Raja Rajeshwara Residency
GOLDEN TOWER · Mancherial · RERA P01200005349
RAJA RAJESHWARA RESIDENCY is a residential apartment project in Naspur, Naspur mandal, Mancherial district. The registration certificate names Sri Laxmi Fly Ash Bricks And Constructions as the registered promoter developing it. The project has a site extent of 711.77 m² and one building with a stilt and five upper floors, comprising 20 2BHK units. It is registered under TG-RERA P01200005349, with proposed completion by 13/12/2024.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | RAJA RAJESHWARA RESIDENCY RERA record |
| Project type / category | Residential apartment project RERA record RERA filing |
| Phase / registered portion | No separate phase name or phase identifier is disclosed. The registration is for the project; the sanctioned record identifies one building. RERA record |
| TG-RERA registration | P01200005349 RERA record |
| Registration validity | 25/11/2022 to 13/12/2024; the certificate states a two-year validity and does not record an extension. This is registration validity, not an occupancy certificate. RERA record |
| Registered promoter | The identity header lists GOLDEN TOWER; the registration certificate names Sri Laxmi Fly Ash Bricks And Constructions. The legal-entity relationship is not established in the supplied overview evidence. RERA record |
| RERA status | Registration certificate records that registration was granted under section 5. The supplied record gives the validity dates above; a current registration status is not established here. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality | Naspur RERA record RERA filing |
| Revenue village | Naspur RERA record Land records |
| Mandal / district / PIN | Naspur / Mancherial / 504302 RERA record |
| Project survey number(s) | Survey No. 76; no subdivision is specified for the project parcel in the registration and building-approval records. Land records |
| Plot numbers | 5, 6 RERA filing |
| Site extent | 711.77 m² total and net area; road-affected area is recorded as 0. RERA filing |
| Boundaries | East: LAND OF M ASHOK REDDY AND BALAJI RESIDENCY; west: 30 FEET ROAD; north: PLOT NO 7 AND PLOT NO 8; south: PLOT NO 4. RERA filing |
| Geolocation | The supplied geocode is Naspur, Naspur mandal, Mancherial, Telangana, 504303, India. Location record |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Naspur Municipality/Municipal Corporation, as stated in the building approval. |
| Principal building approval | 0001/BP/3075/2021, approved 13 December, 2021; file no. 004189/BP/DTCP/3075/0004/2021. Approvals record |
| Approved built-up area | 2,066.07 m² in the project filing. The approval extraction separately lists 1,695.50 m² for five upper residential floors and 357.86 m² for the stilt; the supplied record does not reconcile these figures. RERA filing |
| Building count | One building is recorded in the project filing. RERA filing |
| Sanctioned configuration | One stilt plus five upper floors; the approval states a building height of 14.50 m. |
| Parking level | Stilt is identified in the approval; the sanction conditions say approved cellar/stilt parking is to be used exclusively for vehicle parking. No separate cellar is identified in the extracted floor configuration. |
| Unit count | 20 units in the RERA unit record; the filing also records one total building unit, which does not specify apartment count. RERA unit table RERA filing |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configuration | 2BHK, 20 units; filed saleable area is 72.82 m² per unit. RERA unit table |
| Booked / available | 0 booked and 20 available in the portal record; the booking extract has no as-of date, so these counts are indicative. RERA unit table |
| Completion timeline | Proposed completion date: 13/12/2024; Form B also contains a completion undertaking for 13/12/2024. RERA record |
| Construction stage | No verified construction-progress percentage or current site-stage evidence is supplied. The RERA amenity entries show 0% for the listed works, which is a filed progress field, not independent site verification. RERA amenities |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied in this evidence. Document index |
2. The project story
RAJA RAJESHWARA RESIDENCY is registered as a residential apartment project in Naspur village, Naspur mandal, Mancherial district. The registered land is identified as Survey No. 76, Plot Nos. 5 and 6, with a site extent of 711.77 m². Its recorded boundaries include a 30-foot road on the west. RERA record Land records RERA filing
The building approval describes one residential building with a stilt and five upper floors. The RERA unit record lists 20 two-bedroom apartments. The registration certificate was valid through 13/12/2024, and the project filing proposed completion by that date. The supplied evidence does not establish current construction progress, completion, or occupancy certification; the portal’s unit availability and amenity progress entries should therefore be treated as filed-record snapshots, not verified site conditions. RERA unit table RERA record RERA amenities
3. Master plan, architecture & building design
The building approval identifies a single residential building, “Building - SRI (LAXMI),” with one stilt and five upper floors, a stated height of 14.50 m, and a site area of 711.77 m². It also records a 3.5 m front setback, 3.5 m rear setback, and 3.5 m Side I setback. The supplied extraction does not describe building footprint, floor-by-floor apartment arrangement, internal circulation, number of lifts or stairs, or the residential/common-area distribution.
