Hari Durga Homes
LAHOTI CONSTRUCTIONS · Karimnagar · RERA P02700002669
HARI DURGA HOMES is a residential apartment project in Chaitanyapuri, Karimnagar, Karimnagar district; the mandal is not disclosed in the supplied project record. The registered promoter is LAHOTI CONSTRUCTIONS. The project covers 546.72 m² and comprises one building with 1 Stilt + 5 upper floors and 10 3BHK units, filed as “TRIPLE BEDROOM,” each with a saleable area of 141.38 m². Its TG-RERA registration is P02700002669, and the proposed completion date recorded in the project information is 30/11/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | HARI DURGA HOMES RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | Phase not separately identified; the registration covers the project recorded for Survey No. 1246/A Land records |
| TG-RERA registration | P02700002669; registration certificate issued 06/03/2021, valid from 06/03/2021 to 11/03/2026; no extension is recorded in the supplied certificate Approvals record |
| Registered promoter | LAHOTI CONSTRUCTIONS RERA record Corporate record |
| RERA status | The supplied record identifies it as a “New Project”; the certificate records a five-year registration period ending 11/03/2026. Current registration status is not established by the supplied records. RERA filing |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Chaitanyapuri, Karimnagar; the building-permit record identifies the site as Chaitanyapuri_W48. |
| Revenue village | Not disclosed in the supplied project record. Land records |
| Mandal | Not disclosed in the supplied project record. Land records |
| District / PIN | Karimnagar / 505001 RERA record |
| Project survey number(s) and subdivision(s) | Survey No. 1246/A Land records |
| Registered site extent | 546.72 m²; the RERA land details record total area and net area as 546.72 m². RERA filing |
| Boundaries recorded | East: 9M WIDE ROAD; West: EXISTING BUUILDING; North: EXISTING BUILDING; South: VACANT LAND RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Karimnagar Municipal Corporation, as identified in the filed building-permit order |
| Principal building approval | 3011/W48/2019/5600, approved 11 March, 2020 Approvals record |
| Approved built-up area | RERA project information records 1,676.91 m² as “Approved Built up Area”; the building-permit order separately lists 1,385.45 m² for five residential upper floors and 263.64 m² for the stilt parking level. RERA filing |
| Building count | One building/unit is recorded in the RERA land details. RERA filing |
| Sanctioned configuration | 1 Stilt + 5 upper floors; building height 14.95 m. |
| Parking level | One stilt parking level is shown in the sanction; its listed area is 263.64 m². |
| Unit count | 10 units are recorded in the RERA unit data. The sanction describes a tenements/flats building. RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| Unit type | 3BHK, filed as “TRIPLE BEDROOM” RERA unit table |
| RERA-filed saleable area | 141.38 m² per unit RERA unit table RERA unit details |
| Booked / available | 0 booked and 10 available in the portal data supplied; the portal record has no as-of date, so these counts are indicative. RERA unit table RERA unit details |
| Construction stage | No independently verified or dated construction-progress evidence is supplied. The RERA amenity record lists progress as 0% for its listed items. RERA amenities |
| Completion undertaking | Promoter’s Form B declares completion by 11/03/2026; the RERA project information separately records a proposed completion date of 30/11/2026. These are recorded as separate filed/declared fields, not as verified completion. RERA filing |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The building-permit order says an occupancy certificate is required before occupation. Document index |
2. The project story
HARI DURGA HOMES is recorded with TG-RERA as a residential apartment project in Chaitanyapuri, Karimnagar, on Survey No. 1246/A. The site is recorded as 546.72 m² and is bounded on the east by a 9M WIDE ROAD. The revenue village and mandal are not disclosed in the supplied project record. RERA record Land records
The filed building permit sanctions one residential building with a stilt parking level and five upper floors. The RERA unit record lists ten 3BHK units, filed as “TRIPLE BEDROOM,” each with a saleable area of 141.38 m². Portal counts show all ten as available and none booked, but the portal record has no as-of date. RERA unit table RERA unit details
The supplied evidence does not establish the project’s current construction stage or independently verify progress on site. The RERA amenity record reports 0% progress for its listed items. No occupancy or completion certificate is included; the building-permit order requires an occupancy certificate before occupation. RERA amenities Document index
3. Master plan, architecture & building design
The filed building-permit order identifies a 546.72 m² site and sanctions a single residential building configured as 1 Stilt + 5 upper floors, with a stated height of 14.95 m. It records 1,385.45 m² for the five residential upper floors and 263.64 m² for the stilt parking level. The RERA project fields separately label 1,676.91 m² as approved built-up area; these figures retain their respective source labels and are not treated as interchangeable measurements. RERA filing
The building permit records setbacks of Front 3, Rear 2.5, Side I 3.5 and Side II 4.5. It lists six rainwater-harvesting pits and requires a tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate; the permit’s stated tot-lot area is “NA.”
