Hill Pearl
SMVSCONSTRUCTIONS · Medchal-Malkajgiri · RERA P02200001434
HILL PEARL is a residential apartment project in GAJULARAMARAM locality, Gajula Ramaram-1 village, Qutballapur mandal, Medchal-Malkajgiri district. The registered promoter is SMVSCONSTRUCTIONS, a Partnership. The project occupies 501.42 sq. m and comprises one residential building, Building A, with 1 Stilt + 5 upper floors and 15 2BHK apartments. Its TG-RERA registration is P02200001434, granted on 25/11/2019, and the certificate records validity through 28/03/2025; the Form B declares completion by 26 MAR 2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | HILL PEARL |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | Phase not separately identified in the supplied record; registration is for the project on Survey Nos. 307/ /1 and 307/ /2 |
| TG-RERA registration | P02200001434; granted under section 5 on 25/11/2019 |
| Registration validity | 25/11/2019 to 28/03/2025, unless extended; the supplied certificate records no extension |
| Registered promoter | SMVSCONSTRUCTIONS (also styled “SMVS CONSTRUCTIONS” in project documents); registered entity type: Partnership RERA record RERA filing |
| RERA status in supplied record | Registration validity ended 28/03/2025; no extension is recorded in the supplied certificate. This does not establish the project’s present completion or occupancy status |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | GAJULARAMARAM RERA record |
| Revenue village | Gajula Ramaram-1 RERA record |
| Mandal / district / PIN | Qutballapur / Medchal-Malkajgiri / 500055 RERA record |
| Project survey numbers | 307/ /1 AND 307/ /2 Land records |
| Plot numbers | 182 PART AND 183 |
| Registered site extent | 501.42 sq. m RERA filing |
| Total / net area | Total area: 501.42 sq. m; net area: 501.42 sq. m RERA filing |
| Boundaries | East: 40 WIDE ROAD; West: PLOT NO 206 ANDPLOT NO 207; North: PLOT NO 184; South: 40 WIDE ROAD RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building approval | Building Permit Order 2/C26/05184/2019, dated 28 March, 2019 |
| Related file number | 2/C26/00723/2019 |
| Approved built-up area | 1,197.75 m² residential upper floors; 228.16 m² stilt area, as stated in the sanction extraction |
| Building count and sanctioned form | One residential building, Building A: 1 Stilt + 5 upper floors |
| Height | 14.95 m, as stated in the sanction extraction |
| Parking levels | The sanction identifies the stilt for parking; the supplied extraction does not give a parking-space count |
| Approved versus RERA-declared units | Sanctioned building-unit count: 1; RERA unit schedule: 15 apartments RERA filing RERA unit table |
Offering and status
| Item | Project record |
|---|---|
| Unit type | 2BHK RERA unit table |
| RERA-filed saleable area | 98.17 m² per unit RERA unit table |
| RERA portal unit counts | 15 total; 0 booked and 15 available in the supplied portal snapshot. The snapshot has no stated as-of date; counts are indicative RERA unit table |
| Construction stage | No independently verified site-progress information is supplied. The GHMC permit sets out construction requirements, but does not establish the present stage |
| Completion dates | Form B declares completion by 26 MAR 2025; the TG-RERA certificate records validity through 28/03/2025 |
| Occupancy / completion certificate | Not evidenced in the supplied documents; the building-permit extraction records completion certification as false |
2. The project story
HILL PEARL is registered as a residential apartment project in Gajula Ramaram-1 village, Qutballapur mandal, on the site identified in the RERA record as Survey Nos. 307/ /1 AND 307/ /2, plots 182 PART AND 183, with a registered extent of 501.42 sq. m. The site is bounded by 40 WIDE ROAD to the east and south, PLOT NO 206 ANDPLOT NO 207 to the west, and PLOT NO 184 to the north. The registered location is GAJULARAMARAM locality, Medchal-Malkajgiri district, PIN 500055; the cadastral parcel centroid supplied for the project is 17.52909, 78.42234. RERA record RERA filing Location record
The GHMC Building Permit Order describes one residential building, Building A, with one stilt and five upper floors. The RERA unit schedule lists 15 two-bedroom apartments. The supplied evidence establishes the sanctioned form and filed offering, but does not establish current construction progress, completed portions, or an occupancy-certified building. RERA unit table
The registration certificate records a validity end date of 28/03/2025, while the promoter’s Form B declaration gives a completion undertaking of 26 MAR 2025. Neither date, by itself, establishes that construction was completed or an occupancy certificate was issued.
