Sairam Residency
GONE · Karimnagar · RERA P02700009570
SAIRAM RESIDENCY is a residential apartment project in Subhash Nagar locality, Karimnagar urban, Karimnagar district. The registered promoter is Gone Santosh Reddy. The project occupies 542.64 sq.m. and comprises one residential building, Building A, with 1 stilt + 5 upper floors and 10 3BHK units. It is registered under TG-RERA registration P02700009570, with a proposed completion date of 11/10/2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered name | SAIRAM RESIDENCY RERA record |
| Project type / use | Residential apartment project RERA record RERA filing |
| Phase / registered portion | No separate phase name or phase description is disclosed; registration is for the project. RERA record |
| TG-RERA registration | P02700009570 |
| Registration validity | 11 June 2024 to 11 June 2027, as stated on the certificate. This is the registration period, not the project completion deadline. Approvals record |
| Registered promoter | Gone Santosh Reddy; the RERA filing uses “GONE SANTOSH REDDY.” Corporate record |
| RERA status | Recorded as “On-Going Project”; registration certificate supplied. RERA record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / address | Subhash Nagar locality; within the limits of Karimnagar Municipal Corporation. RERA record RERA filing |
| Revenue village | “Within The Limits Of Karimnagar” is the RERA-filed village description; the approval document identifies the locality as Subhash Nagar, Karimnagar. A more specific revenue-village identification is not established in the supplied records. RERA record RERA filing |
| Mandal / district / PIN | Karimnagar urban / Karimnagar / 505001. RERA record RERA filing |
| Survey number(s) | SY NO 1372 (also written Sy.No. 1372); no subdivision is supplied. RERA record Land records |
| Registered site extent | 542.64 sq.m. in the filed land details and building approval. The Form-B declaration states 649.0A Sq.Yards or 542.64 Sq.Metres. RERA filing |
| Total / net land area | Total area 542.64 sq.m.; net area 542.64 sq.m.; affected area recorded as 0. RERA filing |
| Boundaries recorded by RERA | East: 30 FEET WIDE ROAD; west: 30 FEET WIDE ROAD; north: PLOT OF OTHERS; south: HOUSE OF PARANDHAMULU AND RAMASWAMY. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Karimnagar Municipal Corporation; the filing also identifies DTCP as the authority name for the plan approval. Approvals record |
| Principal building approval | 0075/BP/3011/2024, approved 11 June 2024. Related file number: 004934/BP/DTCP/3011/0081/2024. Approvals record |
| Building count and configuration | One residential building, Building A (A): 1 stilt + 5 upper floors. RERA filing |
| Approved built-up area | The approval records “Residential 5 upper floors Area (m2) 1,234.15”; it separately records stilt area 231.87, parking area 246.80, total proposed built-up area including parking 1480.95, total BUA 1491.67, deductions 10.72, and net BUA 1234.15. These are distinct approval entries and are retained as labelled in the document. |
| Height / parking level | Approval records Height (m): 14.95 and total height 20.24mt; it also records 14.95 mt excluding stilt and 17.99 mt from GL. The stilt is approved for parking. |
| Unit count | 10 units are recorded in the plan document and 10 units in the RERA unit information; the approval document describes one building. RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| RERA-filed configuration | 3BHK; 10 units. RERA unit table RERA unit details |
| RERA-filed saleable area | 153.38 sq.m. per unit. RERA unit table RERA unit details |
| Booked / available | 0 booked / 10 available in the portal data. The portal record has no as-of date, so these counts are indicative, not a current availability confirmation. RERA unit table RERA unit details |
| Construction stage | Project is recorded as “On-Going Project.” No independently verified site-progress assessment or percentage-complete figure is supplied. RERA record RERA amenities |
| Completion dates | RERA header: proposed completion 11/10/2027 and revised proposed completion 11/10/2027. Form-B declaration states completion on or before 711A612027, which appears malformed in the extracted text. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied in the reviewed records. The building approval requires an occupancy certificate before occupation. |