The available evidence does not establish the floor-by-floor flat arrangement, flats per floor, lift or stair configuration, building footprint, internal circulation, or residential/common-area distribution. The project’s sanctioned drawing is identified as document 149436, but it is not extracted as a complete architectural plan in the supplied records. Document index
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK (“TRIPLE BEDROOM” in the RERA filing) | 10 | 0 | 10 | 141.38 m² | 99.7–103.9 m²; median 101.8 m² | 28% |
RERA unit counts, booking status and saleable area are filing data; the booked/available figures are indicative because the portal data has no as-of date. Carpet-area figures are software measurements from approved floor-plan drawing geometry, not RERA-filed measurements, and are marked as needing review. The supplied drawing record reports four measured 3BHK designs. RERA unit table RERA unit details Floor plans
The measured drawing for flat “02” labels three bedrooms, a hall, a kitchen, three toilets and two balconies. One balcony is recorded with dimensions of 1.67 m × 1.13 m and an area of 1.89 m²; balcony areas are excluded from the supplied carpet measurement. Room dimensions and areas are drawing-derived measurements, not RERA disclosures. RERA unit details
Saleable area is the RERA-filed figure; measured carpet area is a separate drawing-based figure. The supplied evidence does not provide a RERA-filed room schedule or a verified unit-specific common-area allocation. RERA unit details Floor plans
5. Parking & vehicle circulation
The sanctioned plan includes one stilt parking level with an area of 263.64 m² and states that the stilt approved for parking is to be used exclusively for vehicle parking, without partition walls or rolling shutters. The building-permit order does not state a parking-space count.
The supplied vendor record lists “10 Covered Parking spaces,” but this is a vendor claim rather than a count established by the filed building-permit data. No unit-specific parking allocation, visitor or accessible parking count, ramp arrangement, driveway plan, or pedestrian/vehicle separation details are established by the supplied evidence. Promoter website
6. Amenities, recreation & open spaces
The TG-RERA amenity record lists the following project provisions. Each listed item has reported progress of 0%; the supplied data does not independently verify completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Permit records tot-lot area as “NA” and requires it to be fenced and maintained as greenery before occupancy certificate. | RERA amenities | RERA record: 0%; not independently verified |
| Internal roads & footpaths | Listed as available in the RERA amenity record; no dimensions supplied. | RERA amenities | 0%; not independently verified |
| Community buildings | Listed; no description or size supplied. | RERA amenities | 0%; not independently verified |
| Water conservation / rainwater harvesting | Amenity record lists rainwater harvesting; permit specifies six rainwater-harvesting pits. | RERA amenities | 0%; not independently verified |
| Water supply | Listed; source, capacity and delivery status not supplied. | RERA amenities | 0%; not independently verified |
| Sewerage and sewage/sullage treatment and disposal | Sewerage (chambers, lines, septic tank, STP) and treatment/disposal are listed; system details are not supplied. | RERA amenities | 0%; not independently verified |
| Storm-water drains | Listed; no design or capacity supplied. | RERA amenities | 0%; not independently verified |
| Street lighting | Listed; no specification supplied. | RERA amenities | 0%; not independently verified |
| Solid-waste management and disposal | Listed; no system details supplied. | RERA amenities | 0%; not independently verified |
| Energy management | Listed; no system details supplied. | RERA amenities | 0%; not independently verified |
| Fire protection and fire-safety requirements | Listed; no system details supplied. | RERA amenities | 0%; not independently verified |
| Electrical meter room / sub-station / receiving station | Listed; the permit also requires space for a transformer. | RERA amenities | 0%; not independently verified |
| Recreational open space | Aggregate area listed without a supplied measurement. | RERA amenities | 0%; not independently verified |
The vendor record also lists backup electricity, CCTV, compound, lift, security personnel and waste disposal; these are vendor-listed claims and are not established in the supplied sanctioned-plan extraction as completed facilities. Promoter website
7. Utilities, building services & safety
