Rk Towers
RK POLA CONSTRUCTIONS AND DEVELOPERS · Suryapet · RERA P01900004292
RK TOWERS is a residential apartment project in VIDYA NAGAER, Suryapet mandal, Suryapet district, developed by the registered promoter RK POLA CONSTRUCTIONS AND DEVELOPERS. The project occupies 666.45 m² and comprises one building, Building - A (RESI), with 1 Stilt + 5 upper floors. TG-RERA records 10 3BHK units, each with a saleable area of 88.21 m². Its TG-RERA registration is P01900004292, and the proposed completion date is 28/01/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Fact | Project record |
|---|---|
| Registered name | RK TOWERS RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | Phase is not separately identified in the supplied record; the registration is for RK TOWERS RERA record |
| TG-RERA registration | P01900004292 |
| Registration validity | Certificate states valid from 24/03/2022 to 28/01/2025; extension status is not shown as extended in the supplied certificate |
| Registered promoter | RK POLA CONSTRUCTIONS AND DEVELOPERS |
| RERA status in supplied record | Registration certificate issued under section 5; certificate validity ended on 28/01/2025. No extension is recorded in the supplied certificate |
Land and geographic identity
| Fact | Project record |
|---|---|
| Locality / address | VIDYA NAGAER, Ward No. 1, Suryapet RERA record RERA filing |
| Revenue village | Bechirag Madharam is named in the title documents; the RERA filing also records Ward No. 1. The supplied records do not reconcile these as revenue-village identifiers RERA filing |
| Mandal / district / PIN | Suryapet / Suryapet / 508213 RERA record |
| Project survey number(s) | Survey No. 281; no project subdivision is recorded Land records |
| Registered site extent | 666.45 m² |
| Total / net area | Total area 666.45 m²; net area 666.45 m² RERA filing |
| Boundaries in RERA filing | East: 30 FT ROAD; West: 30 FT ROAD; North: HOUSE OF DR M SURENDRA AND PLACE OF VUPPU RAMESH; South: HOUSE OF GUTHA SUDHARSHAN REDDY RERA filing |
Development identity
| Fact | Project record |
|---|---|
| Sanctioning authority | Suryapet Municipality/Municipal Corporation |
| Principal building approval | 0009/BP/3049/2022, approved 28 January, 2022 |
| Related file number | 003621/BP/DTCP/3049/0013/2021 |
| Approved built-up area | 1,526.25 m² in the RERA filing RERA filing |
| Building count / configuration | One building, Building - A (RESI); sanctioned as 1 Stilt + 5 upper floors RERA filing |
| Sanctioned height | 14.99 m |
| Approved unit count | 10 3BHK units recorded in the TG-RERA unit data RERA unit table RERA unit details |
| Parking provision | Sanctioned plan identifies stilt parking; the supplied approval extract does not state a car-space count |
Offering and status
| Fact | Project record |
|---|---|
| RERA-filed configuration | 3BHK, 10 units RERA unit table RERA unit details |
| RERA-filed saleable area | 88.21 m² per unit RERA unit table RERA unit details |
| Booked / available | 0 booked / 10 available, as last read from the TG-RERA portal; the record has no as-of date, so counts are indicative RERA unit table |
| Construction stage | No project-specific construction progress percentage or independently verified site status is supplied. TG-RERA amenity entries show 0% progress for the listed items RERA amenities |
| Completion deadline | Promoter’s Form B declares completion by 28/01/2025; the TG-RERA certificate also ends on that date |
| Revised completion date | No revised completion date is recorded in the supplied evidence |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents Document index |
2. The project story
RK TOWERS is registered with TG-RERA as a residential apartment project on Survey No. 281 in Suryapet. The filing identifies a 666.45 m² site and one residential building. The building permit describes Building A as a stilt-and-five-upper-floor apartment building. RERA record Land records
The TG-RERA unit record lists ten 3BHK apartments, all shown as available and none booked; this is a portal snapshot with no recorded as-of date. The supplied evidence does not establish the current physical construction stage, completion of any building portion, or an occupancy certificate. The amenity progress entries are recorded as 0%; they are portal declarations, not an independent site inspection. RERA unit table RERA amenities
The promoter’s Form B affidavit undertakes completion by 28/01/2025. That date is also the end date stated on the registration certificate. The supplied certificate shows no extension, and no revised completion date or completion/occupancy certificate is provided. Document index
3. Master plan, architecture & building design
The supplied building approval describes one residential block, Building A, on a site of 666.45 m², with 1 stilt + 5 upper floors and a sanctioned height of 14.99 m. The RERA filing records approved built-up area as 1,526.25 m². The building-permit extract separately lists residential area 1,523.70 and stilt area 291.56; units for those two figures are not stated in the extracted text, so they are not treated here as comparable area measurements. RERA filing