The project filing reports approved built-up area of 2,066.07 m². The approval extraction separately reports 1,695.50 m² for upper residential floors and 357.86 m² for the stilt. These are retained as separately recorded figures; the supplied documents do not explain their relationship. No FSI-counted area is supplied. RERA filing
The building-plan approval records one rain-water-harvesting pit, space for a transformer, and a garbage house. The approval requires construction to follow the sanctioned plan and states that modifications require separate prior approval. The supplied evidence does not include a readable, extracted floor-plan layout or a complete drawing-derived building design description. The uploaded floor-plan document is identified as doc 259829, but its listing says the floor plan itself was not extracted.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 20 | 0 | 20 | 72.82 m² | 63.6–66.0 m²; median 64.4 m² | Not supplied |
The 2BHK count, bookings, availability and 72.82 m² saleable area are from the RERA unit record. The carpet-area figures are software-measured from floor-plan drawings, not RERA-filed measurements; the measurement record covers 15 flat designs and notes that the drawing measurements need review. RERA unit table RERA unit details Floor plans
The supplied drawing-derived room schedule for one flat identifies two bedrooms, a hall, a kitchen and two toilets. The extracted dimensions are: bedroom 3.42 × 3.50 m; kitchen 3.42 × 3.85 m; toilets 1.32 × 2.24 m and 1.32 × 2.26 m; hall 3.50 × 5.12 m; and second bedroom 3.68 × 3.85 m. These are drawing measurements, not RERA disclosures. RERA unit details
The filing provides saleable area, while the floor-plan analysis provides software-measured carpet area. The supplied records do not give a loading figure or separately quantify balcony, utility or common-area components. The portal’s 0-booked/20-available count has no recorded as-of date. RERA unit table Floor plans
5. Parking & vehicle circulation
The approval conditions state that any cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted to another use. The project filing records a mortgage area of 177.74 m², but the supplied evidence does not establish how that area relates to parking or identify a parking allocation. RERA filing
No sanctioned number of car or two-wheeler spaces, visitor or accessible parking count, ramp or driveway arrangement, EV provision, or unit-wise parking allocation is supplied. A parking-space count or spaces-per-home ratio cannot be established from this record. RERA amenities
6. Amenities, recreation & open spaces
The RERA amenity schedule lists facilities and infrastructure with progress recorded as 0% where a percentage is shown. “YES” indicates an availability entry in the filing, not independent confirmation of installation or operation. The approval separately includes site conditions for rainwater harvesting, transformer space and a garbage house. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | No size supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Water supply | No source, capacity or storage detail supplied | RERA amenity schedule RERA amenities | “YES”; 0% recorded; not independently verified |
| Sewerage (chamber, lines, septic tank, STP) | No system capacity or treatment detail supplied | RERA amenity schedule RERA amenities | “YES”; 0% recorded; not independently verified |
| Storm-water drains | No design or capacity supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Green strip / tot lot / park | No size supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Street lighting | No quantity or specification supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Community buildings | No description or size supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Sewage and sullage treatment/disposal | No treatment method or capacity supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Solid-waste management and disposal | No capacity or operating details supplied | RERA amenity schedule RERA amenities; approval condition | 0% recorded; not independently verified |
| Water conservation / rainwater harvesting | Approval lists one rain-water-harvesting pit | RERA amenity schedule RERA amenities | RERA schedule says “YES” and records 0%; installation not independently verified |
| Energy management | No system details supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
| Fire protection and fire-safety requirements | No system details supplied | RERA amenity schedule RERA amenities; approval conditions | 0% recorded; not independently verified |