2. The project story
SAIRAM RESIDENCY is registered as a residential apartment project on Sy.No. 1372 in the Subhash Nagar locality, within Karimnagar Municipal Corporation limits. The RERA-filed site extent is 542.64 sq.m., with the site bounded by 30-foot-wide roads on the east and west. RERA record RERA filing
The approved scheme is a single building, Building A, with one stilt level and five upper residential floors. The record lists ten 3BHK units, with a RERA-filed saleable area of 153.38 sq.m. for each. The project is recorded as ongoing, but the supplied evidence does not establish the present construction progress through an independent site inspection or dated progress certificate. RERA unit table RERA record
The completion timeline in the RERA record is 11/10/2027. This is separate from the certificate’s registration validity, which runs to 11 June 2027. No occupancy or completion certificate is present in the supplied documents; the sanction requires one before occupation. RERA record
3. Master plan, architecture & building design
The building-permit record describes new RCC residential construction, with one building configured as 1 stilt + 5 upper floors. It records a site area of 542.64 sq.m., road-affected area of 0, net area of 542.64 sq.m., and a residential area entry of 1,234.15 sq.m. for the five upper floors.
The approval also lists a stilt area of 231.87 sq.m., parking area of 246.80 sq.m., total proposed built-up area including parking of 1480.95, total BUA of 1491.67, deductions of 10.72, and net BUA of 1234.15. These figures are reported as separate entries in the source; the available material does not provide a complete area schedule explaining their relationship.
The approval records Height (m): 14.95, while its plan extraction separately lists total height 20.24mt, 14.95 mt excluding stilt, and 17.99 mt from GL. No further height interpretation is supplied here.
The supplied plan data does not establish the floor-by-floor unit arrangement, number of flats per floor, lift or stair configuration, entrances, internal circulation, landscaping dimensions, or common-area schedule. The approval does specify a tot-lot and peripheral greenery as conditions to be maintained before occupancy certification.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 153.38 sq.m. | 71.2–118.2 sq.m.; median 109.9 sq.m. | 28% |
RERA records one 3BHK configuration with ten units and a saleable area of 153.38 sq.m. The booking and availability figures are from portal data with no supplied as-of date. RERA unit table RERA unit details
The carpet-area range and median are software measurements from approved floor-plan drawing geometry, not RERA-filed carpet-area disclosures; the measurement record says four flat designs were measured and notes that three need review. These measurements should be checked against the drawings. Saleable area and carpet area are different measures: the supplied drawing-measurement note says saleable area includes the home’s share of common areas and is larger than carpet area. Floor plans RERA unit details
For one measured flat design, the drawing extraction records living/dining dimensions of 4.57 × 6.86 m, kitchen 2.98 × 3.03 m, three bedrooms (including a master bedroom), three toilets, and a utility measuring 1.59 × 3.03 m. The utility is marked excluded from carpet area in that extraction. These are drawing-based measurements, not independently field-verified dimensions. RERA unit details
5. Parking & vehicle circulation
The approved building plan records a stilt parking level and a parking area of 246.80 sq.m. The commencement-certificate conditions state that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters.
A parking-space count, allocation by unit, visitor or accessible parking count, two-wheeler provision, driveway arrangement, ramp details, and pedestrian separation are not established in the supplied records. The building-permit conditions require electric-vehicle charging infrastructure in building parking areas under the cited technical requirements; the documents do not establish its installed status or capacity.
