Vijetha Seethu Residency
M/S SEETHU BUILDERS · Karimnagar · RERA P02700002112
VIJETHA SEETHU RESIDENCY is a residential apartment project in Bhagath Nagar, Karimnagar urban mandal, Karimnagar district. The registered promoter developing it is M/S SEETHU BUILDERS. The project occupies 690.45 sq.m. and comprises one detached residential building with 1 Stilt + 5 upper floors and 10 2BHK apartments, each with a RERA-filed saleable area of 155.15 sq.m. Its TG-RERA registration is P02700002112, and its proposed completion date is 02/11/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | VIJETHA SEETHU RESIDENCY RERA record |
| Project type / registered portion | Residential apartment project; the record identifies one building, but does not separately state a phase name. RERA record RERA filing |
| TG-RERA registration | P02700002112, granted under section 5; issued 24/08/2020. RERA record |
| Registration validity | Certificate states five years from 24/08/2020, ending 02/11/2025; no extension is recorded in the supplied certificate. Registration validity is distinct from the stated project completion date. RERA record |
| Registered promoter | M/S SEETHU BUILDERS, identified as a partnership. RERA filing Corporate record |
| RERA status in supplied record | The portal registration data was captured on 10 September 2026; the supplied certificate records validity through 02/11/2025 and says extension is not recorded. RERA record Approvals record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality | Bhagath Nagar / BHAGATH NAGAR; the building-permit description also identifies Ramnagar area, Bhagathnagar locality. RERA record RERA filing |
| Revenue village | Bhagath Nagar. The permit extract separately describes the site as Ward 31 / Mukarampura (Part)_W31; a revenue village for that permit description is not otherwise supplied. RERA record Land records |
| Mandal | Not disclosed in the project land identity; the registration certificate states Karimnagar urban. Land records |
| District / PIN | Karimnagar / 505001. RERA record |
| Project survey number(s) | 979/A. No subdivision beyond “/A” is supplied. RERA record Land records |
| Plots | 16, 17. RERA filing |
| Site extent | 690.45 sq.m. total area and 690.45 sq.m. net area; the permit extract records road-affected area as 0 sq.m. RERA filing |
| Boundaries | East: 9M WIDE EXISTING ROAD; West: HOUSE OF M MADHAVIOF H NO 9-1-193 2; North: HOUSE OF SURENDER REDDY H NO 9-1-202 1; South: HOUSE OF B SHOBHARANI H NO 9-1-211. RERA filing Land records |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Karimnagar Municipal Corporation. The project filing also identifies DTCP as authority for the plan approval. Approvals record |
| Principal approval | Building permit / approval 3011/W31/2019/5160, dated 02 November, 2019. Approvals record |
| Approved built-up area | 1,685.65 m² residential upper-floor area; the permit separately records 320.90 m² stilt area. RERA filing |
| Building count and floors | One detached residential building: 1 Stilt + 5 upper floors; permit-recorded height 14.26 m. RERA record |
| Parking level / provision | The permit condition says the approved stilt is to be used exclusively for vehicle parking. A total parking-space count is not supplied. |
| Unit counts | 10 units in the RERA filing; the project information records 1 building unit, while the approved plan extract does not state a unit count. RERA unit table RERA filing |
Offering and status
| Field | Record |
|---|---|
| Configuration | 2BHK apartments. RERA unit table RERA unit details |
| RERA-filed saleable area | 155.15 sq.m. per unit. RERA unit table RERA unit details |
| Booked / available | 0 booked; 10 available, as last read from the TG-RERA portal; no as-of date accompanies the unit counts, so they are indicative. RERA unit table |
| Construction stage | No independently verified site-progress evidence or construction-stage percentage is supplied. The TG-RERA amenity schedule shows 0% progress for the listed works. RERA amenities |
| Completion date | Promoter-declared proposed completion date: 02/11/2025. This is separate from registration validity. RERA record RERA filing |
| OC / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The building-permit order says an occupancy certificate is compulsory before occupation. Document index |
2. The project story
VIJETHA SEETHU RESIDENCY is registered as a residential apartment project on survey 979/A, plots 16, 17, in Bhagath Nagar, Karimnagar. The RERA record describes a single building and lists ten 2BHK apartments. The sanctioned building-permit extract describes a detached residential building with one stilt level and five upper floors. RERA record Land records RERA unit table
The filed RERA unit record lists all ten apartments as available and none as booked, but its booking snapshot is undated. The proposed completion date recorded by the promoter is 02/11/2025. The supplied evidence does not establish the current physical construction stage, independently verify completion, or include an occupancy certificate; these should not be inferred from the proposed date or from the registration certificate. RERA unit table RERA record RERA amenities Document index
