Nandini Isha

NANDINI CONSTRUCTIONS · Karimnagar · RERA P02700010910

NANDINI ISHA is a residential apartment project in KARIMNAGAR / LAXMI NAGAR, Karimnagar urban mandal, Karimnagar district, developed by the registered promoter NANDINI CONSTRUCTIONS. The project occupies a gross site area of 957.43 sq.m and comprises one building, Building A, with Stilt + 5 Upper Floors and 20 apartments: 2BHK (10 units) and 3BHK (10 units). Its TG-RERA registration number is P02700010910, and the project header records a proposed completion date of 18/07/2029.

More from Nandini Constructions · 2 projects →

01What we found

RegisteredTG-RERA - valid till 18 Mar 2029
20documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameNANDINI ISHA RERA record
Project type / phaseResidential apartment project; phase or separately registered portion is not identified in the supplied record. RERA record
TG-RERA registrationP02700010910 RERA record
Registration validity18/03/2026 to 18/03/2029, unless extended by the Authority. This is registration validity, not the building completion deadline. RERA record
Registered promoterNANDINI CONSTRUCTIONS RERA record Corporate record
RERA statusRegistered; the supplied certificate is Form C. RERA record

Land and geographic identity

FieldProject record
LocalityKARIMNAGAR / LAXMI NAGAR; the building-permit plan identifies LAXMI NAGAR. RERA record RERA filing
Revenue villageNot disclosed in the RERA land record. The permit identifies Karimnagar as its village/locality description; the registered project location is Karimnagar urban, Karimnagar. Land records
Mandal / district / PINKarimnagar urban / Karimnagar / 505001 RERA record
Survey numbersSy. Nos. 483, 498 and 499; no subdivisions are stated in the supplied project record. RERA record Land records
Gross / total site area957.43 sq.m RERA filing
Road-affected area94.2 sq.m RERA filing
Net site area863.23 sq.m RERA filing
BoundariesEast: 30 FEET WIDE ROAD; West: PLOT OF OTHERS; North: PLOT OF B VIMALA; South: 50 FEET WIDE ROAD. RERA filing

Development identity

FieldProject record
Sanctioning authorityThe filed building-permit order is issued by Karimnagar Municipal Corporation; its approval-plan record also identifies DTCP. Approvals record
Principal approvalBuilding Permit Order / approval no. 0084/KARI/SWBP/2026, dated 18/03/2026; file no. 011684/KARI/00133/SWBP/2025. Approvals record
Building count and configurationOne residential building, identified as Building A; Stilt + 5 Upper Floors.
Proposed building heightThe permit record gives 14.99 m as building height and 20.99 m as total building height; the approval-plan extract also records proposed height 17.99 m. These are reproduced as recorded, without resolving the differing labels.
Approved built-up area2152.9 sq.m excluding parking; 2630.67 sq.m including parking, as stated in the filed approval-plan record.
Sanctioned versus RERA unit count20 dwelling units in the building-permit record; the project’s RERA unit record also lists 20 units. RERA unit table
Parking provision in approval record7.00 car parking spaces; proposed parking area 432.69 sq.m. Visitor parking: 45.07 (10.47 %) proposed against 43.06 (10 %) required, as recorded in the plan extract.

Offering and status

FieldProject record
Configurations2BHK (10 units) and 3BHK (10 units). RERA unit table
RERA-filed saleable area2BHK: 111.48 sq.m; 3BHK: 151.24 sq.m. RERA unit table
Booked / availablePortal extract lists 0 booked / 10 available for each configuration, total 0 booked / 20 available. The extract has no as-of date, so counts are indicative. RERA unit table
Construction stageA new project is registered, but the supplied evidence does not establish independently verified construction progress. RERA amenity-progress entries are recorded as 0%. RERA record RERA amenities
Completion datesPromoter’s Form B undertakes completion on or before 18/03/2029. The project header separately records a proposed completion date of 18/07/2029; the supplied record does not explain that field’s basis. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The permit requires completion notice and an occupancy certificate before occupation.

2. The project story

  • NANDINI ISHA is recorded with TG-RERA as a residential apartment project in the Laxmi Nagar area of Karimnagar, on Sy. Nos. 483, 498 and 499. The filed building-permit record describes one building, Building A, comprising stilt parking and five upper floors, with 20 dwelling units. RERA record Land records
  • The RERA unit schedule lists ten 2BHK and ten 3BHK apartments. The portal snapshot shows all 20 as available and none booked, but it is undated. This is a filed inventory snapshot, not confirmation of present availability. RERA unit table
  • The project is registered and has a building-permit order in the supplied documents. No independent site-progress evidence or occupancy/completion certificate is included. The permit sets out requirements for commencement notice, completion notice and obtaining an occupancy certificate before occupation; it also records a construction-commencement deadline of 14/09/2026 and completion deadline of 18/03/2029.

