Sign in

Green Fields Realestate

KANDADI · Nagarkurnool · RERA P01600009376

GREEN FIELDS REALESTATE is a plotted development in Kalwakurthy Revenue Village, Kalwakurthy Mandal, Nagarkurnool District. The registered promoter is Mr./Ms. Kandadi Kalpana. The RERA records a land area of 26,952.90 sq. m, and the tentative layout approval records 97 plots, with plot areas of 51.04–246.38 sq. m; building or floor configurations are not disclosed. The project is registered under TG-RERA number P01600009376, with a proposed completion date of 12/04/2025.

01What we found

Period endedTG-RERA registration ran to 12 Apr 2025 - check its extension on TG-RERA
16documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Kalwakurthy, Kalwakurthy, Nagarkurnool · geocoded — approximate.

1. Project at a glance

Project identity

ItemRecord
Registered project nameGREEN FIELDS REALESTATE RERA record
Project typePlotted development RERA record RERA filing
Phase / registered portionNo phase name or separate phase description is disclosed; the registration is for this plotted project. RERA record
TG-RERA registration numberP01600009376 RERA record
Registration validity12/03/2022 to 12/04/2025; the supplied certificate records no extension. This is registration validity, not a completion certificate. RERA record
Registered promoterMr./Ms. Kandadi Kalpana on the TG-RERA certificate; Form B is declared by Ms. Kandadi Kalpana.
RERA statusRecorded as “On-Going Project.” RERA record RERA filing

Land and geographic identity

ItemRecord
LocalityKalwakurthy / KALWAKURTHY RERA record
Revenue villageKalwakurthy Revenue Village
MandalKalwakurthy RERA record
DistrictNagarkurnool RERA record
PIN509324 RERA record
Project survey identificationSY NO 100 P; the layout work-completion certificate identifies 100/Part. RERA record
Registered site extent26,952.90 sq. m in the RERA land details. The tentative layout approval states 6 Acer 26.41 Gts / 32,236 Sq. Yds. RERA filing
Net / total areaRERA records total area and net area as 26,952.90 sq. m. RERA filing Land records
BoundariesEast, west, north and south: “NEIGHBOURS LAND.” RERA filing

Development identity

ItemRecord
Sanctioning authority / principal approvalKalwakurthy Municipality/Municipal Corporation; Tentative Layout Plan No. 0010/LO/3061/2022, approved 12 March 2022.
Approved built-up area12,715.45 sq. m, as recorded in the RERA fields. RERA filing
Plots / arrangementTentative layout approval records 97 plots.
Building count / floor configurationNot disclosed as a multi-building or floor-based development; the approval states only detached dwelling houses designed for occupation by a single family are to be built on a site.
Parking provisionThe approval’s land-use schedule records 0% common parking space. No parking-space count or individual plot parking allocation is supplied.

Offering and status

ItemRecord
Unit typePlots in a plotted residential layout; the approval records 97 plots.
Plot size rangeSoftware-read from the approved layout drawing: 51.04–246.38 sq. m (61.0–294.7 sq. yd); verify against the drawing. Layout record
Booked / available plotsNot established by the supplied current inventory. A filed declaration says plots 6, 14, 15, 18, 39, 57, 78 and 79 had been sold, but it does not establish current booking or availability.
Development stageA municipal Work Completion Certificate dated 25.10.2023 states that layout works and listed infrastructure were completed. This is not an occupancy certificate for homes or proof that individual houses have been built.
Completion datesThe TG-RERA fields state proposed and revised completion as 12/04/2025. The Form B affidavit separately records an undertaking to complete by 11-Mar-2024. RERA filing
Occupancy certificate statusNo project-level occupancy certificate for houses is supplied. The supplied work-completion certificate is for layout infrastructure.

2. The project story

  • GREEN FIELDS REALESTATE is registered as a plotted development in Kalwakurthy Revenue Village, Kalwakurthy Mandal, Nagarkurnool District. The registered land is identified as SY NO 100 P; the municipality’s layout work-completion certificate refers to 100/Part. RERA record
  • The approved layout provides 97 plots, with internal roads and land reserved for parks/open space, social infrastructure, utilities and roads. It is a layout for future detached single-family dwellings, rather than a RERA-recorded apartment or multi-storey housing scheme. The supplied record does not establish that individual houses have been constructed.
  • The municipality issued a Work Completion Certificate for layout works dated 25.10.2023, stating that specified infrastructure works had been completed. This certifies layout works as described in that document; it should not be read as an occupancy certificate for homes or as independent confirmation of present on-site condition.

