. Location, access & connectivity
The registered location is Polepalle, Jadcherla, Mahabubnagar, Telangana 509302, with Polepalle identified as the revenue village. The project parcel centroid is recorded at 16.816489218308234, 78.12235440853064. RERA record Cadastral map
The filed land boundaries identify an 18 Mtr WIDE MAIN ROAD to the north and a 9 Mtr EXISTING 18 Mtr WIDE PROPOSED ROAD to the south. The layout-plan record lists existing, proposed and internal roads, including 12.00 mt and 10.05 mt internal roads. RERA filing
The available location record gives an approximate distance of 56.4 km to the nearest sampled Outer Ring Road interchange. A separate promoter/vendor claim states approximately 2.4 km from NH 44; this is attributed to the vendor, not an independently verified distance. Location record Promoter website
9. Developer & development status
The TG-RERA certificate identifies MD MAZHAR UDDIN as the registered promoter. The Form B declaration is made by Mohammed Mazhar Uddin and is dated August, 2025; it declares completion before 25th May, 2027. The registration certificate remains valid through 25/05/2027, unless extended. These are distinct dates and statements.
The supplied record does not establish a legal entity type, corporate registration identifier, project-specific official contact details, or a completed works percentage. The layout applicant/developer in the approval records is M/s. NISSA REALTORS; the supplied RERA certificate names MD MAZHAR UDDIN as promoter. Corporate record
The tentative-layout approval requires infrastructure and amenity works within two years from its approval date and requires a work-completion certificate by a Licensed Technical Person for final-layout approval. No such work-completion or final-layout certificate is supplied.
10. Approvals, official records & documents
| Identifier / date | P01400010043; valid 26/05/2025–25/05/2027, unless extended |
|---|---|
| What the supplied evidence establishes | Registers NISAA SEZ TOWN and names MD MAZHAR UDDIN as promoter. |
| Identifier / date | 487486/LP/GP/205292/0006/2025; 26-05-2025 |
|---|---|
| What the supplied evidence establishes | MUDA Urban Development Authority approval, delegated to Polepally Grampanchayat, for a tentative residential plotted layout on Survey Nos. 486, 487, 488 and 488/AA. |
| Identifier / date | TS-DTCP file TS/012690/2025 |
|---|---|
| What the supplied evidence establishes | Plan record identifies the 220-plot layout, area schedule, road widths, utility/open-space/social-infrastructure areas and mortgage-reserved plots. |
| Identifier / date | August, 2025 |
|---|---|
| What the supplied evidence establishes | Promoter declaration on project obligations and completion before 25th May, 2027. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied evidence establishes | No occupancy or completion certificate is established by the reviewed evidence. Document index |
| Identifier / date | Not supplied |
|---|---|
| What the supplied evidence establishes | The tentative approval requires a work-completion certificate and later final-layout approval; neither is included in the supplied records. |
The approval document describes a tentative layout and states that approval is not proof of land title. Its detailed conditions include infrastructure delivery, transfer of specified areas by registered gift deed, and obtaining final-layout approval.
1. Project at a glance
Project identity
Registered project name: NISAA SEZ TOWN
Project type: Plotted residential layout; the RERA filing classifies it as a plotted development.
Phase / registered portion: The available record identifies one registered project; no separate phase name or phase-wise scope is disclosed.
TG-RERA registration: P01400010043; registered from 26/05/2025.
Registration validity: The certificate states validity from 26/05/2025 to 25/05/2027, unless extended by the Authority. This is registration validity, not the same as a project completion deadline.
Registered promoter: MD MAZHAR UDDIN.
RERA status in supplied record: New Project; RERA registration is recorded.
Land and geographic identity
Locality / revenue village: Polepalli locality; Polepalle Revenue Village.
Mandal / district / PIN: Jadcherla Mandal, Mahabubnagar District, Telangana 509302.
Project survey numbers: 486, 487, 488, 488/AA.
Site extent: The RERA filing records 66,421.74 sq.m. The tentative-layout approval states Ac. 16.412 cents; 79,439.779 Sq.Yds.
Layout-area figures in filed plan records: The layout-plan record states Total Layout Area 67376.22 sq.mt, Net Area of Plot 66298.18, Balance Area of Plot 66421.22, and Net Layout Area 66421.22; it separately records 955.00 as road-affected/road-widening area. Units for these plan-record entries are as printed in the document extraction.