| Electrical meter room / sub-station / receiving station | Approval requires space for a transformer | RERA amenity schedule RERA amenities | “YES”; 0% recorded; not independently verified |
| Aggregate recreational open space | No area supplied | RERA amenity schedule RERA amenities | 0% recorded; not independently verified |
No clubhouse or specific indoor or sports facility is identified in the supplied evidence. RERA amenities
7. Utilities, building services & safety
The RERA amenity schedule records “YES” for water supply, sewerage and rainwater harvesting, but does not specify water source, storage, treatment, STP capacity or reuse arrangements. It lists storm-water drains and sewage/sullage treatment and disposal without design or capacity details. The building approval requires one rain-water-harvesting pit. RERA amenities
Electrical service information is limited to the amenity schedule’s “YES” entry for an electrical meter room, sub-station or receiving station and the approval’s requirement for transformer space. No electrical-load, backup-power or EV-charging details are supplied. RERA amenities
The approval requires services including sanitation, plumbing, fire safety and lifts to be executed under qualified technical supervision, and assigns responsibility for structural and fire safety to the stated project professionals. These are approval conditions; the supplied record does not establish installed systems, clearances or completed inspections. It contains no lift count or capacity, fire-equipment specification, emergency-access design, accessibility details, CCTV or access-control information.
8. Location, access & connectivity
The official project location is Naspur village, Naspur mandal, Mancherial district, PIN 504302. The building approval describes the site locality as “NEAR ROYAL FUNCTION HALL,” and records a 30-foot road along the western boundary. RERA record RERA filing
The supplied geocode is for Naspur, Naspur mandal, Mancherial, Telangana, 504303, India. One sampled connectivity entry lists the nearest sampled Outer Ring Road interchange at approximately 175.3 km; no route, travel time or public-transport information is supplied. Location record
9. Developer & development status
The project identity header names GOLDEN TOWER as promoter and identifies the organization type as a partnership. The registration certificate names Sri Laxmi Fly Ash Bricks And Constructions as the promoter. The available evidence does not establish the legal relationship between those names, so they should not be assumed to be interchangeable. RERA record Corporate record
The project filing lists CHINTHAPANDU PRATHYUSHA as authorized signatory and SUNKARI ASHOK, KARRA RAJIREDDY and KOMANDLA NARENDER as partners. The registration certificate gives the promoter office as Village CCC, Mandal Naspur, District Mancherial, PIN 504302. No official contact details or website are supplied. Parties record
Form B undertakes completion by 13/12/2024. The registration certificate records validity to the same date and does not state an extension. No current site progress or occupancy certification is established by the supplied evidence. The 20-unit inventory and its booking counts are portal-record figures without an as-of date. RERA unit table
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | FORM C registration certificate for RAJA RAJESHWARA RESIDENCY, registration no. P01200005349; valid 25/11/2022–13/12/2024. |
| Principal building approval | Approval for building construction no. 0001/BP/3075/2021, dated 13 December, 2021; file no. 004189/BP/DTCP/3075/0004/2021; authority stated as Naspur Municipality/Municipal Corporation. |
| Commencement / building-permit document | Document titled “Commencement Certificates for each building in each phase”; the extracted record describes an approval for one stilt-plus-five-upper-floor building. |
| Form B declaration | Form-B affidavit-cum-declaration records title, separate-account, audit, approvals and completion undertakings; the extracted declaration date is unreadable. |
| Floor-plan document | Floor-plan upload is listed as doc 259829; the project evidence includes software-measured 2BHK drawing data from that document, but a full extracted drawing description is not supplied. |
| Occupancy / completion certificate | Not supplied in the available project documents. Document index |
The building approval lists conditions covering sanctioned-plan conformity, rainwater harvesting, transformer space, waste segregation, parking use, and occupancy before delivery of possession. This overview records the extracted conditions; the full approval and its conditions should be reviewed in the approvals assessment.
