SAI KRISHNA RESIDENCY is a residential apartment project in Chanda Nagar, Serilingampally Mandal, Ranga Reddy District, developed by the registered promoter SAI JYOTHI CONSTRUCTIONS. It is on plots 81, 82 & 83, covers 832.2 sq. m and comprises one residential building with 1 Cellar + Stilt + 5 upper floors and 15 apartments. The configurations are 3BHK and 4BHK, with RERA-filed saleable areas of 103.04 sq. m and 140.05 sq. m, respectively. It is registered with TG-RERA under P02400002469, and the project header lists a proposed completion date of 30 November 2026.

More from Sai Jyothi Constructions · 2 projects →

01What we found

Period endedTG-RERA registration ran to 18 Jul 2026 - check its extension on TG-RERA
10documents on file - each fact links to its page
0court cases on this project's land in the court records searched
12items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

12 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameSAI KRISHNA RESIDENCY RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionNo phase name is stated in the supplied registration record. The registration covers the project associated with plots 81, 82 & 83.
TG-RERA registrationP02400002469; granted 11 January 2021; certificate states five-year validity ending 18 July 2026. The certificate records no extension. RERA record
Registered promoterSAI JYOTHI CONSTRUCTIONS, identified in the project filing as a partnership. RERA record RERA filing Corporate record
RERA status in supplied recordRegistered project. The certificate validity end date is 18 July 2026; no later extension or current status update is supplied.

Land and geographic identity

ItemProject record
LocalityChanda Nagar / Chandanagar RERA record RERA filing
Revenue villageChanda Nagar (also stated as Chandanagar in the filed approval and title documents) RERA record
Mandal / district / PINSerilingampally / Ranga Reddy / 500050 RERA record
Project survey number(s)50/AA/50/C in the RERA registration record; the GHMC building permit identifies 50/AA and 50/C. RERA record
Plot numbers81, 82 & 83 RERA filing
Registered site extent832.2 sq. m in the RERA filing and permit extraction; the title report describes 995 sq. yds. / 832.24 sq. m. RERA filing
Total / net areaTotal area 832.2 sq. m; net area 832.20 sq. m in the RERA land record. The permit extraction also states site area and net area of 832.2 sq. m. RERA filing
BoundariesEast: ROAD WIDTH 12; West, North and South: OTHER LAND. RERA filing

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalBuilding Permit Order 2/C21/07761/2020, approved 18 July 2020; associated file number 2/C21/06293/2020. Approvals record
BuildingOne residential building, named SAI JYOYHI-1 (CONSTRUCTIONS) in the permit extraction
Sanctioned configuration1 Cellar + Stilt + 5 upper floors; stated building height 14.95 m.
Approved built-up areaRERA project fields state 2,894.42 sq. m. The supplied permit extraction contains additional area entries, but does not provide a clear, consistently labelled approved-built-up-area figure that can be substituted for the RERA field. RERA filing
Parking levels / areaCellar and stilt are designated for parking; the permit extraction records 467.41 sq. m for cellar parking floors and 291.23 sq. m for stilt parking floors. A sanctioned parking-space count is not supplied.
Unit countGHMC permit says the sanctioned number of units must not be increased, but the supplied extraction does not state the number. The RERA unit record lists 15 units. RERA unit table

Offering and status

ItemProject record
Configurations3BHK and 4BHK apartments RERA unit table
RERA-filed saleable area3BHK: 103.04 sq. m; 4BHK: 140.05 sq. m RERA unit table
Booked / available3BHK: 2 booked / 3 available; 4BHK: 5 booked / 5 available. These are the counts last read from the TG-RERA portal; the record provides no as-of date, so treat them as indicative. RERA unit table
Construction stageNo dated construction-progress report or independently verified site-stage evidence is supplied. The registration and building permit are not evidence of completion. Document index
Completion datePromoter’s Form B declares 18 July 2026 as the completion date. The project header separately lists a proposed completion date of 30 November 2026; the supplied evidence does not explain that field. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied; the GHMC permit extraction states that completion notice and an occupancy certificate are required after completion and that occupancy is compulsory before occupation.

