Hitech City
SHATHAMANYU INFRA DEVELOPERS · Peddapalli · RERA P02900006463
HITECH CITY is a residential plotted development in LAXMIPUR, Ramagundam Mandal, Peddapalli District, developed by registered promoter SHATHAMANYU INFRA DEVELOPERS. The RERA land record states a total and net area of 130041.21 sq. m; the tentative layout approval records 361 residential plots, with no tower, block, floor or plot-size configuration stated in the RERA record. The project is registered under TG-RERA number P02900006463, issued 07/07/2023, with validity stated through 11/02/2026; the promoter-declared completion date is 11/02/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | HITECH CITY RERA record |
| Project type and phase | Plotted development / residential layout; registered phase or separately defined portion: not disclosed RERA record |
| TG-RERA registration | P02900006463; Form C issued 07/07/2023; validity stated as 07/07/2023 to 11/02/2026. The certificate says validity may be extended by the Authority; an extension is not recorded in the supplied certificate. Approvals record |
| RERA-record status | Listed as “New Project”; the supplied registration record does not establish current completion or occupancy status. RERA record RERA filing |
| Registered promoter | SHATHAMANYU INFRA DEVELOPERS, a partnership firm; firm registration number 370 OF 2021. RERA record Corporate record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / recorded project location | LAXMIPUR / LAXMIPURAM Revenue Village; the registration certificate gives the locality as LAXMIPUR. RERA record |
| Mandal | Ramagundam; the layout approval describes Ramagundam Municipal Corporation Mandal. RERA record |
| District | Peddapalli; the layout approval spells this “Peddapally.” RERA record |
| PIN | 505210 in the project record and registration certificate. RERA record |
| Project survey numbers and subdivisions | 257/3, 258/3, 259, 260/2, 263A, 263/AA/2, 264A, 264E, 266AA, 267AA, 267E, 320A. RERA record |
| Site extent | RERA land record: 130041.21 sq. m total and net area. Layout approval: 32 Acer 5.33 Gts 155528 Sq. Yds layout extent. Land records |
| Boundaries in RERA land record | East: LAND OF OTHERS; West: LAND OF OTHERS; North: LAND OF OTHERS; South: LAND OF OTHERS RAILWAY TRACK. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Ramagundam Municipal Corporation. Approvals record |
| Principal layout approval | Tentative layout plan approval 0020/LO/3015/2023; approval date recorded as 11/02/2023. Application number: 011980/LO/DTCP/3015/0034/2022. Approvals record RERA filing |
| Approval status and scope | The filed document is an approval for a tentative layout plan for residential plots—not evidence of final layout release. |
| Plots | The approval extraction states 361 No's; it does not provide an approved built-up area, building count or floor configuration for this plotted layout. |
| Approved built-up area / buildings | Not disclosed for this plotted development. The RERA record lists 65970.44 sq. m as approved built-up area, but its scope is not explained in the supplied fields; it is not treated here as an individual plot or home-area figure. RERA filing |
| Road, park and other land allocation in the approval | Plotted area: 50.9%; road area: 36.36%; open-space park: 9.05%; social infrastructure: 2.68%; utilities: 1%. |
Offering and status
| Field | Record |
|---|---|
| Offering | Residential plots. The supplied RERA approval extraction identifies 361 plots; no RERA unit-type schedule, plot-by-plot inventory, booked/available count or RERA-filed plot-size range is supplied. |
| Promoter-declared completion date | 11/02/2026, as stated in the Form-B declaration and project record. RERA record |
| Construction / development stage | Current physical development stage is not established by the supplied records. RERA amenity entries show 0 progress for the listed items; no independent site verification is supplied. RERA amenities |
| Occupancy / completion certificate | Not supplied. The available municipal approval is tentative layout approval, not an occupancy or completion certificate. |
2. The project story
HITECH CITY is registered as a residential plotted development in LAXMIPURAM Revenue Village, Ramagundam Mandal, Peddapalli District. The municipal approval on file is for a tentative residential layout and records 361 plots. The approval describes a layout with internal roads, park/open space, social-infrastructure land and utility land; it also places responsibility for layout development works on the applicant. RERA record
The promoter’s Form-B declaration undertakes completion by 11/02/2026. That is a promoter declaration, not an independently verified construction-completion finding. The supplied record does not establish current on-site progress, final layout release, or an occupancy/completion certificate. RERA amenities
3. Master plan, architecture & building design
This is a plotted layout, so the available design evidence concerns land division and layout infrastructure rather than apartment blocks or building plans. The tentative layout approval allocates the layout area as follows:
| Layout use | Approval figure |
|---|---|
| Plotted area | 16 Acer 12.05 Gts 78900 Sq. Yds; 50.9% |
| Roads | 11 Acer 25.69 Gts 56350 Sq. Yds; 36.36% |
| Open space (park) | 2 Acer 35.98 Gts 14034 Sq. Yds; 9.05% |
| Social infrastructure | 0 Acer 34.39 Gts 4161 Sq. Yds; 2.68% |
| Utilities | 0 Acer 12.81 Gts 1551 Sq. Yds; 1% |
| Layout extent stated in approval | 32 Acer 5.33 Gts 155528 Sq. Yds |
A separate software extraction from the approved layout drawing reports the land-use areas as 65968.64 sq. m for plots, 47114.04 sq. m for roads, 11733.94 sq. m for parks/open space, 1296.45 sq. m for utilities and 3479.21 sq. m for social infrastructure, over a stated base of 129592.28 sq. m. These are drawing-derived figures and should be checked against the drawing; the extraction also notes the plot schedule is incomplete and contains no plot sizes. Layout record
The approval describes tentative layout infrastructure and directs that roads be made accessible to neighbouring sites, with no compound wall or fencing around the site. It does not provide evidence of apartment towers, floor levels, parking floors, or a building-wise residential/commercial arrangement.
