APARNA CYBERON is a residential apartment project in OSMAN NAGAR VILLAGE, RC PURAM, Sangareddy. It is being developed by APARNA CONSTRUCTIONS AND ESTATES PVT LTD on a registered site extent of 10,305.38 sq. m, with two residential blocks and an amenities block; the filed plan describes Block A as 2 Cellar + 1 Stilt + 10 upper floors, Block B as 1 Stilt + 10 upper floors, and the amenities block as 1 Ground + 2 upper floors. The TG-RERA filing records 160 3BHK units, each with saleable area of 157.64 sq. m. The project is registered under TG-RERA number P01100005168, and the promoter’s Form B declares completion by 22.06.2027.

More from Aparna Constructions And Estates Pvt Ltd · 18 projects →

01What we found

RegisteredTG-RERA - valid till 22 Jun 2027
22documents on file - each fact links to its page
1court case on this project's land (survey 28, 29, Osmannagar)
6items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project photoProject photoProject photoProject photo
▦ View all 6 photos
Osmannagar, Rc Puram, Sangareddy · geocoded — approximate.

1. Project at a glance

Project identity

FieldRecord
Registered project nameAPARNA CYBERON RERA record
Project type / useResidential apartment project; the filed plan also shows an amenities block. RERA record RERA filing
Registered portion / phaseRegistered as “APARNA CYBERON”; the filed plan describes the site as “Site - 2.”
TG-RERA registrationP01100005168, issued 13/10/2022; valid from 13/10/2022 to 22/06/2027, unless extended.
Registered promoterAPARNA CONSTRUCTIONS AND ESTATES PVT LTD RERA record Corporate record
RERA record statusRegistration certificate records the project as registered. The filing labels it “New Project”; an architect’s certificate and HMDA occupancy certificate subsequently record completion and occupancy certification for the identified buildings. RERA filing

Land and geographic identity

FieldRecord
Locality / revenue villageOSMAN NAGAR VILLAGE; also rendered “OSMANNAGAR” in the RERA header and certificate. RERA record
MandalRC PURAM in the RERA project identity; the project documents use Ramachandrapuram / Ramchandrapuram. RERA record RERA filing
DistrictSangareddy (also rendered “Sanga Reddy”). RERA record
PIN500036 in the project header and registration record. RERA record
Project survey numbers / subdivisionsSY.NO 28(P) and SY.NO 29(P); approval and occupancy records likewise identify 28/P and 29/P. RERA record
Registered site extentRERA land details: total area 10,305.38 sq. m, affected in road widening/FTL/Nala widening 339.26 sq. m, and net area 9,966.12 sq. m. RERA filing Land records
Boundaries in RERA filingEast: Village Boundary of Gopanpally; West: Road; North: land in Survey Nos. 28P and 29P; South: land in Survey No. 29P. RERA filing

Development identity

FieldRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA). Approvals record
Principal building approval005346/BP/HMDA/0778/SKP/2021, dated 23 June 2022 in the HMDA building-construction approval. Approvals record
Approved built-up areaHMDA occupancy record lists Block A 12,162.61 sq. m, Block B 12,431.59 sq. m, and Amenities Block 1,324.43 sq. m. The separate RERA plan records a built-up-area figure of 28,673.13 and residential net BUA 24,594.20 plus commercial net BUA 1,324.43. These labels are kept as recorded; they are not interchangeable area measures.
Building arrangement and approved floorsTwo residential blocks and an amenities block. The filed plan describes Block A as 2 Cellar + 1 Stilt + 10 upper floors, Block B as 1 Stilt + 10 upper floors, and the amenities block as 1 Ground + 2 upper floors. The occupancy record lists Block B with two cellar floors; see the recorded building configuration in the source documents.
ParkingFiled plan states 208 proposed parkings and designates cellar/stilt floors for parking. It does not provide a verified breakdown of parking types or unit allocations.
Unit countsRERA filing records 160 3BHK units. RERA unit table RERA unit details

Offering and status

FieldRecord
RERA-filed configuration3BHK; saleable area 157.64 sq. m per unit. RERA unit table RERA unit table
Booked / available101 booked / 59 available as last read from the TG-RERA portal; no as-of date is supplied, so counts are indicative. RERA unit table
Construction / completion statusRERA header’s completeness field is 70%, with no as-of date stated. Separately, an architect’s certificate dated 18.03.2026 certifies completion, and HMDA’s occupancy certificate records completion on 20/01/2026 and issue on 11/03/2026 for the listed buildings. RERA record
Completion undertakingPromoter’s Form B declares completion by 22.06.2027. This is the filed undertaking; registration validity ends on the same date unless extended.
Occupancy certificate scopeHMDA OC 014591/HMDA/04118/SWOC/SKP2/2026 identifies Blocks A and B and the Amenities Block at Survey Nos. 28(P) and 29(P).