3. Master plan, architecture & building design
The GHMC permit extraction describes a single residential building (Building A) on a site stated as 501.42 m², with 1 Stilt + 5 upper floors and a stated building height of 14.95 m. It records 1,197.75 m² for the residential upper floors and 228.16 m² for the stilt; these are the areas as given in the sanction extraction, not saleable or carpet-area figures.
The sanctioned drawing record is not available here as a complete, reviewed plan set. The supplied layout-plan document is not extracted, and the drawing-stamp reading is marked as needing review. Accordingly, the evidence does not support describing floor-by-floor apartment arrangements, building footprint, lifts or stairs, circulation, internal road layout, or detailed open-space distribution. Approvals record
The building permit identifies a tot-lot, transformer space, garbage house and rainwater-harvesting structure (percolation pit) among its stated requirements. It also requires tree planting and maintenance of greenery on the site periphery. These are permit conditions, not evidence that the facilities have been completed.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 15 | 0 | 15 | 98.17 m² | Not measured in the supplied floor-plan records | Not supplied |
The 98.17 m² figure is the RERA-filed saleable area. Saleable area is distinct from carpet area; the supplied floor-plan record reports that no flats were measured, so no software-measured carpet or room dimensions can be stated. The supplied portal booking counts have no as-of date and should be treated as indicative. RERA unit table RERA unit details Floor plans
5. Parking & vehicle circulation
The GHMC permit states that the stilt is approved for parking and must be used exclusively for that purpose; its conditions also refer to cellar and stilt parking. The permit extraction for this project identifies a stilt but does not establish a parking-space count, visitor or accessible spaces, EV charging provision, parking allocation to individual apartments, or detailed vehicle circulation.
The RERA filing marks all 15 apartments as mortgaged, but the supplied information does not identify any apartment-specific parking allocation. A parking space shown or referred to in a plan would not, on its own, establish exclusive ownership or an allotment. RERA unit table
6. Amenities, recreation & open spaces
The RERA amenity record contains 14 listed items. Each item below is recorded at 0% progress; this is a filed progress figure, not independent verification of site condition. “YES” denotes availability recorded in the supplied RERA amenity data, not verified completion. RERA amenities
| Facility | Green Strip/TOT LOT/Park |
|---|---|
| Description / size | Size not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Aggregate area of recreational Open Space |
|---|---|
| Description / size | Area not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Community Buildings |
|---|---|
| Description / size | Details and size not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Internal Roads & Footpaths |
|---|---|
| Description / size | Details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Street Lighting |
|---|---|
| Description / size | Details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Water Supply |
|---|---|
| Description / size | RERA amenity record: YES |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Sewerage (Chamber, Lines, Septic Tank, STP) |
|---|---|
| Description / size | RERA amenity record: YES; specific system and capacity not established |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Storm Water Drains |
|---|---|
| Description / size | Details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Treatment And Disposal Of Sewage And Sullage Water |
|---|---|
| Description / size | Details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Solid Waste Management And Disposal |
|---|---|
| Description / size | Details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Water Conservation, Rain water Harvesting |
|---|---|
| Description / size | RERA amenity record: YES; the GHMC permit also requires a rainwater-harvesting structure (percolation pit) |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Energy management |
|---|---|
| Description / size | RERA amenity record: YES; details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Fire Protection And Fire Safety Requirements |
|---|---|
| Description / size | RERA amenity record: YES; permit conditions specify fire-safety provisions |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
| Facility | Electrical Meter Room, Sub-Station, Receiving Station |
|---|---|
| Description / size | Details not supplied |
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified |
7. Utilities, building services & safety
The GHMC permit conditions require a transformer space, rainwater-harvesting structure, garbage house, emergency lighting in corridors/common passages and staircases, a generator as an alternate electricity source, fire-safety installations, and specified fire extinguishers and alarm systems. The permit also specifies separate underground and terrace water tanks of 25,000 lts. each for residential buildings, and requires hose reels and a down corner. These are sanctioned conditions; the supplied evidence does not verify installation, operating status, or service capacities beyond the stated tank figures.