6. Amenities, recreation & open spaces
| Description / size | RERA amenity record marks available “YES”; no size supplied. The approval requires the tot-lot to be fenced and maintained as greenery before occupancy certification, and peripheral greenery to be maintained. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA-listed; completion is not independently verified. |
| Description / size | No facility description or size supplied; progress recorded as 0. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | No completion evidence supplied. |
| Description / size | No area supplied; progress recorded as 0. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | No completion evidence supplied. |
The amenity register also records internal roads and footpaths, street lighting, water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station. “YES” is recorded for water supply, sewerage, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station; the register records 0 progress for the other listed items. The register does not provide facility sizes or independently verified completion status. RERA amenities
7. Utilities, building services & safety
The RERA amenity register marks water supply, sewerage, water conservation/rainwater harvesting, and an electrical meter room/sub-station/receiving station as “YES.” It records no capacity, water source, storage volume, treatment specification, or service status beyond those entries. RERA amenities
The building approval requires a rainwater-harvesting structure and provides for transformer space. It also lists water supply and electricity connections among public amenities for which an occupancy certificate is required before provision. The approval does not establish that these services have been completed or connected.
Fire protection and fire-safety requirements appear in the RERA amenity register, with progress recorded as 0; no fire-system specification or clearance is supplied. The approval conditions state that sanitation, plumbing, fire-safety requirements, lifts, and electrical installations are to be executed under qualified technical personnel’s supervision, but do not give lift count or capacity, emergency-access details, or fire-equipment particulars. RERA amenities
The approval requires a garbage house within the premises and records the tot-lot and peripheral greenery conditions. No waste-segregation system, CCTV, access-control system, accessibility features, or installed backup-power details are established in the supplied records.
8. Location, access & connectivity
The registered location is H No. 3-6-496/2, Karimnagar urban, Karimnagar, PIN 505001, within the limits of Karimnagar Municipal Corporation. The project is identified in the RERA record as Sy.No. 1372, Subhash Nagar locality. RERA record RERA filing
The RERA-filed boundaries identify 30-foot-wide roads to the east and west. The supplied location record also contains a coordinate labelled “cadastral parcel centroid” at 17.41528, 78.35459. No public-transport details, travel times, or additional approach-route information are supplied. RERA filing Location record
9. Developer & development status
The registered promoter is Gone Santosh Reddy, identified in the registration certificate as the promoter and as son of Raji Reddy. The supplied records do not establish a legal entity type, company registration identifier, promoter website, or official project contact details. Corporate record
The Form-B filing is a promoter declaration. It states that the promoter has legal title to land described as 649.0A Sq.Yards or 542.64 Sq.Metres, declares the land free from encumbrances, and undertakes to complete by the date extracted as “711A612027.” The extracted date is malformed; the RERA header separately records proposed and revised completion dates of 11/10/2027. RERA record
The project is classified as ongoing, but no dated construction-progress percentage or independent site verification is supplied. Registration validity ends 11 June 2027 unless extended; that validity date is distinct from the recorded completion timeline of 11/10/2027. No occupancy certificate is supplied. RERA record
10. Approvals, official records & documents
| Identifier / date | P02700009570; valid 11/06/2024–11/06/2027 |
|---|---|
| What the supplied record establishes | Form ‘C’ certificate for SAIRAM RESIDENCY identifying Gone Santosh Reddy as promoter. |
| Identifier / date | 0075/BP/3011/2024; 11 June 2024 |
|---|---|
| What the supplied record establishes | Karimnagar Municipal Corporation approval for one residential building on Sy.No. 1372, with 1 stilt + 5 upper floors. Related file number: 004934/BP/DTCP/3011/0081/2024. |
| Identifier / date | LTP licence TS/024201/2024; sheet 1 / 1; 07-05-2024 |
|---|---|
| What the supplied record establishes | Plan document filed in the RERA record for the proposed residential building; it records extent 542.64 sq.m. and 10 units. |
| Identifier / date | Filed as “Commencement Certificates for each building in each phase” |
|---|---|
| What the supplied record establishes | Approval record states commencement notice is to be submitted before construction; no separate completion or occupancy certificate is supplied. |
| Identifier / date | Extracted declaration date “1t-a4-2425” |
|---|---|
| What the supplied record establishes | Promoter-declared title, encumbrance, project-account and completion undertakings; the extracted date and completion-date text are malformed. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | The building approval requires an occupancy certificate before occupation. |
1. Project at a glance
Project identity
Registered name: SAIRAM RESIDENCY
Project type / use: Residential apartment project
Phase / registered portion: No separate phase name or phase description is disclosed; registration is for the project.