3. Master plan, architecture & building design
The site extent in the land and permit records is 690.45 sq.m.; the RERA filing records the same figure as total and net area. The building permit describes a detached residential building, 1 Stilt + 5 upper floors, with a permit-recorded height of 14.26 m. It records residential upper-floor area of 1,685.65 m² and stilt area of 320.90 m²; these are distinct permit figures, not carpet or saleable area. Land records RERA filing
The permit extract lists 174.83 m² as the second-floor area and identifies that same area as the mortgage area in the RERA filing. The supplied drawing record contains two sheets, but neither is measured for unit layouts; details such as flats per floor, lift and stair arrangements, building footprint, internal circulation, open-space arrangement and floor-by-floor apartment distribution are therefore not established here. RERA filing Floor plans
The RERA filing gives a single building unit, while the permit extract establishes the approved building form and floors; it does not supply a floor-by-floor unit schedule in the available extraction. The permit requires construction to follow the sanctioned plan and prior approval for modifications. RERA filing
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 155.15 sq.m. | Not measured from the supplied drawings | Not supplied |
The saleable area is the area reported in the TG-RERA filing. The floor-plan record says the drawings have not been measured; accordingly, no software-measured carpet area, room dimensions or balcony/utility measurements can be reported. Carpet area, if later measured, would not be interchangeable with saleable area, which includes the unit’s share of common areas. RERA unit details RERA unit table Floor plans
5. Parking & vehicle circulation
The building permit states that the approved stilt is to be used exclusively for vehicle parking. The permit extract also records a 320.90 m² stilt area, but provides no number of car or two-wheeler spaces, visitor or accessible spaces, or parking-allocation schedule. No separate basement, podium, mechanical parking, ramp or internal-driveway details are established by the supplied evidence.
The permit requires the stilt to be used for parking; this does not by itself establish exclusive parking ownership or an allocation to any particular apartment. No unit-specific parking allocation is supplied. Document index
6. Amenities, recreation & open spaces
The TG-RERA amenity schedule records the following project works. Listed progress is 0% for every item; the schedule does not establish independent completion or verification. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | Size not stated | TG-RERA amenity schedule RERA amenities | 0%; not independently verified |
| Green strip / TOT LOT / park | Size and quantity not stated | TG-RERA amenity schedule RERA amenities | 0%; not independently verified |
| Community buildings | Details not stated | TG-RERA amenity schedule RERA amenities | 0%; not independently verified |
| Aggregate recreational open space | Area not stated | TG-RERA amenity schedule RERA amenities | 0%; not independently verified |
The permit also lists a garbage house as a site provision; no size or delivery status is supplied. The vendor’s amenity list is not used here as evidence of sanctioned or delivered facilities.
7. Utilities, building services & safety
| Service | Supplied evidence |
|---|---|
| Water and conservation | TG-RERA’s amenity schedule marks water supply and water conservation/rainwater harvesting “YES” and records 0% progress. The permit requires a rainwater-harvesting structure (percolation pit) and lists 6 RWHPs; no storage, supply source or treatment capacity is stated. RERA amenities |
| Sewerage and drainage | The RERA schedule marks sewerage (chamber, lines, septic tank, STP) and storm-water drains “YES,” both at 0% progress. It also lists sewage/sullage treatment and disposal at 0%; no system specification or capacity is supplied. RERA amenities |
| Electrical | The RERA schedule marks an electrical meter room, sub-station or receiving station “YES” at 0%. The permit requires space for a transformer; no supply capacity or backup system is stated. RERA amenities |
| Fire and life safety | The RERA schedule lists fire-protection and fire-safety requirements at 0%. No specific fire systems, escape-stair details or clearances are supplied in the available material. RERA amenities |
| Waste | The schedule lists solid-waste management and disposal at 0%; the permit lists a garbage house without further details. RERA amenities |
| Lifts, accessibility and security | Lift capacities, accessible circulation, CCTV, access-control or other security provisions are not established in the supplied project records. Document index RERA amenities |
These records identify filed or permit-listed provisions; they do not establish that the facilities have been built, tested or independently verified.