2. The project story

Sai Krishna Residency is registered as a residential apartment project in Chanda Nagar, Serilingampally Mandal, Ranga Reddy District. The registered land is associated with plots 81, 82 & 83 and survey 50/AA/50/C, with the building permit identifying the land as survey 50/AA and 50/C. RERA record

The GHMC permit describes one residential building with a cellar, stilt and five upper floors. The RERA unit record lists 15 apartments: five 3BHK and ten 4BHK. The project filing shows seven booked and eight available, but does not date those inventory figures. RERA unit table

The supplied records establish a permit and a promoter-declared completion undertaking, but do not establish present construction progress, completion, or occupancy certification. The permit makes an occupancy certificate compulsory before occupation.

3. Master plan, architecture & building design

The filed project describes a 832.2 sq. m site with a net area of 832.20 sq. m. The GHMC permit extraction identifies one residential building and sanctions a cellar, stilt and five upper floors, with a stated height of 14.95 m. It records setbacks of 4 m front, 4 m side I, 3 m side II and 4 m rear. RERA filing

The permit extraction lists 1,920.20 sq. m for residential upper floors, 467.41 sq. m for cellar parking floors, and 291.23 sq. m for stilt parking floors. It also identifies a 52.14 sq. m tot-lot, one rainwater-harvesting structure, space for a transformer, a garbage house and an ETP. These are permit-recorded provisions; the supplied material does not establish their as-built condition.

The RERA filing reports approved built-up area of 2,894.42 sq. m. The provided permit extraction also contains area labels that do not allow a clearly identified permit built-up-area figure to be stated here. No measured building footprint, flats-per-floor plan, lift or stair details, or measured floor-plan geometry are supplied. RERA filing Floor plans

4. Homes, configurations & floor plans

The TG-RERA unit record lists 15 apartments across two configurations. Areas below are the RERA-filed saleable areas, not measured carpet areas. The supplied floor-plan record contains two drawings but reports no flats measured; therefore there is no software-measured carpet area to report from those drawings. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK523103.04 sq. mNot measured in supplied floor-plan recordNot supplied
4BHK1055140.05 sq. mNot measured in supplied floor-plan recordNot supplied

Saleable area and carpet area are different measures: the supplied floor-plan record notes that saleable area also counts a home’s share of common areas. The drawings were not measured in this review, so room dimensions, balcony or utility areas, and typical floor arrangements cannot be confirmed from the supplied evidence. Booking counts have no stated as-of date. Floor plans RERA unit table

5. Parking & vehicle circulation

The GHMC permit designates the cellar and stilt for vehicle parking and states that those areas are to be used exclusively for parking without partition walls or rolling shutters. It records cellar parking-floor area of 467.41 sq. m and stilt parking-floor area of 291.23 sq. m.

A sanctioned number of car or two-wheeler spaces, visitor or accessible parking provision, ramp details, internal vehicle circulation, EV charging, and unit-specific parking allocations are not established in the supplied records. A drawn or designated parking area does not establish exclusive ownership or allocation to a particular apartment. RERA unit table

6. Amenities, recreation & open spaces

The GHMC permit extraction identifies the following site provisions. The supplied records do not provide dated delivery or independent verification of completion.

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green area52.14 sq. m; permit requires it to be fenced and maintained as greenery before issue of the occupancy certificatePermit-recorded; completion not verified
Rainwater-harvesting structureOne percolation-pit structurePermit-recorded; completion not verified
Garbage houseNo size or capacity suppliedPermit-recorded; completion not verified
Transformer spaceRequired provision; no size or capacity suppliedPermit-recorded; completion not verified
ETPListed in permit provisions; no capacity suppliedPermit-recorded; completion not verified

No supplied RERA-filed amenity schedule establishes a clubhouse, gym, swimming pool or other indoor or sports facility as sanctioned or delivered for this project. RERA amenities

