THIRUMALA TOWNSHIP is a residential plotted development in Seetarampally, Naspur Mandal, Mancherial District. It is being developed by the registered promoter VODNALA RAJAMOGILI AND THREE INDIVIDUAL. The registered site area is 24,665.78 sq. m and the layout has 77 residential plots; plot configurations are not disclosed. Its TG-RERA registration number is P01200009900, and the proposed completion date is 12/06/2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | THIRUMALA TOWNSHIP RERA record |
| Project type | Plotted development / residential layout RERA record |
| Phase / registered portion | A single registered project is identified; a separate phase or phase number is not disclosed. RERA record |
| TG-RERA registration | P01200009900 RERA record |
| Registration validity | 12/06/2025 to 12/06/2027; the certificate states a two-year validity. This is the registration period, not an occupancy certificate. RERA record |
| Registered promoter | VODNALA RAJAMOGILI AND THREE INDIVIDUAL RERA record |
| RERA status | Registered; the project is identified as a “New Project.” RERA record Approvals record |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / revenue village | Seetharampally Revenue Village; the RERA registration certificate records the village as Seetarampally. |
| Mandal / district / PIN | Naspur Mandal, Mancherial District, 504302. RERA record |
| Project survey numbers and subdivisions | 30/3, 30/3/2, 30/4, 30/4/2, 30/5, 30/5/2 |
| Registered site area | 24,665.78 sq. m total/net area as recorded in the project filing. RERA filing |
| Final-layout area | 24,665.71 sq. m total and net layout area in the final-layout proceeding. |
| Boundaries recorded in the project filing | East: other land, Sy. No. 31; West: 18 28 M WIDE ROAD; North: ORREY STREAM; South: other land, Sy. No. 35. RERA filing |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Mancherial Municipal Corporation; the TG-RERA filing identifies the authority as DTCP. Approvals record |
| Principal layout approval | Tentative layout approval 0007/LO/3026/2025, dated 12 June 2025. Approvals record |
| Final layout proceeding | Final LP 0013/MANC/SWFL/2025, dated 13/10/2025. |
| Approved built-up area | Not disclosed for this plotted layout. RERA filing |
| Building count / floor configuration | No project building count, floor configuration, or tower height is disclosed. The final-layout conditions refer to individual building permissions for dwelling sites. |
| Plot count | 77 plots in the tentative approval and final-layout proceeding. |
| Layout land-use allocation | Final layout: plotted area 12619.23 sq.m (51.16%); roads 6974.39 sq.m (28.28%); open space 2222.30 sq.m (9.01%); buffer 1980.83 sq.m (8.03%); social infrastructure 619.68 sq.m (2.51%); utility area 249.28 sq.m (1.01%); common parking area 0.00 sq.m (0%). |
Offering and status
| Item | Record |
|---|---|
| Unit type / offering | Plots for residential detached dwelling use; individual plot sizes and plot-level availability are not supplied. RERA record |
| RERA completion date | 12/06/2027 is the proposed completion date in the project filing and the infrastructure/amenities deadline stated in the tentative-layout approval. RERA record |
| Construction / development stage | RERA amenity data records internal roads and footpaths at 10% and the listed infrastructure items at 0%; these are reported progress figures, not an independent site inspection. RERA amenities |
| OC / completion certificate status | No occupancy certificate for buildings is evidenced. The project is a plotted layout; the supplied final-layout proceeding is not an occupancy certificate. |
| Booked / available plots | Not disclosed in the supplied RERA data. RERA record RERA unit table |
2. The project story
- THIRUMALA TOWNSHIP is registered as a residential plotted layout in Seetharampally Revenue Village, Naspur Mandal, Mancherial District. Its registered land identity comprises survey subdivisions 30/3, 30/3/2, 30/4, 30/4/2, 30/5 and 30/5/2. RERA record
- The local authority records a 77-plot layout, with roads, open space, buffer, social infrastructure and utility land shown as separate components. The final-layout proceeding restricts building sites to detached dwelling use designed for a single family; it states that individual building permission is considered separately under applicable building rules.