Boundaries in RERA filing: North: 18 Mtr WIDE MAIN ROAD; south: 9 Mtr EXISTING 18 Mtr WIDE PROPOSED ROAD; east: remaining land of Sy. Nos. 486 and 487; west: remaining land of Sy. No. 488.
Cadastral reference: A Bhu Bharati cadastral record is supplied for survey 486, with a whole-survey extent of 52,242.31 sq.m; this is a survey-level record, not a verified extent of the registered project parcel.
Development identity
Principal layout approval: Tentative layout plan approval 487486/LP/GP/205292/0006/2025, dated 26-05-2025, by MUDA Urban Development Authority, delegated to Polepally Grampanchayat.
Other layout-plan record: TS-DTCP file TS/012690/2025; the extracted layout-plan record identifies TS-DTCP and the same project survey numbers.
Approved built-up area: The plan record states proposed built-up area 0.00 both excluding and including parking. This is a plotted layout; no building area is supplied.
Plot count: 220 plots in the tentative-layout approval and the layout-plan record.
Buildings / floors / parking levels: No building count, floor configuration, parking level, or building-wise sanctioned arrangement is disclosed in the supplied project record.
Offering and status
Offering: Open residential plots. A plot schedule read from the approved layout drawing records 220 plots.
Drawing-derived plot sizes: Software-read plot sizes range from 123.3 sq.m to 316.97 sq.m; median 153.34 sq.m. These are drawing-derived measurements, not RERA-filed unit saleable-area figures.
Booked / available plots: Counts are not disclosed in the supplied evidence.
Completion timeline: The RERA Form B declaration undertakes completion before 25th May, 2027.
Construction / development stage: RERA status is “New Project”; no independently verified site-progress evidence is supplied. The layout approval requires infrastructure and amenity works and later final-layout approval.
Occupancy / completion certificate: No occupancy or completion certificate is recorded in the supplied evidence.
2. The project story
NISAA SEZ TOWN is registered as a plotted residential development at Polepalle Revenue Village, Jadcherla Mandal, Mahabubnagar District. The registered land description covers Survey Nos. 486, 487, 488 and 488/AA. The tentative layout approval and layout-plan record describe 220 plots, with land set aside for plots, roads, open space, utilities and social infrastructure.
The evidence concerns a layout, not a completed apartment or multi-building scheme. The plan record states proposed built-up area as 0.00; its principal physical components are plot sites and shared layout infrastructure. The RERA Form B is a promoter declaration that the project will be completed before 25th May, 2027. No measured or independently verified construction-progress report is supplied, and no occupancy or completion certificate is included.
The registration certificate records that the promoter must enter into prescribed agreements for sale with allottees and execute and register conveyance deeds as applicable. The supplied allotment-letter document is described as partially filled, with plot and allottee particulars blank; it therefore does not establish an allotment or sale of a specific plot.
3. Master plan, architecture & building design
The approved layout-plan record describes a plotted layout and gives a net layout area of 66421.22 (as printed). It allocates 35301.51 to plotted area (53.15%), 22406.26 to roads (33.73%), 6033.37 to organized open space/park (9.08%), 1889.47 to social infrastructure (2.84%), and 790.08 to utilities (1.19%). The drawing record lists these areas in square metres.
The tentative-layout approval gives a separate land-use schedule: plotted area Ac8.723 cents; 42220.606 Sq.Yds (53.1479%), roads Ac5.537 cents; 26797.887 Sq.Yds (33.7336%), open space Ac1.491 cents; 7215.911 Sq.Yds (9.0835%), utilities Aco. 195cents; 944.936 Sq. Yds (1.1895%), and social infrastructure Ac 0.467 cents; 2259.806 Sq. Yds (2.8447%). These are the approval document’s stated allocations.
The layout-plan record lists road widths of 9.14 MT WIDE EXISTING, 18.28 MT WIDE PROPOSED ROAD, 18.00MT WIDE MAINROAD, 12.00 mt internal road, and 10.05 mt internal road. The RERA-filed boundaries likewise refer to an 18 m main road to the north and an existing 9 m road / proposed 18 m road to the south.