The approval extract records 5% open space. It also identifies a 4.5mts. road width and lists a transformer space and garbage house among site provisions. The supplied material does not include a drawing-derived building footprint, detailed floor plans, flats-per-floor arrangement, lift or stair count, internal circulation plan, or a phase-by-phase layout. Document index
The RERA filing records 162.99 m² as mortgage area. This is a filed area entry, not a measure of the saleable or carpet area of an individual home. RERA filing
4. Homes, configurations & floor plans
TG-RERA records ten 3BHK units with a filed saleable area of 88.21 m² each; the portal snapshot shows none booked and all ten available, without an as-of date. No measured carpet-area figure is supplied. Although two drawings were processed, no flat designs were measured for the 3BHK configuration; therefore no drawing-based room dimensions or carpet measurement can be reported. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 88.21 m² | Not measured in supplied drawing record | Not supplied |
Saleable area is the RERA-filed unit figure. The supplied floor-plan record explains that drawing-measured carpet area, where available, is a software measurement and differs from saleable area, which includes the home’s share of common areas. No carpet, balcony, utility, or loading figures are available for these units. RERA unit details Floor plans
5. Parking & vehicle circulation
The building approval states that the approved cellar/stilt areas for parking must be used exclusively for vehicle parking and not partitioned. The extract does not provide a sanctioned parking-space count, vehicle-type breakdown, visitor or accessible-space allocation, or a unit-wise parking allocation.
The RERA filing records 162.99 m² as mortgage area, but does not identify this as a parking allocation. No evidence establishes exclusive ownership or allocation of any drawn or described parking bay. RERA filing Document index
6. Amenities, recreation & open spaces
The following amenity entries appear in the TG-RERA portal data. All listed progress values are 0%; this is portal-recorded progress, not independently verified completion status. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | No size stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Green strip / tot lot / park | No size stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Community buildings | No size stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Aggregate recreational open space | No size stated in the amenity entry; approval records 5% open space | TG-RERA amenity record RERA amenities; building approval | 0% in portal record; not independently verified |
| Water supply | No source or capacity stated | TG-RERA amenity record RERA amenities | Listed “YES”; 0%; not independently verified |
| Sewerage / treatment and disposal of sewage and sullage | No plant capacity stated | TG-RERA amenity record RERA amenities | Listed “YES” for sewerage; both entries show 0%; not independently verified |
| Storm-water drains | No size stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Water conservation / rainwater harvesting | No capacity stated | TG-RERA amenity record RERA amenities | Listed “YES”; 0%; not independently verified |
| Solid-waste management and disposal | No capacity stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Street lighting | No details stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Energy management | No details stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Fire protection and fire-safety requirements | No system details stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
| Electrical meter room / substation / receiving station | No capacity stated | TG-RERA amenity record RERA amenities | 0%; not independently verified |
The building approval also requires a transformer space and garbage house and refers to tot-lot/greenery provisions where applicable. These are approval conditions, not evidence that the facilities have been delivered.
7. Utilities, building services & safety
The TG-RERA amenity record lists water supply, sewerage, and water conservation/rainwater harvesting as “YES,” but provides no source, capacity, design detail, or evidence of completion. Sewerage and treatment/disposal are listed without an STP capacity or reuse details. RERA amenities
The building approval identifies transformer space, a garbage house, and parking use for the approved stilt/cellar areas. It states that plumbing, sanitation, fire safety, lifts, and electrical installations are to be executed under qualified technical supervision, and assigns structural and fire-safety responsibility to the owner, builder/developer and technical professionals. These are approval requirements; the supplied evidence does not establish completed installations, statutory clearances, or operational status.