- The project filing proposes completion by 12/06/2027. RERA’s infrastructure progress entries show 10% for internal roads and footpaths and 0% for the other listed infrastructure categories. These are filing-reported figures; no independent site-progress verification is supplied. No building-level construction or occupancy-certified portion is identified in the evidence. RERA record RERA amenities
3. Master plan, architecture & building design
The approved development is a plotted layout, not an evidenced apartment or villa-block scheme. The final-layout record identifies 77 plots and a total/net layout area of 24,665.71 sq.m. Its land-use schedule allocates 12,619.23 sq.m (51.16%) to plots, 6,974.39 sq.m (28.28%) to roads, 2,222.30 sq.m (9.01%) to open space, 1,980.83 sq.m (8.03%) to buffer, 619.68 sq.m (2.51%) to social infrastructure, and 249.28 sq.m (1.01%) to utilities. It records no common parking area.
The final proceeding records road widths of 18.28m and 9.14m. It requires internal roads to remain open for access to neighbouring lands and provides for a 9 M BUFFER FROM STREAM BOUNDARY AS PER IRRIGATION NOC. No plot-size schedule or drawing-derived plot measurements are supplied here.
The tentative-layout approval describes the layout as subject to infrastructure works and later release of the final layout, and states that layout approval is not proof of title. The final-layout proceeding is a layout approval record; it does not establish that dwelling construction has been completed or that any building has received an occupancy certificate.
4. Homes, configurations & floor plans
The RERA evidence identifies a plotted development with 77 plots. Plot-size bands, plot-by-plot dimensions, booked/available counts and plot-specific saleable areas are not supplied. RERA record
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 77 | Not disclosed | Not disclosed | Not disclosed | Not applicable / not supplied | Not supplied |
The supplied floor-plan record concerns no measured home layouts: two drawings are noted, with 0 measured, 2 scans pending, and no flat count. No software-measured carpet or room dimensions can therefore be reported. Floor plans
5. Parking & vehicle circulation
The final-layout proceeding records 0.00 sq.m (0%) as common parking area. The tentative-layout approval includes utility land and lists common parking among utility-related items, but it does not provide a count of parking spaces or a unit-level parking allocation. No visitor, accessible, mechanical or EV parking provision is established in the supplied project records.
The final layout records internal roads of 18.28m and 9.14m; the proceeding also states that internal roads are to remain open for access to neighbouring lands. No separate vehicle entry/exit design, driveway arrangement or pedestrian-separation plan is supplied.
6. Amenities, recreation & open spaces
The final-layout proceeding sets out land reserved for open space, social infrastructure and utilities. RERA’s infrastructure schedule reports progress separately; the supplied record does not establish that any facility is independently verified as complete. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Open space / park | 2222.30 sq.m (9.01%) in final-layout schedule | Final layout | Reserved in layout; no completion verification supplied. RERA schedule records aggregate recreational open space at 0%. RERA amenities |
| Social infrastructure | 619.68 sq.m (2.51%) | Final layout | Reserved; no specific facility or completion evidence supplied. |
| Utilities area | 249.28 sq.m (1.01%) | Final layout | Reserved for utility uses; no completion verification supplied. |
| Community buildings | No area or facility detail supplied | RERA amenity schedule RERA amenities | Progress recorded at 0%. |
| Green strip / park | No additional size detail supplied | RERA amenity schedule RERA amenities | Progress recorded at 0%; not independently verified. |
A third-party vendor listing includes clubhouse, gym, landscaped garden, play area and swimming pool, but it gives a different location and is not used as evidence of this registered project’s facilities. Promoter website
7. Utilities, building services & safety
The tentative-layout approval describes infrastructure works to include road formation with black top, storm-water drains, underground drainage lines and a common septic tank/STP, internal water-supply pipelines, an overhead tank and assured water source, electrical supply lines and street lights, transformer, avenue planting, park development and rainwater-harvesting pits. These are approval-condition descriptions of required development, not evidence that the works are complete.