The RERA amenity record lists water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, rainwater harvesting, energy management, electrical infrastructure, fire protection, solid-waste management and street lighting. Its listed progress entries are 0%; capacities, detailed designs and independently verified completion are not supplied. RERA amenities
The building-permit order requires construction of a rainwater-harvesting structure, provision of transformer space, and a garbage house within the premises. It also requires the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate, and states that an occupancy certificate is compulsory before occupation. These are permit conditions, not evidence that the facilities have been completed.
The supplied records do not establish water source or storage capacity, an STP’s capacity or reuse arrangements, electrical backup capacity, lift number or capacity, fire-system specifications, CCTV or access-control installation, accessibility features, or verified site completion of any utility or safety system. RERA amenities Promoter website Document index
8. Location, access & connectivity
The project is recorded in Chaitanyapuri, Karimnagar, Telangana, PIN 505001. The building-permit record identifies the site as Chaitanyapuri_W48; the project’s revenue village and mandal are not disclosed in the supplied RERA land details. RERA record Land records
The recorded eastern boundary is a 9M WIDE ROAD. The supplied location data gives a “Financial District (Nanakramguda)” anchor at 1.2 km; the data does not establish the route, measurement method or travel time, so this is reported only as the supplied location-record distance. RERA filing Location record
No further approach-road, public-transport or landmark details are established in the supplied project records. Location record
9. Developer & development status
The registered promoter is LAHOTI CONSTRUCTIONS, recorded as a proprietorship. The promoter address supplied in the project record is Lahoti Nilayam, Jafri Road, Chaitanyapuri, Karimnagar, Karimnagar district, PIN 505001. VINOD KUMAR LAHOTI is recorded as the authorized signatory; the Form B declaration identifies VINOD LAHOTI as promoter and LAHOTI CONSTRUCTIONS as proprietor. Corporate record Parties record
The Form B affidavit dated 21 January 2021 declares that the project land is free from encumbrances, sets out the promoter’s separate-account and audit undertakings, and states a completion undertaking of 11/03/2026. The RERA project information separately records a proposed completion date of 30/11/2026. Neither date establishes actual completion. RERA filing
The supplied records identify one building and do not establish a separate phase-wise construction schedule or independently verified construction progress. RERA filing RERA amenities
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for HARI DURGA HOMES, registration P02700002669; issued 06/03/2021 and valid through 11/03/2026, subject to its stated conditions. |
| Building permit / principal sanction | Karimnagar Municipal Corporation building-permit order 3011/W48/2019/5600, approved 11 March, 2020; sanctions 1 Stilt + 5 upper floors. |
| Registered project land identity | Survey No. 1246/A; site area 546.72 m²; PIN 505001. Revenue village and mandal are not disclosed in the supplied project record. Land records |
| Approved drawing record | Drawing document 149436 is identified in the project records; the supplied evidence does not provide a complete extracted architectural-plan description. Document index |
| Form B declaration | Promoter declaration dated 21 January 2021, including declared completion date and project-fund, audit and approval undertakings. |
| Occupancy / completion certificate | No such certificate is included in the supplied project documents. The building-permit order specifies that an occupancy certificate is required before occupation. Document index |
| Other approval identifiers on the building-permit order | Layout / Sub Divn. Nos. G2/2584/48/2015/KNR and G2/2587/48/2015/KNR; S.R.O. Karimnagar reference 14552/19 dated 27 December, 2019. |
1. Project at a glance
Project identity
Registered project name: HARI DURGA HOMES
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified; the registration covers the project recorded for Survey No. 1246/A
TG-RERA registration: P02700002669; registration certificate issued 06/03/2021, valid from 06/03/2021 to 11/03/2026; no extension is recorded in the supplied certificate
Registered promoter: LAHOTI CONSTRUCTIONS
RERA status: The supplied record identifies it as a “New Project”; the certificate records a five-year registration period ending 11/03/2026. Current registration status is not established by the supplied records.