No lift count or capacity, backup-power arrangement, CCTV or access-control system, waste-segregation status, accessibility plan, or detailed fire-system specification is established by the TG-RERA project record supplied here. RERA amenities Document index
8. Location, access & connectivity
The official project identity places the site in Ward No. 1, Suryapet, Suryapet district, Telangana 508213, with the locality entered as VIDYA NAGAER. The building approval describes the site as Vidyanagar, Suryapet. The RERA-filed boundaries identify roads on the east and west, each recorded as 30 FT ROAD. RERA record RERA filing RERA filing
The location record provides one approximate sampled connectivity distance: Outer Ring Road (nearest sampled interchange, approx) — 105.8 km. No other measured distances or public-transport details are supplied. Location record
9. Developer & development status
The registered promoter is RK POLA CONSTRUCTIONS AND DEVELOPERS, recorded as a partnership. Its supplied registered-office address is H NO 1-2-148/7, NIRMALA HOSPITAL ROAD, VIDYA NAGAER, Ward No. 1, Suryapet, Suryapet, 508213. The RERA record lists POLA RADHAKRISHNA as authorized signatory. Parties record RERA filing RERA filing
The promoter’s GSTIN is 36ABDFR8345P1ZG. The supplied registration records identify the firm as a partnership; the project file does not provide an official project contact number, email address, or website. Corporate record Parties record
The promoter’s Form B affidavit, dated 07-02-2022, declares a completion date of 28/01/2025. The registration certificate records validity through that same date and is not marked extended. No project-specific construction progress report, revised schedule, or occupancy/completion certificate is supplied. Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for RK TOWERS, registration P01900004292, issued 24/03/2022; stated validity through 28/01/2025 |
| Building permission | Approval 0009/BP/3049/2022, Suryapet Municipality/Municipal Corporation, dated 28 January, 2022; file no. 003621/BP/DTCP/3049/0013/2021 |
| Commencement/building approval record | Building construction approval for Building A (RESI), Survey No. 281, recording 1 Stilt + 5 upper floors |
| Promoter declaration | Form B affidavit by Pola Radhakrishna for RK POLA CONSTRUCTIONS AND DEVELOPERS, dated 07-02-2022 |
| Title-related filing | Development Agreement cum GPA and title material filed with RERA |
| Encumbrance records | RERA-filed encumbrance statement record 81176190 is supplied; a second encumbrance document is extracted as unreadable in the available text |
| Layout / occupancy records | No readable approved-layout document, occupancy certificate, or completion certificate is available in the supplied project documents Document index |
The approval contains project-specific construction and site conditions; this Overview summarizes the building identity and records only.
1. Project at a glance
Project identity
Registered name: RK TOWERS
Project type: Residential apartment project
Phase / registered portion: Phase is not separately identified in the supplied record; the registration is for RK TOWERS
TG-RERA registration: P01900004292
Registration validity: Certificate states valid from 24/03/2022 to 28/01/2025; extension status is not shown as extended in the supplied certificate
Registered promoter: RK POLA CONSTRUCTIONS AND DEVELOPERS
RERA status in supplied record: Registration certificate issued under section 5; certificate validity ended on 28/01/2025. No extension is recorded in the supplied certificate
Land and geographic identity
Locality / address: VIDYA NAGAER, Ward No. 1, Suryapet
Revenue village: Bechirag Madharam is named in the title documents; the RERA filing also records Ward No. 1. The supplied records do not reconcile these as revenue-village identifiers
Mandal / district / PIN: Suryapet / Suryapet / 508213
Project survey number(s): Survey No. 281; no project subdivision is recorded
Registered site extent: 666.45 m²
Total / net area: Total area 666.45 m²; net area 666.45 m²
Boundaries in RERA filing: East: 30 FT ROAD; West: 30 FT ROAD; North: HOUSE OF DR M SURENDRA AND PLACE OF VUPPU RAMESH; South: HOUSE OF GUTHA SUDHARSHAN REDDY
Development identity
Sanctioning authority: Suryapet Municipality/Municipal Corporation
Principal building approval: 0009/BP/3049/2022, approved 28 January, 2022
Related file number: 003621/BP/DTCP/3049/0013/2021
Approved built-up area: 1,526.25 m² in the RERA filing
Building count / configuration: One building, Building - A (RESI); sanctioned as 1 Stilt + 5 upper floors
Sanctioned height: 14.99 m
Approved unit count: 10 3BHK units recorded in the TG-RERA unit data
Parking provision: Sanctioned plan identifies stilt parking; the supplied approval extract does not state a car-space count
Offering and status
RERA-filed configuration: 3BHK, 10 units
RERA-filed saleable area: 88.21 m² per unit
Booked / available: 0 booked / 10 available, as last read from the TG-RERA portal; the record has no as-of date, so counts are indicative
Construction stage: No project-specific construction progress percentage or independently verified site status is supplied. TG-RERA amenity entries show 0% progress for the listed items
Completion deadline: Promoter’s Form B declares completion by 28/01/2025; the TG-RERA certificate also ends on that date
Revised completion date: No revised completion date is recorded in the supplied evidence
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents
2. The project story
RK TOWERS is registered with TG-RERA as a residential apartment project on Survey No. 281 in Suryapet. The filing identifies a 666.45 m² site and one residential building. The building permit describes Building A as a stilt-and-five-upper-floor apartment building.