The final-layout proceeding identifies a utility area of 249.28 sq.m (1.01%) and lists water reservoir, septic tank, sewerage treatment plant, electric transformer, solid-waste management, garbage bin and common parking among utility-related items. The RERA infrastructure schedule records water supply, sewerage, storm-water drains, street lighting, rainwater harvesting, solid-waste management and electrical meter/substation/receiving station categories at 0% progress, except internal roads and footpaths at 10%. No capacities, service specifications, fire-safety system details, backup supply, accessibility design or completed-system verification are supplied. RERA amenities
8. Location, access & connectivity
The registered location is Seetarampally, Naspur Mandal, Mancherial District, Telangana 504302; the layout approval refers to Seetharampally Revenue Village. The supplied cadastral parcel centroid is 18.853245403716944, 79.48562880384797. Cadastral map
The project filing records the west boundary as an 18 28 M WIDE ROAD. The final-layout proceeding records road widths of 18.28m and 9.14m and says internal roads are to remain open for access to neighbouring lands. No public-transport routes, nearby landmarks or local travel-time estimates are supplied. The nearest sampled Outer Ring Road interchange is listed at 172.6 km (approx.). RERA filing Location record
9. Developer & development status
The registered promoter is VODNALA RAJAMOGILI AND THREE INDIVIDUAL. The RERA certificate lists the promoter parties at Seetarampally, Naspur, Mancherial, PIN 504302. The legal entity type, corporate registration number and official website/contact details are not established in the supplied project record. RERA record Corporate record
The registration certificate is valid from 12/06/2025 through 12/06/2027 and requires quarterly updates. Separately, the tentative-layout approval requires infrastructure and amenities to be completed within two years from 12 June 2025, stating 12 June, 2027 as the deadline. RERA-listed infrastructure progress is 10% for internal roads and footpaths and 0% for the other listed categories; no independent progress inspection or building occupancy certificate is supplied. RERA amenities
10. Approvals, official records & documents
| Identifier / date | P01200009900; validity 12/06/2025–12/06/2027 |
|---|---|
| What it establishes | Registration of THIRUMALA TOWNSHIP and the registered promoter and land identity. |
| Identifier / date | 0007/LO/3026/2025; 12 June 2025; Mancherial Municipal Corporation |
|---|---|
| What it establishes | Tentative approval for a 77-plot layout on the stated survey subdivisions, with land-use allocations and development conditions. |
| Identifier / date | 0013/MANC/SWFL/2025; 13/10/2025; Mancherial Municipal Corporation |
|---|---|
| What it establishes | Final layout record for 77 plots, with the stated layout area, land-use schedule, road widths and conditions. |
| Identifier / date | Filed document |
|---|---|
| What it establishes | Promoter declaration concerning title, encumbrances, project funds, audits, approvals and completion; the extracted declaration states a completion undertaking of 12/06/2025. |
| Identifier / date | Not evidenced |
|---|---|
| What it establishes | The supplied final-layout proceeding is not a building occupancy certificate. No building-level occupancy or completion certificate is supplied. |
1. Project at a glance
Project identity
Registered project name: THIRUMALA TOWNSHIP
Project type: Plotted development / residential layout
Phase / registered portion: A single registered project is identified; a separate phase or phase number is not disclosed.
TG-RERA registration: P01200009900
Registration validity: 12/06/2025 to 12/06/2027; the certificate states a two-year validity. This is the registration period, not an occupancy certificate.
Registered promoter: VODNALA RAJAMOGILI AND THREE INDIVIDUAL
RERA status: Registered; the project is identified as a “New Project.”
Land and geographic identity
Locality / revenue village: Seetharampally Revenue Village; the RERA registration certificate records the village as Seetarampally.
Mandal / district / PIN: Naspur Mandal, Mancherial District, 504302.
Project survey numbers and subdivisions: 30/3, 30/3/2, 30/4, 30/4/2, 30/5, 30/5/2
Registered site area: 24,665.78 sq. m total/net area as recorded in the project filing.
Final-layout area: 24,665.71 sq. m total and net layout area in the final-layout proceeding.
Boundaries recorded in the project filing: East: other land, Sy. No. 31; West: 18 28 M WIDE ROAD; North: ORREY STREAM; South: other land, Sy. No. 35.
Development identity
Sanctioning authority: Mancherial Municipal Corporation; the TG-RERA filing identifies the authority as DTCP.
Principal layout approval: Tentative layout approval 0007/LO/3026/2025, dated 12 June 2025.
Final layout proceeding: Final LP 0013/MANC/SWFL/2025, dated 13/10/2025.
Approved built-up area: Not disclosed for this plotted layout.
Building count / floor configuration: No project building count, floor configuration, or tower height is disclosed. The final-layout conditions refer to individual building permissions for dwelling sites.
Plot count: 77 plots in the tentative approval and final-layout proceeding.
Layout land-use allocation: Final layout: plotted area 12619.23 sq.m (51.16%); roads 6974.39 sq.m (28.28%); open space 2222.30 sq.m (9.01%); buffer 1980.83 sq.m (8.03%); social infrastructure 619.68 sq.m (2.51%); utility area 249.28 sq.m (1.01%); common parking area 0.00 sq.m (0%).