Land and geographic identity
Locality: Chaitanyapuri, Karimnagar; the building-permit record identifies the site as Chaitanyapuri_W48.
Revenue village: Not disclosed in the supplied project record.
Mandal: Not disclosed in the supplied project record.
District / PIN: Karimnagar / 505001
Project survey number(s) and subdivision(s): Survey No. 1246/A
Registered site extent: 546.72 m²; the RERA land details record total area and net area as 546.72 m².
Boundaries recorded: East: 9M WIDE ROAD; West: EXISTING BUUILDING; North: EXISTING BUILDING; South: VACANT LAND
Development identity
Sanctioning authority: Karimnagar Municipal Corporation, as identified in the filed building-permit order
Principal building approval: 3011/W48/2019/5600, approved 11 March, 2020
Approved built-up area: RERA project information records 1,676.91 m² as “Approved Built up Area”; the building-permit order separately lists 1,385.45 m² for five residential upper floors and 263.64 m² for the stilt parking level.
Building count: One building/unit is recorded in the RERA land details.
Sanctioned configuration: 1 Stilt + 5 upper floors; building height 14.95 m.
Parking level: One stilt parking level is shown in the sanction; its listed area is 263.64 m².
Unit count: 10 units are recorded in the RERA unit data. The sanction describes a tenements/flats building.
Offering and status
Unit type: 3BHK, filed as “TRIPLE BEDROOM”
RERA-filed saleable area: 141.38 m² per unit
Booked / available: 0 booked and 10 available in the portal data supplied; the portal record has no as-of date, so these counts are indicative.
Construction stage: No independently verified or dated construction-progress evidence is supplied. The RERA amenity record lists progress as 0% for its listed items.
Completion undertaking: Promoter’s Form B declares completion by 11/03/2026; the RERA project information separately records a proposed completion date of 30/11/2026. These are recorded as separate filed/declared fields, not as verified completion.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The building-permit order says an occupancy certificate is required before occupation.
2. The project story
HARI DURGA HOMES is recorded with TG-RERA as a residential apartment project in Chaitanyapuri, Karimnagar, on Survey No. 1246/A. The site is recorded as 546.72 m² and is bounded on the east by a 9M WIDE ROAD. The revenue village and mandal are not disclosed in the supplied project record.
The filed building permit sanctions one residential building with a stilt parking level and five upper floors. The RERA unit record lists ten 3BHK units, filed as “TRIPLE BEDROOM,” each with a saleable area of 141.38 m². Portal counts show all ten as available and none booked, but the portal record has no as-of date.
The supplied evidence does not establish the project’s current construction stage or independently verify progress on site. The RERA amenity record reports 0% progress for its listed items. No occupancy or completion certificate is included; the building-permit order requires an occupancy certificate before occupation.