8. Location, access & connectivity
The registered project location is Bhagath Nagar, Karimnagar, Karimnagar district, Telangana, PIN 505001, on survey 979/A, plots 16, 17. The land schedule gives the east boundary as 9M WIDE EXISTING ROAD. The building-permit extract describes the site as Mukarampura (Part)_W31, Ramnagar area, Bhagathnagar locality, Ward 31, and refers to an 18M road width in a permit condition. RERA record Land records
The supplied location record provides a cadastral parcel centroid of 17.41528, 78.35459 and one measured connectivity distance: Financial District (Nanakramguda), 1.2 km. The supplied material does not detail public transport, additional approach roads or other landmark distances. Location record
9. Developer & development status
The registered promoter is M/S SEETHU BUILDERS, identified in the project filing as a partnership. The supplied promoter record lists partners KOMMU SUGUNA DEVI, SIRIPURAM PADMA and CHIDURA SURESH, and authorized signatories SIRIPURAM SURENDER and ILI VIJAYA BHASKER. Corporate record Parties record
The registration certificate gives the promoter office as Village Vavilalapally (47th ward), Mandal Karimnagar urban, District Karimnagar, PIN 505001. A company registration identifier and official project contact details are not established in the supplied material. Corporate record
The RERA filing’s proposed completion date is 02/11/2025. The supplied portal data does not provide a current construction-progress percentage, and the project records supplied here contain no occupancy or completion certificate. RERA record RERA filing RERA amenities Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for VIJETHA SEETHU RESIDENCY, registration P02700002112, issued 24/08/2020; states validity through 02/11/2025 and a 70% separate-account condition. |
| Building permit | Karimnagar Municipal Corporation building permit 3011/W31/2019/5160, dated 02 November, 2019; permit extract describes one residential building with 1 stilt + 5 upper floors. |
| Permit references | Layout / Sub Divn. No. 530/W31/2012/KNR; licensed surveyor No. G 1/49/2019; notarised affidavit No. 11248/2019, dated 16 October, 2019. |
| Title-related filing | Advocate’s title investigation report is filed as document 107336; the supplied overview record identifies the project parcel as survey 979/A, plots 16, 17. |
| Encumbrance statement | Project-filed encumbrance statement, document 107337. |
| Form B declaration | Document 107340; the visible extraction states an annual-audit undertaking and is incomplete. |
| Occupancy / completion certificate | Not present in the supplied project documents. The permit requires an occupancy certificate before occupation. Document index |
The approved layout sheet and other architectural drawing details are not sufficiently extracted to describe beyond the building-permit particulars above. The supplied permit also lists site provisions including a transformer space, rainwater-harvesting structure and garbage house.
1. Project at a glance
Project identity
Registered project name: VIJETHA SEETHU RESIDENCY
Project type / registered portion: Residential apartment project; the record identifies one building, but does not separately state a phase name.
TG-RERA registration: P02700002112, granted under section 5; issued 24/08/2020.
Registration validity: Certificate states five years from 24/08/2020, ending 02/11/2025; no extension is recorded in the supplied certificate. Registration validity is distinct from the stated project completion date.
Registered promoter: M/S SEETHU BUILDERS, identified as a partnership.
RERA status in supplied record: The portal registration data was captured on 10 September 2026; the supplied certificate records validity through 02/11/2025 and says extension is not recorded.
Land and geographic identity
Locality: Bhagath Nagar / BHAGATH NAGAR; the building-permit description also identifies Ramnagar area, Bhagathnagar locality.
Revenue village: Bhagath Nagar. The permit extract separately describes the site as Ward 31 / Mukarampura (Part)_W31; a revenue village for that permit description is not otherwise supplied.
Mandal: Not disclosed in the project land identity; the registration certificate states Karimnagar urban.
District / PIN: Karimnagar / 505001.
Project survey number(s): 979/A. No subdivision beyond “/A” is supplied.
Plots: 16, 17.
Site extent: 690.45 sq.m. total area and 690.45 sq.m. net area; the permit extract records road-affected area as 0 sq.m.
Boundaries: East: 9M WIDE EXISTING ROAD; West: HOUSE OF M MADHAVIOF H NO 9-1-193 2; North: HOUSE OF SURENDER REDDY H NO 9-1-202 1; South: HOUSE OF B SHOBHARANI H NO 9-1-211.