Offering and status
Unit type / offering: Plots for residential detached dwelling use; individual plot sizes and plot-level availability are not supplied.
RERA completion date: 12/06/2027 is the proposed completion date in the project filing and the infrastructure/amenities deadline stated in the tentative-layout approval.
Construction / development stage: RERA amenity data records internal roads and footpaths at 10% and the listed infrastructure items at 0%; these are reported progress figures, not an independent site inspection.
OC / completion certificate status: No occupancy certificate for buildings is evidenced. The project is a plotted layout; the supplied final-layout proceeding is not an occupancy certificate.
Booked / available plots: Not disclosed in the supplied RERA data.
2. The project story
- THIRUMALA TOWNSHIP is registered as a residential plotted layout in Seetharampally Revenue Village, Naspur Mandal, Mancherial District. Its registered land identity comprises survey subdivisions 30/3, 30/3/2, 30/4, 30/4/2, 30/5 and 30/5/2.
- The local authority records a 77-plot layout, with roads, open space, buffer, social infrastructure and utility land shown as separate components. The final-layout proceeding restricts building sites to detached dwelling use designed for a single family; it states that individual building permission is considered separately under applicable building rules.
- The project filing proposes completion by 12/06/2027. RERA’s infrastructure progress entries show 10% for internal roads and footpaths and 0% for the other listed infrastructure categories. These are filing-reported figures; no independent site-progress verification is supplied. No building-level construction or occupancy-certified portion is identified in the evidence.
3. Master plan, architecture & building design
The approved development is a plotted layout, not an evidenced apartment or villa-block scheme. The final-layout record identifies 77 plots and a total/net layout area of 24,665.71 sq.m. Its land-use schedule allocates 12,619.23 sq.m (51.16%) to plots, 6,974.39 sq.m (28.28%) to roads, 2,222.30 sq.m (9.01%) to open space, 1,980.83 sq.m (8.03%) to buffer, 619.68 sq.m (2.51%) to social infrastructure, and 249.28 sq.m (1.01%) to utilities. It records no common parking area.
The final proceeding records road widths of 18.28m and 9.14m. It requires internal roads to remain open for access to neighbouring lands and provides for a 9 M BUFFER FROM STREAM BOUNDARY AS PER IRRIGATION NOC. No plot-size schedule or drawing-derived plot measurements are supplied here.
The tentative-layout approval describes the layout as subject to infrastructure works and later release of the final layout, and states that layout approval is not proof of title. The final-layout proceeding is a layout approval record; it does not establish that dwelling construction has been completed or that any building has received an occupancy certificate.
4. Homes, configurations & floor plans
The RERA evidence identifies a plotted development with 77 plots. Plot-size bands, plot-by-plot dimensions, booked/available counts and plot-specific saleable areas are not supplied.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 77 | Not disclosed | Not disclosed | Not disclosed | Not applicable / not supplied | Not supplied |
The supplied floor-plan record concerns no measured home layouts: two drawings are noted, with 0 measured, 2 scans pending, and no flat count. No software-measured carpet or room dimensions can therefore be reported.
5. Parking & vehicle circulation
The final-layout proceeding records 0.00 sq.m (0%) as common parking area. The tentative-layout approval includes utility land and lists common parking among utility-related items, but it does not provide a count of parking spaces or a unit-level parking allocation. No visitor, accessible, mechanical or EV parking provision is established in the supplied project records.
The final layout records internal roads of 18.28m and 9.14m; the proceeding also states that internal roads are to remain open for access to neighbouring lands. No separate vehicle entry/exit design, driveway arrangement or pedestrian-separation plan is supplied.
6. Amenities, recreation & open spaces
The final-layout proceeding sets out land reserved for open space, social infrastructure and utilities. RERA’s infrastructure schedule reports progress separately; the supplied record does not establish that any facility is independently verified as complete.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Open space / park | 2222.30 sq.m (9.01%) in final-layout schedule | Final layout | Reserved in layout; no completion verification supplied. RERA schedule records aggregate recreational open space at 0%. |
| Social infrastructure | 619.68 sq.m (2.51%) | Final layout | Reserved; no specific facility or completion evidence supplied. |
| Utilities area | 249.28 sq.m (1.01%) | Final layout | Reserved for utility uses; no completion verification supplied. |
| Community buildings | No area or facility detail supplied | RERA amenity schedule | Progress recorded at 0%. |
| Green strip / park | No additional size detail supplied | RERA amenity schedule | Progress recorded at 0%; not independently verified. |
A third-party vendor listing includes clubhouse, gym, landscaped garden, play area and swimming pool, but it gives a different location and is not used as evidence of this registered project’s facilities.