The permit requires an entry and an exit with a minimum width of 4.5mts. and height clearance of 5mts., fire-resistant swing doors for collapsible lifts, and an automatic sprinkler system if basement area exceeds 200 sq. m. The supplied records do not confirm whether a basement exists or whether the conditional sprinkler requirement applies. No lift count or capacity, sewage-treatment capacity, water source, backup-power capacity, CCTV/security system, accessibility details, or operational utility status is evidenced. RERA amenities
8. Location, access & connectivity
The land record identifies 40 WIDE ROAD along the east and south boundaries. The GHMC permit extraction refers to 18 mt. road widths in its conditions, but the supplied material does not establish the project’s full approach route or public transport access. HITEC City is listed as an anchor at 10.7 km; the evidence does not provide a travel time. RERA filing Location record
9. Developer & development status
The registered promoter is SMVSCONSTRUCTIONS, identified as a partnership in the RERA promoter information. The supplied GSTIN is 36ADRFS4218E1ZW. The RERA record lists SRINIVASARAO KOLLI as Authorized Signatory and MALLESWARI KOLLI as Partner. The supplied registration certificate lists the promoter office as Village: Miyapur, Mandal: Serilingampally, District: Ranga Reddy, Pin: 500049. RERA filing Corporate record Parties record
The Form B affidavit is a promoter declaration made through authorised signatory Kolli Srinivasarao. It declares the land free from encumbrances and undertakes completion by 26 MAR 2025; these statements are attributed to the promoter and are not independent verification of title, construction progress or completion.
No independently verified current construction stage or occupancy-certificate status is supplied. The GHMC permit states that an occupancy certificate is compulsory before occupation and that completion notice must be submitted after completion; the supplied permit extraction records completion certification as false.
10. Approvals, official records & documents
| Identifier / date | P02200001434; issued 25/11/2019; validity through 28/03/2025 |
|---|---|
| What the supplied record establishes | Registration of HILL PEARL and its stated conditions, including the separate-account condition; no extension is recorded in the certificate |
| Identifier / date | 2/C26/05184/2019; 28 March, 2019; file 2/C26/00723/2019 |
|---|---|
| What the supplied record establishes | Conditional building permission for Building A, residential, 1 Stilt + 5 upper floors |
| Identifier / date | Survey Nos. 307/ /1 and 307/ /2; plots 182 PART AND 183 |
|---|---|
| What the supplied record establishes | Project land identity and filed unit schedule |
| Identifier / date | Dated 26 MAR 2019 |
|---|---|
| What the supplied record establishes | Promoter’s declarations concerning title, encumbrances, separate account and completion undertaking |
| Identifier / date | Document 68649 |
|---|---|
| What the supplied record establishes | Layout-plan submission is listed, but the supplied record is not extracted as a reviewed plan |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | The available permit extraction records completion certification as false; no occupancy or completion certificate is evidenced |
The evidence index does not establish whether further approvals or certificates have since been issued.
1. Project at a glance
Project identity
Registered project name: HILL PEARL
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified in the supplied record; registration is for the project on Survey Nos. 307/ /1 and 307/ /2
TG-RERA registration: P02200001434; granted under section 5 on 25/11/2019
Registration validity: 25/11/2019 to 28/03/2025, unless extended; the supplied certificate records no extension
Registered promoter: SMVSCONSTRUCTIONS (also styled “SMVS CONSTRUCTIONS” in project documents); registered entity type: Partnership
RERA status in supplied record: Registration validity ended 28/03/2025; no extension is recorded in the supplied certificate. This does not establish the project’s present completion or occupancy status
Land and geographic identity
Locality: GAJULARAMARAM
Revenue village: Gajula Ramaram-1
Mandal / district / PIN: Qutballapur / Medchal-Malkajgiri / 500055
Project survey numbers: 307/ /1 AND 307/ /2
Plot numbers: 182 PART AND 183
Registered site extent: 501.42 sq. m
Total / net area: Total area: 501.42 sq. m; net area: 501.42 sq. m
Boundaries: East: 40 WIDE ROAD; West: PLOT NO 206 ANDPLOT NO 207; North: PLOT NO 184; South: 40 WIDE ROAD
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: Building Permit Order 2/C26/05184/2019, dated 28 March, 2019
Related file number: 2/C26/00723/2019
Approved built-up area: 1,197.75 m² residential upper floors; 228.16 m² stilt area, as stated in the sanction extraction
Building count and sanctioned form: One residential building, Building A: 1 Stilt + 5 upper floors
Height: 14.95 m, as stated in the sanction extraction
Parking levels: The sanction identifies the stilt for parking; the supplied extraction does not give a parking-space count
Approved versus RERA-declared units: Sanctioned building-unit count: 1; RERA unit schedule: 15 apartments
Offering and status
Unit type: 2BHK
RERA-filed saleable area: 98.17 m² per unit
RERA portal unit counts: 15 total; 0 booked and 15 available in the supplied portal snapshot. The snapshot has no stated as-of date; counts are indicative
Construction stage: No independently verified site-progress information is supplied. The GHMC permit sets out construction requirements, but does not establish the present stage
Completion dates: Form B declares completion by 26 MAR 2025; the TG-RERA certificate records validity through 28/03/2025
Occupancy / completion certificate: Not evidenced in the supplied documents; the building-permit extraction records completion certification as false
2. The project story
HILL PEARL is registered as a residential apartment project in Gajula Ramaram-1 village, Qutballapur mandal, on the site identified in the RERA record as Survey Nos. 307/ /1 AND 307/ /2, plots 182 PART AND 183, with a registered extent of 501.42 sq. m. The site is bounded by 40 WIDE ROAD to the east and south, PLOT NO 206 ANDPLOT NO 207 to the west, and PLOT NO 184 to the north. The registered location is GAJULARAMARAM locality, Medchal-Malkajgiri district, PIN 500055; the cadastral parcel centroid supplied for the project is 17.52909, 78.42234.