The TG-RERA unit record lists ten 3BHK apartments, all shown as available and none booked; this is a portal snapshot with no recorded as-of date. The supplied evidence does not establish the current physical construction stage, completion of any building portion, or an occupancy certificate. The amenity progress entries are recorded as 0%; they are portal declarations, not an independent site inspection.
The promoter’s Form B affidavit undertakes completion by 28/01/2025. That date is also the end date stated on the registration certificate. The supplied certificate shows no extension, and no revised completion date or completion/occupancy certificate is provided.
3. Master plan, architecture & building design
The supplied building approval describes one residential block, Building A, on a site of 666.45 m², with 1 stilt + 5 upper floors and a sanctioned height of 14.99 m. The RERA filing records approved built-up area as 1,526.25 m². The building-permit extract separately lists residential area 1,523.70 and stilt area 291.56; units for those two figures are not stated in the extracted text, so they are not treated here as comparable area measurements.
The approval extract records 5% open space. It also identifies a 4.5mts. road width and lists a transformer space and garbage house among site provisions. The supplied material does not include a drawing-derived building footprint, detailed floor plans, flats-per-floor arrangement, lift or stair count, internal circulation plan, or a phase-by-phase layout.
The RERA filing records 162.99 m² as mortgage area. This is a filed area entry, not a measure of the saleable or carpet area of an individual home.
4. Homes, configurations & floor plans
TG-RERA records ten 3BHK units with a filed saleable area of 88.21 m² each; the portal snapshot shows none booked and all ten available, without an as-of date. No measured carpet-area figure is supplied. Although two drawings were processed, no flat designs were measured for the 3BHK configuration; therefore no drawing-based room dimensions or carpet measurement can be reported.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 88.21 m² | Not measured in supplied drawing record | Not supplied |
Saleable area is the RERA-filed unit figure. The supplied floor-plan record explains that drawing-measured carpet area, where available, is a software measurement and differs from saleable area, which includes the home’s share of common areas. No carpet, balcony, utility, or loading figures are available for these units.
5. Parking & vehicle circulation
The building approval states that the approved cellar/stilt areas for parking must be used exclusively for vehicle parking and not partitioned. The extract does not provide a sanctioned parking-space count, vehicle-type breakdown, visitor or accessible-space allocation, or a unit-wise parking allocation.
The RERA filing records 162.99 m² as mortgage area, but does not identify this as a parking allocation. No evidence establishes exclusive ownership or allocation of any drawn or described parking bay.
6. Amenities, recreation & open spaces
The following amenity entries appear in the TG-RERA portal data. All listed progress values are 0%; this is portal-recorded progress, not independently verified completion status.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | No size stated | TG-RERA amenity record | 0%; not independently verified |
| Green strip / tot lot / park | No size stated | TG-RERA amenity record | 0%; not independently verified |
| Community buildings | No size stated | TG-RERA amenity record | 0%; not independently verified |
| Aggregate recreational open space | No size stated in the amenity entry; approval records 5% open space | TG-RERA amenity record; building approval | 0% in portal record; not independently verified |
| Water supply | No source or capacity stated | TG-RERA amenity record | Listed “YES”; 0%; not independently verified |
| Sewerage / treatment and disposal of sewage and sullage | No plant capacity stated | TG-RERA amenity record | Listed “YES” for sewerage; both entries show 0%; not independently verified |
| Storm-water drains | No size stated | TG-RERA amenity record | 0%; not independently verified |
| Water conservation / rainwater harvesting | No capacity stated | TG-RERA amenity record | Listed “YES”; 0%; not independently verified |
| Solid-waste management and disposal | No capacity stated | TG-RERA amenity record | 0%; not independently verified |
| Street lighting | No details stated | TG-RERA amenity record | 0%; not independently verified |
| Energy management | No details stated | TG-RERA amenity record | 0%; not independently verified |
| Fire protection and fire-safety requirements | No system details stated | TG-RERA amenity record | 0%; not independently verified |
| Electrical meter room / substation / receiving station | No capacity stated | TG-RERA amenity record | 0%; not independently verified |
The building approval also requires a transformer space and garbage house and refers to tot-lot/greenery provisions where applicable. These are approval conditions, not evidence that the facilities have been delivered.