7. Utilities, building services & safety
The tentative-layout approval describes infrastructure works to include road formation with black top, storm-water drains, underground drainage lines and a common septic tank/STP, internal water-supply pipelines, an overhead tank and assured water source, electrical supply lines and street lights, transformer, avenue planting, park development and rainwater-harvesting pits. These are approval-condition descriptions of required development, not evidence that the works are complete.
The final-layout proceeding identifies a utility area of 249.28 sq.m (1.01%) and lists water reservoir, septic tank, sewerage treatment plant, electric transformer, solid-waste management, garbage bin and common parking among utility-related items. The RERA infrastructure schedule records water supply, sewerage, storm-water drains, street lighting, rainwater harvesting, solid-waste management and electrical meter/substation/receiving station categories at 0% progress, except internal roads and footpaths at 10%. No capacities, service specifications, fire-safety system details, backup supply, accessibility design or completed-system verification are supplied.
8. Location, access & connectivity
The registered location is Seetarampally, Naspur Mandal, Mancherial District, Telangana 504302; the layout approval refers to Seetharampally Revenue Village. The supplied cadastral parcel centroid is 18.853245403716944, 79.48562880384797.
The project filing records the west boundary as an 18 28 M WIDE ROAD. The final-layout proceeding records road widths of 18.28m and 9.14m and says internal roads are to remain open for access to neighbouring lands. No public-transport routes, nearby landmarks or local travel-time estimates are supplied. The nearest sampled Outer Ring Road interchange is listed at 172.6 km (approx.).
9. Developer & development status
The registered promoter is VODNALA RAJAMOGILI AND THREE INDIVIDUAL. The RERA certificate lists the promoter parties at Seetarampally, Naspur, Mancherial, PIN 504302. The legal entity type, corporate registration number and official website/contact details are not established in the supplied project record.
The registration certificate is valid from 12/06/2025 through 12/06/2027 and requires quarterly updates. Separately, the tentative-layout approval requires infrastructure and amenities to be completed within two years from 12 June 2025, stating 12 June, 2027 as the deadline. RERA-listed infrastructure progress is 10% for internal roads and footpaths and 0% for the other listed categories; no independent progress inspection or building occupancy certificate is supplied.
10. Approvals, official records & documents
| Identifier / date | P01200009900; validity 12/06/2025–12/06/2027 |
|---|---|
| What it establishes | Registration of THIRUMALA TOWNSHIP and the registered promoter and land identity. |
| Identifier / date | 0007/LO/3026/2025; 12 June 2025; Mancherial Municipal Corporation |
|---|---|
| What it establishes | Tentative approval for a 77-plot layout on the stated survey subdivisions, with land-use allocations and development conditions. |
| Identifier / date | 0013/MANC/SWFL/2025; 13/10/2025; Mancherial Municipal Corporation |
|---|---|
| What it establishes | Final layout record for 77 plots, with the stated layout area, land-use schedule, road widths and conditions. |
| Identifier / date | Filed document |
|---|---|
| What it establishes | Promoter declaration concerning title, encumbrances, project funds, audits, approvals and completion; the extracted declaration states a completion undertaking of 12/06/2025. |
| Identifier / date | Not evidenced |
|---|---|
| What it establishes | The supplied final-layout proceeding is not a building occupancy certificate. No building-level occupancy or completion certificate is supplied. |
Frequently asked questions
Is THIRUMALA TOWNSHIP registered with Telangana RERA?
Yes. THIRUMALA TOWNSHIP is registered with the Telangana Real Estate Regulatory Authority as P01200009900; the registration status is New Project.
Who is the developer of THIRUMALA TOWNSHIP?
The promoter named in the RERA registration is VODNALA RAJAMOGILI AND THREE INDIVIDUAL.
Where is THIRUMALA TOWNSHIP located?
THIRUMALA TOWNSHIP is in SEETHARAMPALLY, Seetarampally, Naspur, Mancherial, Telangana (504302).
When will THIRUMALA TOWNSHIP be completed?
The promoter's proposed date of completion filed with RERA is 12/06/2027. This is the promoter's declaration, not a guarantee.