The GHMC Building Permit Order describes one residential building, Building A, with one stilt and five upper floors. The RERA unit schedule lists 15 two-bedroom apartments. The supplied evidence establishes the sanctioned form and filed offering, but does not establish current construction progress, completed portions, or an occupancy-certified building.
The registration certificate records a validity end date of 28/03/2025, while the promoter’s Form B declaration gives a completion undertaking of 26 MAR 2025. Neither date, by itself, establishes that construction was completed or an occupancy certificate was issued.
3. Master plan, architecture & building design
The GHMC permit extraction describes a single residential building (Building A) on a site stated as 501.42 m², with 1 Stilt + 5 upper floors and a stated building height of 14.95 m. It records 1,197.75 m² for the residential upper floors and 228.16 m² for the stilt; these are the areas as given in the sanction extraction, not saleable or carpet-area figures.
The sanctioned drawing record is not available here as a complete, reviewed plan set. The supplied layout-plan document is not extracted, and the drawing-stamp reading is marked as needing review. Accordingly, the evidence does not support describing floor-by-floor apartment arrangements, building footprint, lifts or stairs, circulation, internal road layout, or detailed open-space distribution.
The building permit identifies a tot-lot, transformer space, garbage house and rainwater-harvesting structure (percolation pit) among its stated requirements. It also requires tree planting and maintenance of greenery on the site periphery. These are permit conditions, not evidence that the facilities have been completed.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 15 | 0 | 15 | 98.17 m² | Not measured in the supplied floor-plan records | Not supplied |
The 98.17 m² figure is the RERA-filed saleable area. Saleable area is distinct from carpet area; the supplied floor-plan record reports that no flats were measured, so no software-measured carpet or room dimensions can be stated. The supplied portal booking counts have no as-of date and should be treated as indicative.
5. Parking & vehicle circulation
The GHMC permit states that the stilt is approved for parking and must be used exclusively for that purpose; its conditions also refer to cellar and stilt parking. The permit extraction for this project identifies a stilt but does not establish a parking-space count, visitor or accessible spaces, EV charging provision, parking allocation to individual apartments, or detailed vehicle circulation.
The RERA filing marks all 15 apartments as mortgaged, but the supplied information does not identify any apartment-specific parking allocation. A parking space shown or referred to in a plan would not, on its own, establish exclusive ownership or an allotment.
6. Amenities, recreation & open spaces
The RERA amenity record contains 14 listed items. Each item below is recorded at 0% progress; this is a filed progress figure, not independent verification of site condition. “YES” denotes availability recorded in the supplied RERA amenity data, not verified completion.
| Category | Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|---|
| Landscape/open space | Green Strip/TOT LOT/Park | Size not supplied | 0%; not independently verified | |
| Landscape/open space | Aggregate area of recreational Open Space | Area not supplied | 0%; not independently verified | |
| Sports/recreation | Community Buildings | Details and size not supplied | 0%; not independently verified | |
| Convenience/community | Internal Roads & Footpaths | Details not supplied | 0%; not independently verified | |
| Convenience/community | Street Lighting | Details not supplied | 0%; not independently verified | |
| Site services | Water Supply | RERA amenity record: YES | 0%; not independently verified | |
| Site services | Sewerage (Chamber, Lines, Septic Tank, STP) | RERA amenity record: YES; specific system and capacity not established | 0%; not independently verified | |
| Site services | Storm Water Drains | Details not supplied | 0%; not independently verified | |
| Site services | Treatment And Disposal Of Sewage And Sullage Water | Details not supplied | 0%; not independently verified | |
| Site services | Solid Waste Management And Disposal | Details not supplied | 0%; not independently verified | |
| Site services | Water Conservation, Rain water Harvesting | RERA amenity record: YES; the GHMC permit also requires a rainwater-harvesting structure (percolation pit) | 0%; not independently verified | |
| Site services | Energy management | RERA amenity record: YES; details not supplied | 0%; not independently verified | |
| Site services | Fire Protection And Fire Safety Requirements | RERA amenity record: YES; permit conditions specify fire-safety provisions | 0%; not independently verified | |
| Site services | Electrical Meter Room, Sub-Station, Receiving Station | Details not supplied | 0%; not independently verified |
7. Utilities, building services & safety
The GHMC permit conditions require a transformer space, rainwater-harvesting structure, garbage house, emergency lighting in corridors/common passages and staircases, a generator as an alternate electricity source, fire-safety installations, and specified fire extinguishers and alarm systems. The permit also specifies separate underground and terrace water tanks of 25,000 lts. each for residential buildings, and requires hose reels and a down corner. These are sanctioned conditions; the supplied evidence does not verify installation, operating status, or service capacities beyond the stated tank figures.