3. Master plan, architecture & building design
The filed building-permit order identifies a 546.72 m² site and sanctions a single residential building configured as 1 Stilt + 5 upper floors, with a stated height of 14.95 m. It records 1,385.45 m² for the five residential upper floors and 263.64 m² for the stilt parking level. The RERA project fields separately label 1,676.91 m² as approved built-up area; these figures retain their respective source labels and are not treated as interchangeable measurements.
The building permit records setbacks of Front 3, Rear 2.5, Side I 3.5 and Side II 4.5. It lists six rainwater-harvesting pits and requires a tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate; the permit’s stated tot-lot area is “NA.”
The available evidence does not establish the floor-by-floor flat arrangement, flats per floor, lift or stair configuration, building footprint, internal circulation, or residential/common-area distribution. The project’s sanctioned drawing is identified as document 149436, but it is not extracted as a complete architectural plan in the supplied records.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK (“TRIPLE BEDROOM” in the RERA filing) | 10 | 0 | 10 | 141.38 m² | 99.7–103.9 m²; median 101.8 m² | 28% |
RERA unit counts, booking status and saleable area are filing data; the booked/available figures are indicative because the portal data has no as-of date. Carpet-area figures are software measurements from approved floor-plan drawing geometry, not RERA-filed measurements, and are marked as needing review. The supplied drawing record reports four measured 3BHK designs.
The measured drawing for flat “02” labels three bedrooms, a hall, a kitchen, three toilets and two balconies. One balcony is recorded with dimensions of 1.67 m × 1.13 m and an area of 1.89 m²; balcony areas are excluded from the supplied carpet measurement. Room dimensions and areas are drawing-derived measurements, not RERA disclosures.
Saleable area is the RERA-filed figure; measured carpet area is a separate drawing-based figure. The supplied evidence does not provide a RERA-filed room schedule or a verified unit-specific common-area allocation.
5. Parking & vehicle circulation
The sanctioned plan includes one stilt parking level with an area of 263.64 m² and states that the stilt approved for parking is to be used exclusively for vehicle parking, without partition walls or rolling shutters. The building-permit order does not state a parking-space count.
The supplied vendor record lists “10 Covered Parking spaces,” but this is a vendor claim rather than a count established by the filed building-permit data. No unit-specific parking allocation, visitor or accessible parking count, ramp arrangement, driveway plan, or pedestrian/vehicle separation details are established by the supplied evidence.
6. Amenities, recreation & open spaces
The TG-RERA amenity record lists the following project provisions. Each listed item has reported progress of 0%; the supplied data does not independently verify completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Permit records tot-lot area as “NA” and requires it to be fenced and maintained as greenery before occupancy certificate. | RERA record: 0%; not independently verified | |
| Internal roads & footpaths | Listed as available in the RERA amenity record; no dimensions supplied. | 0%; not independently verified | |
| Community buildings | Listed; no description or size supplied. | 0%; not independently verified | |
| Water conservation / rainwater harvesting | Amenity record lists rainwater harvesting; permit specifies six rainwater-harvesting pits. | 0%; not independently verified | |
| Water supply | Listed; source, capacity and delivery status not supplied. | 0%; not independently verified | |
| Sewerage and sewage/sullage treatment and disposal | Sewerage (chambers, lines, septic tank, STP) and treatment/disposal are listed; system details are not supplied. | 0%; not independently verified | |
| Storm-water drains | Listed; no design or capacity supplied. | 0%; not independently verified | |
| Street lighting | Listed; no specification supplied. | 0%; not independently verified | |
| Solid-waste management and disposal | Listed; no system details supplied. | 0%; not independently verified | |
| Energy management | Listed; no system details supplied. | 0%; not independently verified | |
| Fire protection and fire-safety requirements | Listed; no system details supplied. | 0%; not independently verified | |
| Electrical meter room / sub-station / receiving station | Listed; the permit also requires space for a transformer. | 0%; not independently verified | |
| Recreational open space | Aggregate area listed without a supplied measurement. | 0%; not independently verified |
The vendor record also lists backup electricity, CCTV, compound, lift, security personnel and waste disposal; these are vendor-listed claims and are not established in the supplied sanctioned-plan extraction as completed facilities.