1. Project at a glance
Project identity
Registered project name: RAJA RAJESHWARA RESIDENCY
Project type / category: Residential apartment project
Phase / registered portion: No separate phase name or phase identifier is disclosed. The registration is for the project; the sanctioned record identifies one building.
TG-RERA registration: P01200005349
Registration validity: 25/11/2022 to 13/12/2024; the certificate states a two-year validity and does not record an extension. This is registration validity, not an occupancy certificate.
Registered promoter: The identity header lists GOLDEN TOWER; the registration certificate names Sri Laxmi Fly Ash Bricks And Constructions. The legal-entity relationship is not established in the supplied overview evidence.
RERA status: Registration certificate records that registration was granted under section 5. The supplied record gives the validity dates above; a current registration status is not established here.
Land and geographic identity
Locality: Naspur
Revenue village: Naspur
Mandal / district / PIN: Naspur / Mancherial / 504302
Project survey number(s): Survey No. 76; no subdivision is specified for the project parcel in the registration and building-approval records.
Plot numbers: 5, 6
Site extent: 711.77 m² total and net area; road-affected area is recorded as 0.
Boundaries: East: LAND OF M ASHOK REDDY AND BALAJI RESIDENCY; west: 30 FEET ROAD; north: PLOT NO 7 AND PLOT NO 8; south: PLOT NO 4.
Geolocation: The supplied geocode is Naspur, Naspur mandal, Mancherial, Telangana, 504303, India.
Development identity
Sanctioning authority: Naspur Municipality/Municipal Corporation, as stated in the building approval.
Principal building approval: 0001/BP/3075/2021, approved 13 December, 2021; file no. 004189/BP/DTCP/3075/0004/2021.
Approved built-up area: 2,066.07 m² in the project filing. The approval extraction separately lists 1,695.50 m² for five upper residential floors and 357.86 m² for the stilt; the supplied record does not reconcile these figures.
Building count: One building is recorded in the project filing.
Sanctioned configuration: One stilt plus five upper floors; the approval states a building height of 14.50 m.
Parking level: Stilt is identified in the approval; the sanction conditions say approved cellar/stilt parking is to be used exclusively for vehicle parking. No separate cellar is identified in the extracted floor configuration.
Unit count: 20 units in the RERA unit record; the filing also records one total building unit, which does not specify apartment count.
Offering and status
RERA-filed configuration: 2BHK, 20 units; filed saleable area is 72.82 m² per unit.
Booked / available: 0 booked and 20 available in the portal record; the booking extract has no as-of date, so these counts are indicative.
Completion timeline: Proposed completion date: 13/12/2024; Form B also contains a completion undertaking for 13/12/2024.
Construction stage: No verified construction-progress percentage or current site-stage evidence is supplied. The RERA amenity entries show 0% for the listed works, which is a filed progress field, not independent site verification.
Occupancy / completion certificate: No occupancy or completion certificate is supplied in this evidence.
2. The project story
RAJA RAJESHWARA RESIDENCY is registered as a residential apartment project in Naspur village, Naspur mandal, Mancherial district. The registered land is identified as Survey No. 76, Plot Nos. 5 and 6, with a site extent of 711.77 m². Its recorded boundaries include a 30-foot road on the west.
The building approval describes one residential building with a stilt and five upper floors. The RERA unit record lists 20 two-bedroom apartments. The registration certificate was valid through 13/12/2024, and the project filing proposed completion by that date. The supplied evidence does not establish current construction progress, completion, or occupancy certification; the portal’s unit availability and amenity progress entries should therefore be treated as filed-record snapshots, not verified site conditions.