7. Utilities, building services & safety

The building permit records a rainwater-harvesting structure, an ETP, a garbage house and space for a transformer. It does not supply capacities, operating specifications, or evidence that these provisions have been installed or commissioned. The project amenity record marks water supply, sewerage, storm-water drains, green strip/tot-lot and rainwater harvesting as available, each with 50% progress, but provides no dated certification or independent site verification. RERA amenities

The permit also requires an occupancy Fire NOC from the Director (EV&DM) before an occupancy certificate, identifies the cellar and stilt as parking-only areas, and requires an occupancy certificate before occupation. These are recorded permit conditions, not evidence that the required NOC has been obtained or that the building is compliant or ready for occupation.

The supplied material does not establish water source or storage capacity, STP details or reuse, electrical supply or backup capacity, lift count or capacity, fire-system installation, CCTV, access control, or accessible circulation. RERA amenities Promoter website

8. Location, access & connectivity

The registered location is Chanda Nagar, Chanda Nagar revenue village, Serilingampally Mandal, Ranga Reddy District, PIN 500050. The project record gives a cadastral parcel centroid of 17.50192, 78.32684. RERA record RERA filing Location record

The nearest sampled Outer Ring Road interchange is recorded at approximately 7.7 km. No measured distances to other landmarks, public-transport stops, schools or airports are supplied. Location record

9. Developer & development status

The registered promoter is SAI JYOTHI CONSTRUCTIONS, identified in the RERA filing as a partnership. The named authorized signatory is UPPULURU VENKATA RAMANA MURTHY; the listed partners are DADUVY MADHURIMA, VADDEPALLI DAMODAR RAO and SADDI CHANNA REDDY. The supplied promoter address is Annapurna Enclave, Chandanagar, Chanda Nagar, Serilingampally, Ranga Reddy, 500050. Corporate record Parties record RERA filing

In Form B dated 11 September 2020, the promoter declared a completion date of 18 July 2026 and made project-account, audit and pending-approval undertakings. The supplied evidence contains no dated construction update, independently verified progress assessment, occupancy certificate, or evidence of an extension to the registration.

10. Approvals, official records & documents

TG-RERA registration certificate
Reference and scopeP02400002469, for Sai Krishna Residency; issued 11 January 2021; validity stated through 18 July 2026
Evidence statusCertificate supplied; no extension shown
GHMC building permit
Reference and scopeBuilding Permit Order 2/C21/07761/2020, file 2/C21/06293/2020, approved 18 July 2020; building at Chandanagar on survey 50/AA and 50/C
Evidence statusPermit extraction supplied; conditional permission for cellar, stilt and five upper floors
Layout / subdivision reference
Reference and scopeG/250/LP/372/02, shown in the building-permit extraction
Evidence statusReference is supplied; an approved layout drawing or separate layout certificate is not supplied here
Form B promoter declaration
Reference and scopeSai Krishna Residency; dated 11 September 2020; includes the promoter’s declared title, encumbrance and completion statements
Evidence statusDeclaration supplied; statements are promoter assertions, not independent verification
Occupancy / completion certificate
Reference and scopeNot supplied
Evidence statusThe permit states an occupancy certificate is compulsory before occupation
Project construction-progress evidence
Reference and scopeNo dated progress certificate or site-verification report supplied
Evidence statusCurrent construction stage cannot be established from this evidence Document index RERA amenities

Frequently asked questions

Is SAI KRISHNA RESIDENCY registered with Telangana RERA?

Yes. SAI KRISHNA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02400002469; the registration status is New Project.

Who is the developer of SAI KRISHNA RESIDENCY?

The promoter named in the RERA registration is SAI JYOTHI CONSTRUCTIONS.

Where is SAI KRISHNA RESIDENCY located?

SAI KRISHNA RESIDENCY is in CHANDA NAGAR, Serilingampally, Rangareddy, Telangana (500050).

When will SAI KRISHNA RESIDENCY be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.