7. Utilities, building services & safety
The RERA amenity record lists water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, rainwater harvesting, energy management, electrical infrastructure, fire protection, solid-waste management and street lighting. Its listed progress entries are 0%; capacities, detailed designs and independently verified completion are not supplied.
The building-permit order requires construction of a rainwater-harvesting structure, provision of transformer space, and a garbage house within the premises. It also requires the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate, and states that an occupancy certificate is compulsory before occupation. These are permit conditions, not evidence that the facilities have been completed.
The supplied records do not establish water source or storage capacity, an STP’s capacity or reuse arrangements, electrical backup capacity, lift number or capacity, fire-system specifications, CCTV or access-control installation, accessibility features, or verified site completion of any utility or safety system.
8. Location, access & connectivity
The project is recorded in Chaitanyapuri, Karimnagar, Telangana, PIN 505001. The building-permit record identifies the site as Chaitanyapuri_W48; the project’s revenue village and mandal are not disclosed in the supplied RERA land details.
The recorded eastern boundary is a 9M WIDE ROAD. The supplied location data gives a “Financial District (Nanakramguda)” anchor at 1.2 km; the data does not establish the route, measurement method or travel time, so this is reported only as the supplied location-record distance.
No further approach-road, public-transport or landmark details are established in the supplied project records.
9. Developer & development status
The registered promoter is LAHOTI CONSTRUCTIONS, recorded as a proprietorship. The promoter address supplied in the project record is Lahoti Nilayam, Jafri Road, Chaitanyapuri, Karimnagar, Karimnagar district, PIN 505001. VINOD KUMAR LAHOTI is recorded as the authorized signatory; the Form B declaration identifies VINOD LAHOTI as promoter and LAHOTI CONSTRUCTIONS as proprietor.
The Form B affidavit dated 21 January 2021 declares that the project land is free from encumbrances, sets out the promoter’s separate-account and audit undertakings, and states a completion undertaking of 11/03/2026. The RERA project information separately records a proposed completion date of 30/11/2026. Neither date establishes actual completion.
The supplied records identify one building and do not establish a separate phase-wise construction schedule or independently verified construction progress.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for HARI DURGA HOMES, registration P02700002669; issued 06/03/2021 and valid through 11/03/2026, subject to its stated conditions.
Building permit / principal sanction: Karimnagar Municipal Corporation building-permit order 3011/W48/2019/5600, approved 11 March, 2020; sanctions 1 Stilt + 5 upper floors.
Registered project land identity: Survey No. 1246/A; site area 546.72 m²; PIN 505001. Revenue village and mandal are not disclosed in the supplied project record.
Approved drawing record: Drawing document 149436 is identified in the project records; the supplied evidence does not provide a complete extracted architectural-plan description.
Form B declaration: Promoter declaration dated 21 January 2021, including declared completion date and project-fund, audit and approval undertakings.
Occupancy / completion certificate: No such certificate is included in the supplied project documents. The building-permit order specifies that an occupancy certificate is required before occupation.
Other approval identifiers on the building-permit order: Layout / Sub Divn. Nos. G2/2584/48/2015/KNR and G2/2587/48/2015/KNR; S.R.O. Karimnagar reference 14552/19 dated 27 December, 2019.
Frequently asked questions
Is HARI DURGA HOMES registered with Telangana RERA?
Yes. HARI DURGA HOMES is registered with the Telangana Real Estate Regulatory Authority as P02700002669; the registration status is New Project.
Who is the developer of HARI DURGA HOMES?
The promoter named in the RERA registration is LAHOTI CONSTRUCTIONS.
Where is HARI DURGA HOMES located?
HARI DURGA HOMES is in KARIMNAGAR, Telangana (505001).
When will HARI DURGA HOMES be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.
More projects in Karimnagar