3. Master plan, architecture & building design

  • The filed plan describes a single residential building on a site with gross plot area 957.43 sq.m, road-affected area 94.2 sq.m and net plot area 863.23 sq.m. It records proposed coverage of 55.00 % (477.82 sq.m) and vacant plot area of 380.04 sq.m. These are plan-record figures; the supplied evidence does not independently verify construction on site.
  • The building is shown as Stilt + 5 Upper Floors and contains 20 dwelling units. The plan extract records total proposed BUA of 2152.9 sq.m excluding parking and 2630.67 sq.m including parking. It does not provide a separate carpet-area total for the building.
  • The approval-plan extract identifies a front setback of 2.50 m, rear setback of 2.50 m, side 1 setback of 2.50 m and side 2 setback of 4.0 m. The building-permit order separately records front and rear setbacks of 2.5 m and side setbacks of 4.0 m each. The supplied material does not provide a complete drawing-derived account of floor-by-floor circulation, lift or stair arrangements, entries, or the building footprint.
  • The permit identifies 94.2 sq.m as road-affected area to be surrendered to the municipal authority without compensation. Its conditions also call for greenery, a tot-lot, rainwater harvesting, transformer space and a garbage house; these are approval conditions, not evidence that the works are complete.

4. Homes, configurations & floor plans

RERA records ten apartments in each of the two configurations. The saleable areas below are RERA-filed. Carpet-area figures are software measurements from the approved floor-plan drawings, not RERA disclosures; the drawing measurements are flagged as needing review. Saleable area includes the home’s share of common areas and should not be treated as carpet area. RERA unit table Floor plans

ConfigurationUnitsBookedAvailable*RERA saleable areaMeasured carpet area**Loading (if supplied)
2BHK10010111.48 sq.m60.7–68.9 sq.m; median 64.8 sq.m42%
3BHK10010151.24 sq.m93.5–98.4 sq.m; median 95.9 sq.m37%

\* Booked and available counts are from an undated TG-RERA portal extract. \** Software-measured from drawing geometry; the supplied review flag applies to all four measured designs in each configuration. Verify measurements against the filed plan. RERA unit table Floor plans

  • The drawing extract includes a sample 2BHK plan labelled Flat 04 on the 5th Floor Plan, with hall, dining room, two bedrooms, kitchen, toilets and balconies. A sample 3BHK plan labelled Flat 03 on the Typical Floor Plan for floors 1 to 4 shows living/dining, three bedrooms, kitchen, pooja space, toilets and balconies. These are drawing labels and sample-room descriptions, not a complete unit-by-unit schedule. RERA unit details
  • Balconies are excluded from the supplied software carpet-area measurements. The supplied record does not give separate balcony or utility-area totals for all units. RERA unit details Floor plans

5. Parking & vehicle circulation

  • The filed approval-plan record states 7.00 car parking spaces, with required parking area 430.58 sq.m and proposed parking area 432.69 sq.m. It records proposed visitor parking as 45.07 (10.47 %) against 43.06 (10 %) required. These are plan figures; the supplied documents do not establish individual parking allocations or exclusive ownership of any bay.
  • The building-permit conditions state that approved stilt parking is to be used exclusively for parking and not partitioned, converted or misused. The supplied record does not specify two-wheeler spaces, accessible spaces, EV chargers, ramp details, or a separate parking-level count beyond the stilt configuration.

6. Amenities, recreation & open spaces

The RERA amenity extract lists 14 items and records 0% progress for each item. It marks water supply, sewerage, green strip/tot-lot/park, rainwater harvesting and electrical meter room/sub-station/receiving station as “YES”; those entries are RERA-filed availability indicators, not independent completion verification. RERA amenities

Community / recreation
Description / sizeCommunity buildings; aggregate recreational open space
Evidence sourceRERA amenity register
Declared progress / verified status0%; no completed status verified. RERA amenities
Green space / play
Description / sizeGreen strip / tot-lot / park; plan also lists Tot-lot 1–4 and Greenstrip 1–4
Evidence sourceRERA amenity register; building-permit plan
Declared progress / verified statusRERA register: “YES”, 0%; permit conditions require greenery and tot-lot. Completion not verified. RERA amenities
Water conservation
Description / sizeRainwater harvesting; permit records 1 rainwater-harvesting pit
Evidence sourceRERA amenity register; building-permit order
Declared progress / verified statusRERA register: “YES”, 0%; installation not verified. RERA amenities
Other listed facilities
Description / sizeInternal roads and footpaths; storm-water drains; street lighting; treatment/disposal of sewage and sullage; solid-waste management; energy management; fire protection and safety
Evidence sourceRERA amenity register
Declared progress / verified statusEach listed at 0%; completion not verified. RERA amenities
Electrical service space
Description / sizeElectrical meter room / sub-station / receiving station
Evidence sourceRERA amenity register; building-permit conditions
Declared progress / verified statusRERA register: “YES”, 0%; permit requires transformer space. Completion not verified. RERA amenities
  • The permit records 35 trees and requires a garbage house within the premises. These are approval-record provisions or conditions; the supplied evidence does not show that they have been delivered.