TG-RERA registration: P02700009570
Registration validity: 11 June 2024 to 11 June 2027, as stated on the certificate. This is the registration period, not the project completion deadline.
Registered promoter: Gone Santosh Reddy; the RERA filing uses “GONE SANTOSH REDDY.”
RERA status: Recorded as “On-Going Project”; registration certificate supplied.
Land and geographic identity
Locality / address: Subhash Nagar locality; within the limits of Karimnagar Municipal Corporation.
Revenue village: “Within The Limits Of Karimnagar” is the RERA-filed village description; the approval document identifies the locality as Subhash Nagar, Karimnagar. A more specific revenue-village identification is not established in the supplied records.
Mandal / district / PIN: Karimnagar urban / Karimnagar / 505001.
Survey number(s): SY NO 1372 (also written Sy.No. 1372); no subdivision is supplied.
Registered site extent: 542.64 sq.m. in the filed land details and building approval. The Form-B declaration states 649.0A Sq.Yards or 542.64 Sq.Metres.
Total / net land area: Total area 542.64 sq.m.; net area 542.64 sq.m.; affected area recorded as 0.
Boundaries recorded by RERA: East: 30 FEET WIDE ROAD; west: 30 FEET WIDE ROAD; north: PLOT OF OTHERS; south: HOUSE OF PARANDHAMULU AND RAMASWAMY.
Development identity
Sanctioning authority: Karimnagar Municipal Corporation; the filing also identifies DTCP as the authority name for the plan approval.
Principal building approval: 0075/BP/3011/2024, approved 11 June 2024. Related file number: 004934/BP/DTCP/3011/0081/2024.
Building count and configuration: One residential building, Building A (A): 1 stilt + 5 upper floors.
Approved built-up area: The approval records “Residential 5 upper floors Area (m2) 1,234.15”; it separately records stilt area 231.87, parking area 246.80, total proposed built-up area including parking 1480.95, total BUA 1491.67, deductions 10.72, and net BUA 1234.15. These are distinct approval entries and are retained as labelled in the document.
Height / parking level: Approval records Height (m): 14.95 and total height 20.24mt; it also records 14.95 mt excluding stilt and 17.99 mt from GL. The stilt is approved for parking.
Unit count: 10 units are recorded in the plan document and 10 units in the RERA unit information; the approval document describes one building.
Offering and status
RERA-filed configuration: 3BHK; 10 units.
RERA-filed saleable area: 153.38 sq.m. per unit.
Booked / available: 0 booked / 10 available in the portal data. The portal record has no as-of date, so these counts are indicative, not a current availability confirmation.
Construction stage: Project is recorded as “On-Going Project.” No independently verified site-progress assessment or percentage-complete figure is supplied.
Completion dates: RERA header: proposed completion 11/10/2027 and revised proposed completion 11/10/2027. Form-B declaration states completion on or before 711A612027, which appears malformed in the extracted text.
Occupancy / completion certificate: No occupancy or completion certificate is supplied in the reviewed records. The building approval requires an occupancy certificate before occupation.
2. The project story
SAIRAM RESIDENCY is registered as a residential apartment project on Sy.No. 1372 in the Subhash Nagar locality, within Karimnagar Municipal Corporation limits. The RERA-filed site extent is 542.64 sq.m., with the site bounded by 30-foot-wide roads on the east and west.
The approved scheme is a single building, Building A, with one stilt level and five upper residential floors. The record lists ten 3BHK units, with a RERA-filed saleable area of 153.38 sq.m. for each. The project is recorded as ongoing, but the supplied evidence does not establish the present construction progress through an independent site inspection or dated progress certificate.