2. The project story

Aparna Cyberon is registered as a residential apartment project on the RERA-identified land in Osman Nagar Village, RC Puram, Sangareddy district. Its filed building plan organizes the development into two residential blocks and a separate amenities block. The RERA inventory records 160 3BHK apartments; the available portal snapshot lists 101 booked and 59 available, without an as-of date. RERA record RERA filing RERA unit table

The project’s documents present both a completion undertaking and later completion evidence: the promoter’s 2022 Form B states a completion target of 22.06.2027, while an architect’s certificate dated 18.03.2026 certifies overall completion and HMDA’s OC records the buildings as fit for occupation. The header also reports 70% completeness, but does not date that figure. It should therefore be read as a portal field, not as independent current-site verification. RERA record

3. Master plan, architecture & building design

The RERA-filed plan identifies a minimum plot area of 10,305.38 sq. m, a road-affected area of 339.26 sq. m, and net plot area of 9,966.12 sq. m. It records proposed coverage of 3,445.95 sq. m (34.58%), vacant plot area of 6,520.17 sq. m, residential net BUA of 24,594.20, commercial net BUA of 1,324.43, and built-up area of 28,673.13.

The filed plan shows Block A with two cellar levels, a stilt and ten upper floors; Block B with a stilt and ten upper floors; and an amenities block with a ground floor and two upper floors. The HMDA occupancy record describes Block A and Block B with two cellar floors, one stilt floor and ten upper floors, and the Amenities Block with two cellar floors, a ground floor and two upper floors. The source documents therefore provide different floor descriptions for Block B and the amenities block; this overview preserves each document’s stated configuration rather than resolving it.

The occupancy record gives building heights of 29.7 metres for Blocks A and B and 11.65 metres for the Amenities Block. It records zero deviated built-up area for each of the three blocks. The filed plan identifies a proposed coverage area and vacant plot area, but does not provide a sufficiently detailed landscape or open-space plan in the supplied extraction to describe its internal arrangement.

The project-specific environmental clearance document supplied here concerns Aparna Cyberzed, not the registered Aparna Cyberon project, and is not used to describe Cyberon’s approved design.

4. Homes, configurations & floor plans

The TG-RERA filing records 160 3BHK units, each with saleable area of 157.64 sq. m. The plan-drawing software measurement for 3BHK layouts is not a RERA disclosure and is a drawing-based estimate requiring review. Saleable area and measured carpet area are different measures; the supplied record states that saleable area includes a share of common areas. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK16010159157.64 sq. m88.7–143.1 sq. m (software-measured drawing range; median 112.5 sq. m)29% (software-derived)

The drawing review measured 30 3BHK designs from the filed plan, with 13 marked as needing review. One typical 3BHK drawing includes three bedrooms, a living/dining area, kitchen, toilets, balcony and utility. For the illustrated unit, the software lists bedroom dimensions of 3.66 × 3.66 m, 3.66 × 3.96 m and 3.65 × 5.14 m; a living/dining area of 7.41 × 8.9 m; kitchen of 2.44 × 3.71 m; and a 1.32 × 3.88 m balcony and utility. These are drawing measurements, not RERA-filed unit specifications. RERA unit details Floor plans

5. Parking & vehicle circulation

The filed plan states 208 proposed parkings and identifies cellar/stilt floors for parking; its conditions say these floors are to be used for parking only. The HMDA approval also specifies parking use for cellar/stilt areas. The supplied information does not establish a resident/visitor/accessible-space breakdown, parking allocation by apartment, mechanical parking, EV charging, or a verified parking-space-per-home figure. A depicted parking bay is not evidence of exclusive ownership or a particular buyer’s allocation.

The plan identifies a 12.00 MT wide existing road and a 30.00 MT wide proposed road. The HMDA approval records minimum access-road clearance dimensions of 4.5 m width and 5 m height; the supplied extracts do not describe internal driveway circulation or pedestrian separation.

6. Amenities, recreation & open spaces

The filed plan names project facilities, while the RERA amenities record gives completion percentages for selected infrastructure items. Those percentages are promoter/RERA-recorded progress fields, not independent inspection results. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
ClubhouseNamed in the filed plan; no size supplied.Architect’s certificate refers to a “Club House”; no separate independent facility inspection supplied.
Tot lot / green stripNamed in the filed plan.Green Strip/TOT LOT/Park listed at 95%; not independently verified. RERA amenities
Community buildingsCommunity Buildings listed in RERA amenities record.RERA amenities85%; not independently verified.
Recreational open spaceAggregate area of recreational open space listed.RERA amenities90%; area not supplied and not independently verified.
Internal roads and footpathsListed in RERA amenities record.RERA amenities100%; not independently verified.
Street lightingListed in RERA amenities record.RERA amenities100%; not independently verified.

The plan also names a Society Room and Drivers Room, but supplies no dimensions or completion status for either.