7. Utilities, building services & safety

  • The RERA amenity register marks water supply and sewerage as “YES” but records 0% progress. It does not identify a water source, storage or treatment capacity, or confirm completed connections. The permit calls for a rainwater-harvesting pit and a garbage house; the RERA amenity register likewise records rainwater harvesting at 0%. RERA amenities
  • The permit requires transformer space and lists sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be carried out under qualified technical supervision. The supplied material does not state the number or capacity of lifts, provide service-lift details, or confirm installation.
  • The permit conditions require fire-fighting and means-of-escape provisions, and state that an Occupancy Fire NOC is to be obtained before issue of an occupancy certificate. These are stated approval requirements; no Fire NOC, occupancy certificate or evidence of completed safety systems is supplied.

8. Location, access & connectivity

  • The registered location is Karimnagar urban, Karimnagar, Telangana, PIN 505001. The permit identifies the site as Laxmi Nagar, Karimnagar, on Sy. Nos. 483, 498 and 499. The RERA land record does not disclose a revenue village. RERA record Land records
  • The site boundaries recorded in the RERA project information are a 30 FEET WIDE ROAD on the east and a 50 FEET WIDE ROAD on the south. The building-permit plan records existing road width of 9.0 m and proposed road width of 15.0 m, and also lists 15m Wide Main Road, 9m Wide Main Road and 4.5m Wide Drive Way. The supplied record does not establish public-transport access or measured distances to local landmarks. RERA filing

9. Developer & development status

  • The registered promoter is NANDINI CONSTRUCTIONS, recorded as a partnership. Its supplied GSTIN is 36AATFN3728P1ZD. The registered address is H NO 1-5-414, NANDINI CONSTRUCTIONS, LAXMI NAGAR, LAXMINAGAR LOCALITY, WITHIN THE LIMITS OF KARIMNAGAR MUNICIPAL CORPORATION, KARIMNAGAR, Karimnagar urban, Karimnagar, 505001. No official website or contact details are supplied here. Corporate record RERA filing RERA filing
  • The filed Form B declaration, dated 28-04-2026, is made by authorized signatory PODDUTOORI ANURAG and undertakes completion on or before 18/03/2029. This is a promoter declaration, not an independent progress assessment.
  • The supplied evidence identifies one registered project building and no phase-wise construction schedule or independently verified progress report. No occupancy or completion certificate is supplied. The building-permit record requires a commencement notice before work begins and a completion notice and occupancy certificate before occupation.

10. Approvals, official records & documents

TG-RERA registration
Reference and scopeProject NANDINI ISHA, registration P02700010910; valid 18/03/2026–18/03/2029, unless extended
EvidenceForm C registration certificate
Building permit
Reference and scopeApproval no. 0084/KARI/SWBP/2026; file no. 011684/KARI/00133/SWBP/2025; dated 18/03/2026; Building A, Stilt + 5 Upper Floors, Sy. Nos. 483, 498 and 499
EvidenceBuilding Permit Order
Approval-plan record
Reference and scopeDTCP identified as authority; proposed plan and site/building parameters for the residential apartment
EvidenceFiled plan
Form B declaration
Reference and scopePromoter declaration, dated 28-04-2026, including completion undertaking and project-fund declarations
Occupancy / completion certificate
Reference and scopeNot supplied in the project documents reviewed for this Overview
EvidenceNo certificate identified in the supplied documents Document index

The building-permit record states that the permission does not confer ownership rights and sets conditions concerning commencement, construction in accordance with the sanctioned plan, surrender of the road-affected portion, parking use, completion notice and obtaining an occupancy certificate before occupation.

Frequently asked questions

Is NANDINI ISHA registered with Telangana RERA?

Yes. NANDINI ISHA is registered with the Telangana Real Estate Regulatory Authority as P02700010910; the registration status is New Project.

Who is the developer of NANDINI ISHA?

The promoter named in the RERA registration is NANDINI CONSTRUCTIONS.

Where is NANDINI ISHA located?

NANDINI ISHA is in KARIMNAGAR, Karimnagar urban, Telangana (505001).

When will NANDINI ISHA be completed?

The promoter's proposed date of completion filed with RERA is 18/07/2029. This is the promoter's declaration, not a guarantee.