Development identity
Sanctioning authority: Karimnagar Municipal Corporation. The project filing also identifies DTCP as authority for the plan approval.
Principal approval: Building permit / approval 3011/W31/2019/5160, dated 02 November, 2019.
Approved built-up area: 1,685.65 m² residential upper-floor area; the permit separately records 320.90 m² stilt area.
Building count and floors: One detached residential building: 1 Stilt + 5 upper floors; permit-recorded height 14.26 m.
Parking level / provision: The permit condition says the approved stilt is to be used exclusively for vehicle parking. A total parking-space count is not supplied.
Unit counts: 10 units in the RERA filing; the project information records 1 building unit, while the approved plan extract does not state a unit count.
Offering and status
Configuration: 2BHK apartments.
RERA-filed saleable area: 155.15 sq.m. per unit.
Booked / available: 0 booked; 10 available, as last read from the TG-RERA portal; no as-of date accompanies the unit counts, so they are indicative.
Construction stage: No independently verified site-progress evidence or construction-stage percentage is supplied. The TG-RERA amenity schedule shows 0% progress for the listed works.
Completion date: Promoter-declared proposed completion date: 02/11/2025. This is separate from registration validity.
OC / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The building-permit order says an occupancy certificate is compulsory before occupation.
2. The project story
VIJETHA SEETHU RESIDENCY is registered as a residential apartment project on survey 979/A, plots 16, 17, in Bhagath Nagar, Karimnagar. The RERA record describes a single building and lists ten 2BHK apartments. The sanctioned building-permit extract describes a detached residential building with one stilt level and five upper floors.
The filed RERA unit record lists all ten apartments as available and none as booked, but its booking snapshot is undated. The proposed completion date recorded by the promoter is 02/11/2025. The supplied evidence does not establish the current physical construction stage, independently verify completion, or include an occupancy certificate; these should not be inferred from the proposed date or from the registration certificate.
3. Master plan, architecture & building design
The site extent in the land and permit records is 690.45 sq.m.; the RERA filing records the same figure as total and net area. The building permit describes a detached residential building, 1 Stilt + 5 upper floors, with a permit-recorded height of 14.26 m. It records residential upper-floor area of 1,685.65 m² and stilt area of 320.90 m²; these are distinct permit figures, not carpet or saleable area.
The permit extract lists 174.83 m² as the second-floor area and identifies that same area as the mortgage area in the RERA filing. The supplied drawing record contains two sheets, but neither is measured for unit layouts; details such as flats per floor, lift and stair arrangements, building footprint, internal circulation, open-space arrangement and floor-by-floor apartment distribution are therefore not established here.
The RERA filing gives a single building unit, while the permit extract establishes the approved building form and floors; it does not supply a floor-by-floor unit schedule in the available extraction. The permit requires construction to follow the sanctioned plan and prior approval for modifications.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 155.15 sq.m. | Not measured from the supplied drawings | Not supplied |
The saleable area is the area reported in the TG-RERA filing. The floor-plan record says the drawings have not been measured; accordingly, no software-measured carpet area, room dimensions or balcony/utility measurements can be reported. Carpet area, if later measured, would not be interchangeable with saleable area, which includes the unit’s share of common areas.
5. Parking & vehicle circulation
The building permit states that the approved stilt is to be used exclusively for vehicle parking. The permit extract also records a 320.90 m² stilt area, but provides no number of car or two-wheeler spaces, visitor or accessible spaces, or parking-allocation schedule. No separate basement, podium, mechanical parking, ramp or internal-driveway details are established by the supplied evidence.
The permit requires the stilt to be used for parking; this does not by itself establish exclusive parking ownership or an allocation to any particular apartment. No unit-specific parking allocation is supplied.
6. Amenities, recreation & open spaces
The TG-RERA amenity schedule records the following project works. Listed progress is 0% for every item; the schedule does not establish independent completion or verification.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | Size not stated | TG-RERA amenity schedule | 0%; not independently verified |
| Green strip / TOT LOT / park | Size and quantity not stated | TG-RERA amenity schedule | 0%; not independently verified |
| Community buildings | Details not stated | TG-RERA amenity schedule | 0%; not independently verified |
| Aggregate recreational open space | Area not stated | TG-RERA amenity schedule | 0%; not independently verified |
The permit also lists a garbage house as a site provision; no size or delivery status is supplied. The vendor’s amenity list is not used here as evidence of sanctioned or delivered facilities.