The permit requires an entry and an exit with a minimum width of 4.5mts. and height clearance of 5mts., fire-resistant swing doors for collapsible lifts, and an automatic sprinkler system if basement area exceeds 200 sq. m. The supplied records do not confirm whether a basement exists or whether the conditional sprinkler requirement applies. No lift count or capacity, sewage-treatment capacity, water source, backup-power capacity, CCTV/security system, accessibility details, or operational utility status is evidenced.
8. Location, access & connectivity
The land record identifies 40 WIDE ROAD along the east and south boundaries. The GHMC permit extraction refers to 18 mt. road widths in its conditions, but the supplied material does not establish the project’s full approach route or public transport access. HITEC City is listed as an anchor at 10.7 km; the evidence does not provide a travel time.
9. Developer & development status
The registered promoter is SMVSCONSTRUCTIONS, identified as a partnership in the RERA promoter information. The supplied GSTIN is 36ADRFS4218E1ZW. The RERA record lists SRINIVASARAO KOLLI as Authorized Signatory and MALLESWARI KOLLI as Partner. The supplied registration certificate lists the promoter office as Village: Miyapur, Mandal: Serilingampally, District: Ranga Reddy, Pin: 500049.
The Form B affidavit is a promoter declaration made through authorised signatory Kolli Srinivasarao. It declares the land free from encumbrances and undertakes completion by 26 MAR 2025; these statements are attributed to the promoter and are not independent verification of title, construction progress or completion.
No independently verified current construction stage or occupancy-certificate status is supplied. The GHMC permit states that an occupancy certificate is compulsory before occupation and that completion notice must be submitted after completion; the supplied permit extraction records completion certification as false.
10. Approvals, official records & documents
| Identifier / date | P02200001434; issued 25/11/2019; validity through 28/03/2025 |
|---|---|
| What the supplied record establishes | Registration of HILL PEARL and its stated conditions, including the separate-account condition; no extension is recorded in the certificate |
| Identifier / date | 2/C26/05184/2019; 28 March, 2019; file 2/C26/00723/2019 |
|---|---|
| What the supplied record establishes | Conditional building permission for Building A, residential, 1 Stilt + 5 upper floors |
| Identifier / date | Survey Nos. 307/ /1 and 307/ /2; plots 182 PART AND 183 |
|---|---|
| What the supplied record establishes | Project land identity and filed unit schedule |
| Identifier / date | Dated 26 MAR 2019 |
|---|---|
| What the supplied record establishes | Promoter’s declarations concerning title, encumbrances, separate account and completion undertaking |
| Identifier / date | Document 68649 |
|---|---|
| What the supplied record establishes | Layout-plan submission is listed, but the supplied record is not extracted as a reviewed plan |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | The available permit extraction records completion certification as false; no occupancy or completion certificate is evidenced |
The evidence index does not establish whether further approvals or certificates have since been issued.
Frequently asked questions
Is HILL PEARL registered with Telangana RERA?
Yes. HILL PEARL is registered with the Telangana Real Estate Regulatory Authority as P02200001434; the registration status is New Project.
Who is the developer of HILL PEARL?
The promoter named in the RERA registration is SMVSCONSTRUCTIONS.
Where is HILL PEARL located?
HILL PEARL is in GAJULARAMARAM, Gajula Ramaram-1, Qutballapur, Medchal-Malkajgiri, Telangana (500055).
When will HILL PEARL be completed?
The promoter's proposed date of completion filed with RERA is 28/03/2025. This is the promoter's declaration, not a guarantee.
More projects in Gajula Ramaram 1