3. Master plan, architecture & building design

This is a plotted layout, so the relevant design evidence is the layout plan and its land-use schedule rather than building or floor plans. The tentative layout approval identifies a site extent of 6 Acer 26.41 Gts / 32,236 Sq. Yds and 97 plots.

The layout drawing’s software-read plot schedule records 97 plots, with plot areas from 51.04 sq. m to 246.38 sq. m; the plot-count and size readings should be checked against the drawing. Layout record The RERA land details record a net layout area of 26,952.90 sq. m. RERA filing

Layout land useArea / share recorded in the approval
Plotted area3 Acer 5.68 Gts / 15,208 Sq. Yds; 47.18%
Roads2 Acer 2.93 Gts / 10,034 Sq. Yds; 31.13%
Open space (park)0 Acer 24.35 Gts / 2,946 Sq. Yds; 9.14%
Social infrastructure0 Acer 16.5 Gts / 1,996 Sq. Yds; 6.19%
Utilities0 Acer 2.66 Gts / 322 Sq. Yds; 1%
Common parking space0 Sq. Yds; 0%
Mortgage area, identified as part of plotted area0 Acer 20.75 Gts / 2,511 Sq. Yds; 16.46%

The RERA fields also record approved built-up area of 12,715.45 sq. m. This is not the same measure as the layout’s plotted land area. No building arrangement, building footprints, heights, floor configurations, or housing-plan details are supplied. RERA filing Document index

4. Homes, configurations & floor plans

The RERA-filed offering is a plotted layout, not a configuration of flats. The tentative layout approval records 97 plots. Plot areas below are software-read from the approved layout drawing, not RERA-filed saleable-area figures; check the drawing for plot-specific details. Layout record

Plot informationFigure
Total plots97
Smallest plot51.04 sq. m / 61.0 sq. yd Layout record
Median plot125.31 sq. m / 149.9 sq. yd Layout record
Largest plot246.38 sq. m / 294.7 sq. yd Layout record

The drawing-derived size bands are: 4 plots in 0–100 sq. yd, 65 in 100–150 sq. yd, 14 in 150–200 sq. yd, 12 in 200–250 sq. yd and 2 in 250–300 sq. yd. Layout record No current booked/available count or plot-by-plot inventory is supplied. No floor-plan or measured carpet-area record applies to the plotted offering. Floor plans

5. Parking & vehicle circulation

The layout approval allocates 0% of site area to common parking space; no count of common, visitor, accessible or plot-specific parking bays is supplied. The approval records roads, while the vendor data mentions internal roads and footpaths; no road widths, vehicle entry/exit details, dedicated pedestrian separation, EV charging provision or parking-allotment arrangements are established in the supplied records. Promoter website

6. Amenities, recreation & open spaces

The layout approval includes land reserved for open space, social infrastructure and utilities. It also specifies infrastructure works and amenities; the municipal work-completion certificate states that listed works had been completed. The table distinguishes approval conditions from the completion status stated by the municipality.

Park / open space
Description / size0 Acer 24.35 Gts / 2,946 Sq. Yds; 9.14% of the layout
Evidence sourceTentative layout approval
Declared progress / verified statusReserved by approval; the work-completion certificate reports greenery/planting in earmarked public open spaces.
Social infrastructure land
Description / size0 Acer 16.5 Gts / 1,996 Sq. Yds; 6.19%
Evidence sourceTentative layout approval
Declared progress / verified statusLand reservation recorded; no specific facility or delivered building is identified.
Utilities land
Description / size0 Acer 2.66 Gts / 322 Sq. Yds; 1%
Evidence sourceTentative layout approval
Declared progress / verified statusLand reservation recorded; no facility-specific completion evidence.
Greenery / avenue plantation
Description / sizeNo quantity supplied
Evidence sourceMunicipal work-completion certificate
Declared progress / verified statusCertificate states greenery, including avenue plantation, was undertaken.