The completion timeline in the RERA record is 11/10/2027. This is separate from the certificate’s registration validity, which runs to 11 June 2027. No occupancy or completion certificate is present in the supplied documents; the sanction requires one before occupation.
3. Master plan, architecture & building design
The building-permit record describes new RCC residential construction, with one building configured as 1 stilt + 5 upper floors. It records a site area of 542.64 sq.m., road-affected area of 0, net area of 542.64 sq.m., and a residential area entry of 1,234.15 sq.m. for the five upper floors.
The approval also lists a stilt area of 231.87 sq.m., parking area of 246.80 sq.m., total proposed built-up area including parking of 1480.95, total BUA of 1491.67, deductions of 10.72, and net BUA of 1234.15. These figures are reported as separate entries in the source; the available material does not provide a complete area schedule explaining their relationship.
The approval records Height (m): 14.95, while its plan extraction separately lists total height 20.24mt, 14.95 mt excluding stilt, and 17.99 mt from GL. No further height interpretation is supplied here.
The supplied plan data does not establish the floor-by-floor unit arrangement, number of flats per floor, lift or stair configuration, entrances, internal circulation, landscaping dimensions, or common-area schedule. The approval does specify a tot-lot and peripheral greenery as conditions to be maintained before occupancy certification.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 153.38 sq.m. | 71.2–118.2 sq.m.; median 109.9 sq.m. | 28% |
RERA records one 3BHK configuration with ten units and a saleable area of 153.38 sq.m. The booking and availability figures are from portal data with no supplied as-of date.
The carpet-area range and median are software measurements from approved floor-plan drawing geometry, not RERA-filed carpet-area disclosures; the measurement record says four flat designs were measured and notes that three need review. These measurements should be checked against the drawings. Saleable area and carpet area are different measures: the supplied drawing-measurement note says saleable area includes the home’s share of common areas and is larger than carpet area.
For one measured flat design, the drawing extraction records living/dining dimensions of 4.57 × 6.86 m, kitchen 2.98 × 3.03 m, three bedrooms (including a master bedroom), three toilets, and a utility measuring 1.59 × 3.03 m. The utility is marked excluded from carpet area in that extraction. These are drawing-based measurements, not independently field-verified dimensions.
5. Parking & vehicle circulation
The approved building plan records a stilt parking level and a parking area of 246.80 sq.m. The commencement-certificate conditions state that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters.
A parking-space count, allocation by unit, visitor or accessible parking count, two-wheeler provision, driveway arrangement, ramp details, and pedestrian separation are not established in the supplied records. The building-permit conditions require electric-vehicle charging infrastructure in building parking areas under the cited technical requirements; the documents do not establish its installed status or capacity.
6. Amenities, recreation & open spaces
| Description / size | RERA amenity record marks available “YES”; no size supplied. The approval requires the tot-lot to be fenced and maintained as greenery before occupancy certification, and peripheral greenery to be maintained. |
|---|---|
| Declared progress / verified status | RERA-listed; completion is not independently verified. |
| Description / size | No facility description or size supplied; progress recorded as 0. |
|---|---|
| Declared progress / verified status | No completion evidence supplied. |
| Description / size | No area supplied; progress recorded as 0. |
|---|---|
| Declared progress / verified status | No completion evidence supplied. |
The amenity register also records internal roads and footpaths, street lighting, water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and an electrical meter room/sub-station/receiving station. “YES” is recorded for water supply, sewerage, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station; the register records 0 progress for the other listed items. The register does not provide facility sizes or independently verified completion status.
7. Utilities, building services & safety
The RERA amenity register marks water supply, sewerage, water conservation/rainwater harvesting, and an electrical meter room/sub-station/receiving station as “YES.” It records no capacity, water source, storage volume, treatment specification, or service status beyond those entries.