3. Master plan, architecture & building design
The building approval identifies a single residential building, “Building - SRI (LAXMI),” with one stilt and five upper floors, a stated height of 14.50 m, and a site area of 711.77 m². It also records a 3.5 m front setback, 3.5 m rear setback, and 3.5 m Side I setback. The supplied extraction does not describe building footprint, floor-by-floor apartment arrangement, internal circulation, number of lifts or stairs, or the residential/common-area distribution.
The project filing reports approved built-up area of 2,066.07 m². The approval extraction separately reports 1,695.50 m² for upper residential floors and 357.86 m² for the stilt. These are retained as separately recorded figures; the supplied documents do not explain their relationship. No FSI-counted area is supplied.
The building-plan approval records one rain-water-harvesting pit, space for a transformer, and a garbage house. The approval requires construction to follow the sanctioned plan and states that modifications require separate prior approval. The supplied evidence does not include a readable, extracted floor-plan layout or a complete drawing-derived building design description. The uploaded floor-plan document is identified as doc 259829, but its listing says the floor plan itself was not extracted.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 20 | 0 | 20 | 72.82 m² | 63.6–66.0 m²; median 64.4 m² | Not supplied |
The 2BHK count, bookings, availability and 72.82 m² saleable area are from the RERA unit record. The carpet-area figures are software-measured from floor-plan drawings, not RERA-filed measurements; the measurement record covers 15 flat designs and notes that the drawing measurements need review.
The supplied drawing-derived room schedule for one flat identifies two bedrooms, a hall, a kitchen and two toilets. The extracted dimensions are: bedroom 3.42 × 3.50 m; kitchen 3.42 × 3.85 m; toilets 1.32 × 2.24 m and 1.32 × 2.26 m; hall 3.50 × 5.12 m; and second bedroom 3.68 × 3.85 m. These are drawing measurements, not RERA disclosures.
The filing provides saleable area, while the floor-plan analysis provides software-measured carpet area. The supplied records do not give a loading figure or separately quantify balcony, utility or common-area components. The portal’s 0-booked/20-available count has no recorded as-of date.
5. Parking & vehicle circulation
The approval conditions state that any cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted to another use. The project filing records a mortgage area of 177.74 m², but the supplied evidence does not establish how that area relates to parking or identify a parking allocation.
No sanctioned number of car or two-wheeler spaces, visitor or accessible parking count, ramp or driveway arrangement, EV provision, or unit-wise parking allocation is supplied. A parking-space count or spaces-per-home ratio cannot be established from this record.
6. Amenities, recreation & open spaces
The RERA amenity schedule lists facilities and infrastructure with progress recorded as 0% where a percentage is shown. “YES” indicates an availability entry in the filing, not independent confirmation of installation or operation. The approval separately includes site conditions for rainwater harvesting, transformer space and a garbage house.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads & footpaths | No size supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Water supply | No source, capacity or storage detail supplied | RERA amenity schedule | “YES”; 0% recorded; not independently verified |
| Sewerage (chamber, lines, septic tank, STP) | No system capacity or treatment detail supplied | RERA amenity schedule | “YES”; 0% recorded; not independently verified |
| Storm-water drains | No design or capacity supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Green strip / tot lot / park | No size supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Street lighting | No quantity or specification supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Community buildings | No description or size supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Sewage and sullage treatment/disposal | No treatment method or capacity supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Solid-waste management and disposal | No capacity or operating details supplied | RERA amenity schedule; approval condition | 0% recorded; not independently verified |
| Water conservation / rainwater harvesting | Approval lists one rain-water-harvesting pit | RERA amenity schedule | RERA schedule says “YES” and records 0%; installation not independently verified |
| Energy management | No system details supplied | RERA amenity schedule | 0% recorded; not independently verified |
| Fire protection and fire-safety requirements | No system details supplied | RERA amenity schedule; approval conditions | 0% recorded; not independently verified |
| Electrical meter room / sub-station / receiving station | Approval requires space for a transformer | RERA amenity schedule | “YES”; 0% recorded; not independently verified |
| Aggregate recreational open space | No area supplied | RERA amenity schedule | 0% recorded; not independently verified |
No clubhouse or specific indoor or sports facility is identified in the supplied evidence.