7. Utilities, building services & safety
Water and conservation: TG-RERA’s amenity schedule marks water supply and water conservation/rainwater harvesting “YES” and records 0% progress. The permit requires a rainwater-harvesting structure (percolation pit) and lists 6 RWHPs; no storage, supply source or treatment capacity is stated.
Sewerage and drainage: The RERA schedule marks sewerage (chamber, lines, septic tank, STP) and storm-water drains “YES,” both at 0% progress. It also lists sewage/sullage treatment and disposal at 0%; no system specification or capacity is supplied.
Electrical: The RERA schedule marks an electrical meter room, sub-station or receiving station “YES” at 0%. The permit requires space for a transformer; no supply capacity or backup system is stated.
Fire and life safety: The RERA schedule lists fire-protection and fire-safety requirements at 0%. No specific fire systems, escape-stair details or clearances are supplied in the available material.
Waste: The schedule lists solid-waste management and disposal at 0%; the permit lists a garbage house without further details.
Lifts, accessibility and security: Lift capacities, accessible circulation, CCTV, access-control or other security provisions are not established in the supplied project records.
These records identify filed or permit-listed provisions; they do not establish that the facilities have been built, tested or independently verified.
8. Location, access & connectivity
The registered project location is Bhagath Nagar, Karimnagar, Karimnagar district, Telangana, PIN 505001, on survey 979/A, plots 16, 17. The land schedule gives the east boundary as 9M WIDE EXISTING ROAD. The building-permit extract describes the site as Mukarampura (Part)_W31, Ramnagar area, Bhagathnagar locality, Ward 31, and refers to an 18M road width in a permit condition.
The supplied location record provides a cadastral parcel centroid of 17.41528, 78.35459 and one measured connectivity distance: Financial District (Nanakramguda), 1.2 km. The supplied material does not detail public transport, additional approach roads or other landmark distances.
9. Developer & development status
The registered promoter is M/S SEETHU BUILDERS, identified in the project filing as a partnership. The supplied promoter record lists partners KOMMU SUGUNA DEVI, SIRIPURAM PADMA and CHIDURA SURESH, and authorized signatories SIRIPURAM SURENDER and ILI VIJAYA BHASKER.
The registration certificate gives the promoter office as Village Vavilalapally (47th ward), Mandal Karimnagar urban, District Karimnagar, PIN 505001. A company registration identifier and official project contact details are not established in the supplied material.
The RERA filing’s proposed completion date is 02/11/2025. The supplied portal data does not provide a current construction-progress percentage, and the project records supplied here contain no occupancy or completion certificate.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for VIJETHA SEETHU RESIDENCY, registration P02700002112, issued 24/08/2020; states validity through 02/11/2025 and a 70% separate-account condition.
Building permit: Karimnagar Municipal Corporation building permit 3011/W31/2019/5160, dated 02 November, 2019; permit extract describes one residential building with 1 stilt + 5 upper floors.
Permit references: Layout / Sub Divn. No. 530/W31/2012/KNR; licensed surveyor No. G 1/49/2019; notarised affidavit No. 11248/2019, dated 16 October, 2019.
Title-related filing: Advocate’s title investigation report is filed as document 107336; the supplied overview record identifies the project parcel as survey 979/A, plots 16, 17.
Encumbrance statement: Project-filed encumbrance statement, document 107337.
Form B declaration: Document 107340; the visible extraction states an annual-audit undertaking and is incomplete.
Occupancy / completion certificate: Not present in the supplied project documents. The permit requires an occupancy certificate before occupation.
The approved layout sheet and other architectural drawing details are not sufficiently extracted to describe beyond the building-permit particulars above. The supplied permit also lists site provisions including a transformer space, rainwater-harvesting structure and garbage house.
Frequently asked questions
Is VIJETHA SEETHU RESIDENCY registered with Telangana RERA?
Yes. VIJETHA SEETHU RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02700002112; the registration status is New Project.
Who is the developer of VIJETHA SEETHU RESIDENCY?
The promoter named in the RERA registration is M/S SEETHU BUILDERS.
Where is VIJETHA SEETHU RESIDENCY located?
VIJETHA SEETHU RESIDENCY is in BHAGATH NAGAR, Karimnagar, Telangana (505001).
When will VIJETHA SEETHU RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 02/11/2025. This is the promoter's declaration, not a guarantee.