The layout drawing’s software-read schedule contains 220 plot entries; the evidence notes that the sum of plot areas matches the plotted area in the drawing’s own area statement. The plan record also identifies 31 mortgage-reserved plot numbers, while the tentative approval describes plots 161 TO 172, 176 TO 194 as mortgaged to the Grampanchayat.
No buildings, floor plans, building heights, parking levels, or apartment layouts are evidenced. The floor-plan review reports two layout sheets and no flats.
4. Homes, configurations & floor plans
This is a plotted development, so apartment configurations and apartment carpet-area measurements are not applicable. The RERA-filed unit-level plot inventory, booked counts and available counts are not provided in the supplied evidence.
The layout schedule was software-read from the approved drawing; plot sizes should be checked against the drawing before relying on them for a specific purchase. The measured plot-size range is 123.3–316.97 sq.m; the median is 153.34 sq.m. The most frequent printed sizes in the software-read schedule are 153.34 sq.m (91 plots), 168.67 sq.m (23), 138.00 sq.m (23), 151.41 sq.m (12) and 172.35 sq.m (6). These are drawing-based measurements, not RERA-filed saleable-area figures.
| Plot-size band (sq.yd) | Corresponding band (sq.m) | Plots |
|---|---|---|
| 100–150 | 84–125 | 3 |
| 150–200 | 125–167 | 161 |
| 200–250 | 167–209 | 42 |
| 250–300 | 209–251 | 5 |
| 300–400 | 251–334 | 9 |
5. Parking & vehicle circulation
The evidence does not establish a project-wide parking-space count, visitor or accessible parking provision, or individual plot parking allocation. The layout-plan record reports 0.00 for common parking area. No parking levels, ramps, vehicle-entry arrangements, EV charging provision, or exclusive parking rights are documented.
The plan record provides internal road widths of 12.00 mt and 10.05 mt, as well as the wider road entries listed in the master-plan section. The tentative approval requires roads to be formed and opened for access to neighbouring sites; this is an approval condition, not evidence that the works have been completed.
6. Amenities, recreation & open spaces
| Description / size | Approved tentative-layout schedule: Ac1.491 cents; 7215.911 Sq.Yds (9.0835%). Layout-plan record: 6033.37 (9.08%), as printed in the plan record’s square-metre schedule. |
|---|---|
| Declared progress / verified status | Included in layout records; no completion verification supplied. |
| Description / size | Tentative approval: Ac5.537 cents; 26797.887 Sq.Yds (33.7336%). Layout-plan record: 22406.26 (33.73%), as printed. |
|---|---|
| Declared progress / verified status | Approval requires formation and handover; completion is not independently verified. |
| Description / size | Tentative approval: Ac 0.467 cents; 2259.806 Sq. Yds (2.8447%). Layout-plan record: 1889.47 (2.84%), as printed. |
|---|---|
| Declared progress / verified status | Area is identified; no completed facility or specific building is verified. |
| Description / size | Tentative approval: Aco. 195cents; 944.936 Sq. Yds (1.1895%). Layout-plan record: 790.08 (1.19%), as printed. |
|---|---|
| Declared progress / verified status | Area is identified; utility installations are not verified complete. |
| Description / size | Listed among layout amenities/utilities. |
|---|---|
| Declared progress / verified status | No size or progress evidence supplied. |
| Description / size | Listed in the RERA amenity record without a facility description or size. |
|---|---|
| Declared progress / verified status | Progress recorded as 0; no completion verification supplied. |
| Description / size | The tentative approval lists pharmacy, clinic, school, play school, creche, dispensary and convenient shops among amenity/utilities terms. |
|---|---|
| Declared progress / verified status | No specific delivered facility or completion status is evidenced. |
The tentative approval requires developed open space, social-infrastructure and utility areas and roads to be transferred to the local authority by registered gift deed before final-layout release. It also requires specified infrastructure works, including road formation, drains, greenery, rainwater-harvesting pits, street lighting, electricity, sewerage disposal and protected water supply. These are approval requirements, not confirmation of completed facilities.
7. Utilities, building services & safety
The RERA amenity record lists water supply, sewerage (chambers, lines, septic tank/STP), storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, street lighting, and an electrical meter room/sub-station/receiving station. The entries show no supplied progress beyond 0 where a percentage is recorded; completion is not independently verified.