No clubhouse, indoor recreation facility, sports facility or community building is established in the supplied project evidence. The amenities record shows community buildings at 0%. RERA amenities

7. Utilities, building services & safety

  • The tentative layout approval specifies a water reservoir, septic tank, sewage treatment plant, electric transformer, solid-waste management and common parking space in its amenities/utilities list. The conditions also require street lighting and electricity facilities, sewerage disposal and protected water supply. These are approval-record requirements or listed provisions; the approval’s separate land-use schedule records 0% common parking space.
  • The municipal Work Completion Certificate states that street lighting and electricity facilities were provided, sewerage disposal and protected water supply were extended to the layout, and roads, drains and rainwater-harvesting works were addressed. It does not provide capacities, operating details or current-condition testing.
ServiceEvidence and status
WaterProtected water supply is required by the approval conditions and reported extended in the municipal work-completion certificate. Source, storage capacity and treatment details are not supplied.
Sewerage / drainageThe approval lists a septic tank and sewage treatment plant; the completion certificate reports sewerage disposal provision. No capacity, reuse scheme or storm-water drainage specification is supplied.
Rainwater / storm waterThe completion certificate refers to nala channelisation and rainwater-harvesting pits, but does not give a pit count.
ElectricalThe approval lists an electric transformer; the completion certificate reports street lighting and electricity facilities. Supply capacity and backup details are not disclosed.
WasteThe approval’s amenities/utilities list includes solid-waste management. No operating or completion particulars are supplied.
Fire / life safety, lifts and accessibilityNo project-specific evidence supplied for fire systems, lifts, ramps or accessible circulation. Document index

8. Location, access & connectivity

The registered location is Kalwakurthy, Nagarkurnool District, Telangana, PIN 509324; the revenue location is Kalwakurthy Revenue Village, Kalwakurthy Mandal. RERA record RERA filing The supplied cadastral parcel centroid is 16.68238291484037, 78.48663562618265. Cadastral map

The nearest sampled Outer Ring Road interchange is listed at approximately 61.2 km. Location record No project-specific approach-road description, public-transport information or additional measured landmark distances are supplied.

9. Developer & development status

The TG-RERA certificate identifies the promoter as Mr./Ms. Kandadi Kalpana, and the filed Form B declaration is made by Ms. Kandadi Kalpana. The entity type, company-registration details and official website or contact information are not established in the supplied records. Corporate record

The municipal work-completion certificate names Kandadi Kalpana as the applicant and reports completion of listed layout works. The TG-RERA project fields record proposed and revised completion as 12/04/2025; the Form B affidavit records a completion undertaking of 11-Mar-2024. RERA filing The supplied records do not establish construction or occupancy certification for houses on the plots.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01600009376; valid 12/03/2022–12/04/2025
What it establishesRegistration of GREEN FIELDS REALESTATE as a project under section 5; the certificate records no extension.
Tentative layout approval
Identifier / date0010/LO/3061/2022; 12 March 2022
What it establishesTentative layout approval for land in Sy. No. 100 P, Kalwakurthy Revenue Village; records 97 plots, land-use allocations and conditions. The document states that tentative layout approval is not proof of land title.
Layout work-completion certificate
Identifier / dateDTLP No. 10/LO/3061/2022; 25.10.2023
What it establishesKalwakurthy Municipality certificate reporting completion of listed layout works for Survey No. 100/Part; it is not an occupancy certificate for homes.
Form B affidavit-cum-declaration
Identifier / dateDated 28-January-2025
What it establishesPromoter declaration including a title basis, encumbrance statement and completion undertaking.
Approved layout drawing
Identifier / dateDocument 533297 Layout record
What it establishesDrawing-derived plot schedule and land-use reading; plot measurements are software-read and should be checked against the drawing.
Other certificate in RERA file
Identifier / dateApproval no. 000216/LO/Plg/HMDA /2021; document 661286
What it establishesThe supplied certificate concerns SINGAPUR TOWN, PRANEETA DEVELOPERS and registration P02400003349; it does not identify GREEN FIELDS REALESTATE as the project.

Frequently asked questions

Is GREEN FIELDS REALESTATE registered with Telangana RERA?

Yes. GREEN FIELDS REALESTATE is registered with the Telangana Real Estate Regulatory Authority as P01600009376; the registration status is On-Going Project.

Who is the developer of GREEN FIELDS REALESTATE?

The promoter named in the RERA registration is KANDADI.

Where is GREEN FIELDS REALESTATE located?

GREEN FIELDS REALESTATE is in KALWAKURTHY, Nagarkurnool, Telangana (509324).

When will GREEN FIELDS REALESTATE be completed?

The promoter's proposed date of completion filed with RERA is 12/04/2025. This is the promoter's declaration, not a guarantee.

More projects in Kalwakurthy