7. Utilities, building services & safety

The filed plan names an STP of 225.00 KL, a pump house/motor room, generator room, distribution transformer, BMS room, communication room and visitors parking. It also identifies greenery and a clubhouse. These are plan-listed facilities; the available material does not establish their current operating status or provide water-source, storage, treatment-process, generator-capacity, lift, CCTV-system or EV-charging specifications.

The RERA amenities record lists water supply, sewerage and STP, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, rainwater harvesting, energy management and fire protection/fire-safety requirements. Most are recorded at 100%, with electrical meter room/sub-station/receiving station at 95%; “Sewage Treatment Process” is recorded at 0%. These are portal progress fields, not independent verification of completed or compliant systems. RERA amenities

The HMDA approval places responsibility for structural and fire safety on the owner/builder and technical professionals, requires rainwater-harvesting structures, and states that an occupancy certificate is required before occupation. The supplied material does not include evidence establishing actual performance or current compliance of each system.

8. Location, access & connectivity

The registered location is Osman Nagar Village, RC Puram, Sangareddy district, PIN 500036. The RERA-filed site boundaries identify Gopanpally village boundary to the east and a road to the west. RERA record RERA filing

The location record identifies the nearest sampled Outer Ring Road interchange at approximately 7.0 km. No public-transport details, route measurements or travel-time evidence are supplied. The promoter’s website description of “Osman Nagar, Hyderabad” is not used to replace the registered revenue location. Location record Promoter website

9. Developer & development status

The registered legal promoter is APARNA CONSTRUCTIONS AND ESTATES PVT LTD, a private limited company. The supplied corporate record gives GSTIN 36AADCA1031D1ZH. The project filing names Sannareddy Subramanyam Reddy as Managing Director and authorized signatory. The registration certificate lists a promoter office at Punja Gutta, Khairtabad, Hyderabad, PIN 500034; the project header separately records an address at Astral Heights, Road No. 1, Tellapur Municipality, Osman Nagar Village, RC Puram, Sangareddy, PIN 500036. Corporate record Parties record RERA record

The promoter’s Form B, dated 13 September 2022, declares legal title to the project land, states that the land is free from encumbrances, and undertakes completion by 22.06.2027. These are promoter declarations in the RERA filing. The architect’s certificate dated 18.03.2026 certifies completion, and HMDA’s OC records the identified buildings as fit for occupation.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01100005168; issued 13/10/2022; valid to 22/06/2027 unless extended
Scope and evidenceAPARNA CYBERON; Survey Nos. SY.NO 28(P) and SY.NO 29(P).
RERA-filed plan
Identifier / dateApproval no. TS/061564/2021; dated 09-12-2021 in the extraction
Scope and evidencePlan for proposed residential apartments “APARNA CYBERON” Site - 2; Survey Nos. 28(P) and 29(P). The supplied extraction does not provide a readable sanctioning authority or readable approval stamp.
HMDA building-construction approval
Identifier / date005346/BP/HMDA/0778/SKP/2021; 23 June 2022
Scope and evidenceApproval for buildings on Survey Nos. 28/P and 29/P, Osman Nagar.
Form B declaration
Identifier / date13 September 2022
Scope and evidencePromoter declaration of title, encumbrance status, fund handling and completion undertaking.
HMDA occupancy certificate
Identifier / date014591/HMDA/04118/SWOC/SKP2/2026; issued 11/03/2026; completion date recorded as 20/01/2026
Scope and evidenceBlocks A and B and Amenities Block; Survey Nos. 28(P) and 29(P).
Architect’s completion certificate (Form 1A)
Identifier / date18.03.2026
Scope and evidenceCertifies overall completion of the registered project and lists occupancy-certificate references for Block-A, Block-Br, Club House and Building.
Project-specific environmental document supplied
Identifier / dateEC26B3813TG5980846N; 17/03/2026
Scope and evidenceThe supplied record identifies Aparna Cyberzed, not Aparna Cyberon; it is not treated here as a Cyberon project clearance.

The HMDA occupancy record lists zero deviated built-up area for Block A, Block B and the Amenities Block. The full approval conditions and title/encumbrance analysis are addressed in their respective report sections.

Frequently asked questions

Is APARNA CYBERON registered with Telangana RERA?

Yes. APARNA CYBERON is registered with the Telangana Real Estate Regulatory Authority as P01100005168; the registration status is New Project.

Who is the developer of APARNA CYBERON?

The promoter named in the RERA registration is APARNA CONSTRUCTIONS AND ESTATES PVT LTD.

Where is APARNA CYBERON located?

APARNA CYBERON is in OSMAN NAGAR VILLAGE, OSMANNAGAR, RC PURAM, Sangareddy, Telangana (500036).

When will APARNA CYBERON be completed?

The promoter's proposed date of completion filed with RERA is 22/06/2027. This is the promoter's declaration, not a guarantee.