The tentative-layout approval specifically requires a protected water-supply system, sewerage-disposal system, storm-water drains and nala channelization, an overhead tank or sump and septic tank as applicable, harvesting pits, street lighting and electricity facilities. It lists a water reservoir, septic tank/STP, electric transformer and solid-waste-management area among utility provisions. No capacities, operating status, test results or completion certificates are supplied.
No evidence is supplied for building fire-safety systems, lifts, backup power, CCTV or access-control arrangements as sanctioned or completed project infrastructure. The approval document’s safety and construction responsibilities are conditions for development, not evidence of compliance or delivery.
8. Location, access & connectivity
The registered location is Polepalle, Jadcherla, Mahabubnagar, Telangana 509302, with Polepalle identified as the revenue village. The project parcel centroid is recorded at 16.816489218308234, 78.12235440853064.
The filed land boundaries identify an 18 Mtr WIDE MAIN ROAD to the north and a 9 Mtr EXISTING 18 Mtr WIDE PROPOSED ROAD to the south. The layout-plan record lists existing, proposed and internal roads, including 12.00 mt and 10.05 mt internal roads.
The available location record gives an approximate distance of 56.4 km to the nearest sampled Outer Ring Road interchange. A separate promoter/vendor claim states approximately 2.4 km from NH 44; this is attributed to the vendor, not an independently verified distance.
9. Developer & development status
The TG-RERA certificate identifies MD MAZHAR UDDIN as the registered promoter. The Form B declaration is made by Mohammed Mazhar Uddin and is dated August, 2025; it declares completion before 25th May, 2027. The registration certificate remains valid through 25/05/2027, unless extended. These are distinct dates and statements.
The supplied record does not establish a legal entity type, corporate registration identifier, project-specific official contact details, or a completed works percentage. The layout applicant/developer in the approval records is M/s. NISSA REALTORS; the supplied RERA certificate names MD MAZHAR UDDIN as promoter.
The tentative-layout approval requires infrastructure and amenity works within two years from its approval date and requires a work-completion certificate by a Licensed Technical Person for final-layout approval. No such work-completion or final-layout certificate is supplied.
10. Approvals, official records & documents
| Identifier / date | P01400010043; valid 26/05/2025–25/05/2027, unless extended |
|---|---|
| What the supplied evidence establishes | Registers NISAA SEZ TOWN and names MD MAZHAR UDDIN as promoter. |
| Identifier / date | 487486/LP/GP/205292/0006/2025; 26-05-2025 |
|---|---|
| What the supplied evidence establishes | MUDA Urban Development Authority approval, delegated to Polepally Grampanchayat, for a tentative residential plotted layout on Survey Nos. 486, 487, 488 and 488/AA. |
| Identifier / date | TS-DTCP file TS/012690/2025 |
|---|---|
| What the supplied evidence establishes | Plan record identifies the 220-plot layout, area schedule, road widths, utility/open-space/social-infrastructure areas and mortgage-reserved plots. |
| Identifier / date | August, 2025 |
|---|---|
| What the supplied evidence establishes | Promoter declaration on project obligations and completion before 25th May, 2027. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied evidence establishes | No occupancy or completion certificate is established by the reviewed evidence. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied evidence establishes | The tentative approval requires a work-completion certificate and later final-layout approval; neither is included in the supplied records. |
The approval document describes a tentative layout and states that approval is not proof of land title. Its detailed conditions include infrastructure delivery, transfer of specified areas by registered gift deed, and obtaining final-layout approval.
Frequently asked questions
Is NISAA SEZ TOWN registered with Telangana RERA?
Yes. NISAA SEZ TOWN is registered with the Telangana Real Estate Regulatory Authority as P01400010043; the registration status is New Project.
Who is the developer of NISAA SEZ TOWN?
The promoter named in the RERA registration is MD MAZHAR UDDIN.
Where is NISAA SEZ TOWN located?
NISAA SEZ TOWN is in Polepalli, Polepalle, Jadcherla, Mahabubnagar, Telangana (509302).
When will NISAA SEZ TOWN be completed?
The promoter's proposed date of completion filed with RERA is 25/09/2027. This is the promoter's declaration, not a guarantee.