7. Utilities, building services & safety
The TG-RERA amenity record lists water supply, sewerage, and water conservation/rainwater harvesting as “YES,” but provides no source, capacity, design detail, or evidence of completion. Sewerage and treatment/disposal are listed without an STP capacity or reuse details.
The building approval identifies transformer space, a garbage house, and parking use for the approved stilt/cellar areas. It states that plumbing, sanitation, fire safety, lifts, and electrical installations are to be executed under qualified technical supervision, and assigns structural and fire-safety responsibility to the owner, builder/developer and technical professionals. These are approval requirements; the supplied evidence does not establish completed installations, statutory clearances, or operational status.
No lift count or capacity, backup-power arrangement, CCTV or access-control system, waste-segregation status, accessibility plan, or detailed fire-system specification is established by the TG-RERA project record supplied here.
8. Location, access & connectivity
The official project identity places the site in Ward No. 1, Suryapet, Suryapet district, Telangana 508213, with the locality entered as VIDYA NAGAER. The building approval describes the site as Vidyanagar, Suryapet. The RERA-filed boundaries identify roads on the east and west, each recorded as 30 FT ROAD.
The location record provides one approximate sampled connectivity distance: Outer Ring Road (nearest sampled interchange, approx) — 105.8 km. No other measured distances or public-transport details are supplied.
9. Developer & development status
The registered promoter is RK POLA CONSTRUCTIONS AND DEVELOPERS, recorded as a partnership. Its supplied registered-office address is H NO 1-2-148/7, NIRMALA HOSPITAL ROAD, VIDYA NAGAER, Ward No. 1, Suryapet, Suryapet, 508213. The RERA record lists POLA RADHAKRISHNA as authorized signatory.
The promoter’s GSTIN is 36ABDFR8345P1ZG. The supplied registration records identify the firm as a partnership; the project file does not provide an official project contact number, email address, or website.
The promoter’s Form B affidavit, dated 07-02-2022, declares a completion date of 28/01/2025. The registration certificate records validity through that same date and is not marked extended. No project-specific construction progress report, revised schedule, or occupancy/completion certificate is supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for RK TOWERS, registration P01900004292, issued 24/03/2022; stated validity through 28/01/2025
Building permission: Approval 0009/BP/3049/2022, Suryapet Municipality/Municipal Corporation, dated 28 January, 2022; file no. 003621/BP/DTCP/3049/0013/2021
Commencement/building approval record: Building construction approval for Building A (RESI), Survey No. 281, recording 1 Stilt + 5 upper floors
Promoter declaration: Form B affidavit by Pola Radhakrishna for RK POLA CONSTRUCTIONS AND DEVELOPERS, dated 07-02-2022
Title-related filing: Development Agreement cum GPA and title material filed with RERA
Encumbrance records: RERA-filed encumbrance statement record 81176190 is supplied; a second encumbrance document is extracted as unreadable in the available text
Layout / occupancy records: No readable approved-layout document, occupancy certificate, or completion certificate is available in the supplied project documents
The approval contains project-specific construction and site conditions; this Overview summarizes the building identity and records only.
Frequently asked questions
Is RK TOWERS registered with Telangana RERA?
Yes. RK TOWERS is registered with the Telangana Real Estate Regulatory Authority as P01900004292; the registration status is New Project.
Who is the developer of RK TOWERS?
The promoter named in the RERA registration is RK POLA CONSTRUCTIONS AND DEVELOPERS.
Where is RK TOWERS located?
RK TOWERS is in VIDYA NAGAER, Ward No. 1, Suryapet, Telangana (508213).
When will RK TOWERS be completed?
The promoter's proposed date of completion filed with RERA is 28/01/2025. This is the promoter's declaration, not a guarantee.
More projects in Suryapet