7. Utilities, building services & safety
The RERA amenity schedule records “YES” for water supply, sewerage and rainwater harvesting, but does not specify water source, storage, treatment, STP capacity or reuse arrangements. It lists storm-water drains and sewage/sullage treatment and disposal without design or capacity details. The building approval requires one rain-water-harvesting pit.
Electrical service information is limited to the amenity schedule’s “YES” entry for an electrical meter room, sub-station or receiving station and the approval’s requirement for transformer space. No electrical-load, backup-power or EV-charging details are supplied.
The approval requires services including sanitation, plumbing, fire safety and lifts to be executed under qualified technical supervision, and assigns responsibility for structural and fire safety to the stated project professionals. These are approval conditions; the supplied record does not establish installed systems, clearances or completed inspections. It contains no lift count or capacity, fire-equipment specification, emergency-access design, accessibility details, CCTV or access-control information.
8. Location, access & connectivity
The official project location is Naspur village, Naspur mandal, Mancherial district, PIN 504302. The building approval describes the site locality as “NEAR ROYAL FUNCTION HALL,” and records a 30-foot road along the western boundary.
The supplied geocode is for Naspur, Naspur mandal, Mancherial, Telangana, 504303, India. One sampled connectivity entry lists the nearest sampled Outer Ring Road interchange at approximately 175.3 km; no route, travel time or public-transport information is supplied.
9. Developer & development status
The project identity header names GOLDEN TOWER as promoter and identifies the organization type as a partnership. The registration certificate names Sri Laxmi Fly Ash Bricks And Constructions as the promoter. The available evidence does not establish the legal relationship between those names, so they should not be assumed to be interchangeable.
The project filing lists CHINTHAPANDU PRATHYUSHA as authorized signatory and SUNKARI ASHOK, KARRA RAJIREDDY and KOMANDLA NARENDER as partners. The registration certificate gives the promoter office as Village CCC, Mandal Naspur, District Mancherial, PIN 504302. No official contact details or website are supplied.
Form B undertakes completion by 13/12/2024. The registration certificate records validity to the same date and does not state an extension. No current site progress or occupancy certification is established by the supplied evidence. The 20-unit inventory and its booking counts are portal-record figures without an as-of date.
10. Approvals, official records & documents
TG-RERA registration: FORM C registration certificate for RAJA RAJESHWARA RESIDENCY, registration no. P01200005349; valid 25/11/2022–13/12/2024.
Principal building approval: Approval for building construction no. 0001/BP/3075/2021, dated 13 December, 2021; file no. 004189/BP/DTCP/3075/0004/2021; authority stated as Naspur Municipality/Municipal Corporation.
Commencement / building-permit document: Document titled “Commencement Certificates for each building in each phase”; the extracted record describes an approval for one stilt-plus-five-upper-floor building.
Form B declaration: Form-B affidavit-cum-declaration records title, separate-account, audit, approvals and completion undertakings; the extracted declaration date is unreadable.
Floor-plan document: Floor-plan upload is listed as doc 259829; the project evidence includes software-measured 2BHK drawing data from that document, but a full extracted drawing description is not supplied.
Occupancy / completion certificate: Not supplied in the available project documents.
The building approval lists conditions covering sanctioned-plan conformity, rainwater harvesting, transformer space, waste segregation, parking use, and occupancy before delivery of possession. This overview records the extracted conditions; the full approval and its conditions should be reviewed in the approvals assessment.
Frequently asked questions
Is RAJA RAJESHWARA RESIDENCY registered with Telangana RERA?
Yes. RAJA RAJESHWARA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P01200005349; the registration status is New Project.
Who is the developer of RAJA RAJESHWARA RESIDENCY?
The promoter named in the RERA registration is GOLDEN TOWER.
Where is RAJA RAJESHWARA RESIDENCY located?
RAJA RAJESHWARA RESIDENCY is in NASPUR, Mancherial, Telangana (504302).
When will RAJA RAJESHWARA RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 13/12/2024. This is the promoter's declaration, not a guarantee.
More projects in Naspur