The building approval requires a rainwater-harvesting structure and provides for transformer space. It also lists water supply and electricity connections among public amenities for which an occupancy certificate is required before provision. The approval does not establish that these services have been completed or connected.
Fire protection and fire-safety requirements appear in the RERA amenity register, with progress recorded as 0; no fire-system specification or clearance is supplied. The approval conditions state that sanitation, plumbing, fire-safety requirements, lifts, and electrical installations are to be executed under qualified technical personnel’s supervision, but do not give lift count or capacity, emergency-access details, or fire-equipment particulars.
The approval requires a garbage house within the premises and records the tot-lot and peripheral greenery conditions. No waste-segregation system, CCTV, access-control system, accessibility features, or installed backup-power details are established in the supplied records.
8. Location, access & connectivity
The registered location is H No. 3-6-496/2, Karimnagar urban, Karimnagar, PIN 505001, within the limits of Karimnagar Municipal Corporation. The project is identified in the RERA record as Sy.No. 1372, Subhash Nagar locality.
The RERA-filed boundaries identify 30-foot-wide roads to the east and west. The supplied location record also contains a coordinate labelled “cadastral parcel centroid” at 17.41528, 78.35459. No public-transport details, travel times, or additional approach-route information are supplied.
9. Developer & development status
The registered promoter is Gone Santosh Reddy, identified in the registration certificate as the promoter and as son of Raji Reddy. The supplied records do not establish a legal entity type, company registration identifier, promoter website, or official project contact details.
The Form-B filing is a promoter declaration. It states that the promoter has legal title to land described as 649.0A Sq.Yards or 542.64 Sq.Metres, declares the land free from encumbrances, and undertakes to complete by the date extracted as “711A612027.” The extracted date is malformed; the RERA header separately records proposed and revised completion dates of 11/10/2027.
The project is classified as ongoing, but no dated construction-progress percentage or independent site verification is supplied. Registration validity ends 11 June 2027 unless extended; that validity date is distinct from the recorded completion timeline of 11/10/2027. No occupancy certificate is supplied.
10. Approvals, official records & documents
| Identifier / date | P02700009570; valid 11/06/2024–11/06/2027 |
|---|---|
| What the supplied record establishes | Form ‘C’ certificate for SAIRAM RESIDENCY identifying Gone Santosh Reddy as promoter. |
| Identifier / date | 0075/BP/3011/2024; 11 June 2024 |
|---|---|
| What the supplied record establishes | Karimnagar Municipal Corporation approval for one residential building on Sy.No. 1372, with 1 stilt + 5 upper floors. Related file number: 004934/BP/DTCP/3011/0081/2024. |
| Identifier / date | LTP licence TS/024201/2024; sheet 1 / 1; 07-05-2024 |
|---|---|
| What the supplied record establishes | Plan document filed in the RERA record for the proposed residential building; it records extent 542.64 sq.m. and 10 units. |
| Identifier / date | Filed as “Commencement Certificates for each building in each phase” |
|---|---|
| What the supplied record establishes | Approval record states commencement notice is to be submitted before construction; no separate completion or occupancy certificate is supplied. |
| Identifier / date | Extracted declaration date “1t-a4-2425” |
|---|---|
| What the supplied record establishes | Promoter-declared title, encumbrance, project-account and completion undertakings; the extracted date and completion-date text are malformed. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | The building approval requires an occupancy certificate before occupation. |
Frequently asked questions
Is SAIRAM RESIDENCY registered with Telangana RERA?
Yes. SAIRAM RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02700009570; the registration status is On-Going Project.
Who is the developer of SAIRAM RESIDENCY?
The promoter named in the RERA registration is GONE.
Where is SAIRAM RESIDENCY located?
SAIRAM RESIDENCY is in WITHIN THE LIMITS OF KARIMNAGAR MUNICIPAL CORPORATION, Karimnagar urban, Karimnagar, Telangana (505001).
When will SAIRAM RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 11/10/2027. This is the promoter's declaration, not a guarantee.