4. Homes, configurations & floor plans
The RERA-filed approval describes 361 residential plots. A plot-by-plot schedule, RERA-filed plot-size range, and booked or available inventory are not present in the supplied data.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading |
|---|---|---|---|---|---|---|
| Residential plots | 361 (as stated in tentative layout approval) | Not disclosed | Not disclosed | Not disclosed | Not applicable / not supplied | Not supplied |
The vendor section lists plot sizes of 1158 Sq. Ft. and 5339 Sq. Ft., but these are vendor-attributed figures, not a RERA-filed plot schedule. Promoter website The two available drawing sheets are layout sheets; the floor-plan extraction reports no flats and no measured home areas. Floor plans
5. Parking & vehicle circulation
The supplied records do not state parking-space counts, visitor or accessible parking, parking allotments, or EV charging. The tentative layout approval identifies roads and requires road accessibility, but does not establish parking provision or exclusive parking rights for any plot.
6. Amenities, recreation & open spaces
The tentative layout approval describes planned layout works and allocated public/open-space areas. Its amenity record marks progress as 0 for listed items, and no independent completion verification is supplied. RERA amenities
| Description / size | Approval reserves 2 Acer 35.98 Gts 14034 Sq. Yds (9.05%) for open space (park). |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Planned / reserved in tentative approval; completion not verified. |
| Description / size | 0 Acer 34.39 Gts 4161 Sq. Yds (2.68%). |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Land reserved; facility details and completion status not supplied. |
| Description / size | No size or facility description supplied. |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | Progress shown as 0; completion not verified. |
| Description / size | Internal roads are listed; the approval calls for road formation with black top. |
|---|---|
| Evidence source | RERA amenity record RERA amenities; tentative layout approval |
| Declared progress / verified status | Progress shown as 0; completion not verified. |
| Description / size | Listed in the RERA amenity record; no separate dimensions supplied. |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | Progress shown as 0; completion not verified. |
7. Utilities, building services & safety
The tentative layout approval describes proposed infrastructure works, including an assured water supply source, internal water-supply pipelines, overhead tank, water reservoir, underground drainage, common septic tank/STP, storm-water drains, electrical supply lines, transformer, street lighting, solid-waste management, avenue planting and rainwater-harvesting pits. These are approval-described works, not proof that the facilities have been completed or are operating.
| Evidence in supplied records | Water reservoir, internal supply pipelines, overhead tank and an assured water-supply source are described in the approval. |
|---|---|
| Status / limitation | Proposed layout works; source, storage capacity and completion are not supplied. |
| Evidence in supplied records | Underground drainage lines and common septic tank/STP are described; sewerage, storm-water drainage and sewage/sullage treatment are listed in the RERA amenity record. |
|---|---|
| Status / limitation | Progress shown as 0 in the amenity record; capacity and operating status are not supplied. RERA amenities |
| Evidence in supplied records | Electrical supply lines, street lights and transformer are described; an electrical meter room/sub-station/receiving station is listed in the RERA amenity record. |
|---|---|
| Status / limitation | Proposed/listed; no capacity or completion verification supplied. RERA amenities |
| Evidence in supplied records | Solid-waste management is described in the approval and listed in the RERA amenity record. |
|---|---|
| Status / limitation | Progress shown as 0 in the amenity record; operational details are not supplied. RERA amenities |
| Evidence in supplied records | Rainwater-harvesting pits are described in the approval and water conservation/rainwater harvesting is listed in the RERA amenity record. |
|---|---|
| Status / limitation | Proposed/listed; completion is not verified. RERA amenities |
| Evidence in supplied records | Fire protection and fire-safety requirements appear in the RERA amenity record. |
|---|---|
| Status / limitation | No system specifications, clearances or completion evidence supplied. RERA amenities |
| Evidence in supplied records | Not disclosed in the supplied records. |
|---|---|
| Status / limitation | No capacities or completion status can be stated. |
8. Location, access & connectivity
The registered location is LAXMIPUR / LAXMIPURAM Revenue Village, Ramagundam Mandal, Peddapalli District, PIN 505210. The project record lists land boundaries as land of others to the east, west and north, and land of others plus a railway track to the south. RERA record RERA filing
A supplied location record gives a geocode at 18.7161424, 79.4973417, identified as Urban Health Centre, Laxmipur, Ring Road, Sarada Nagar, Ramagundam. The sampled connectivity record lists the nearest sampled Outer Ring Road interchange at 161.7 km (approx.). This is a recorded sampled distance, not a travel-time estimate. Location record
9. Developer & development status
The registered promoter is SHATHAMANYU INFRA DEVELOPERS, a partnership firm, GSTIN 36AELFS7821N1ZA, with firm registration number 370 OF 2021. The project record gives the promoter address as B, G M COLONY, LAXMIPURAM, RAMAGUNDAM MUNICIPAL CORPORATION, Ramagundam, Peddapalli, 505210. The RERA certificate separately records the promoter office as Village G.M COLONY, Mandal Ramagundam, District Peddapalli, PIN 505209. Corporate record RERA record
The Form-B affidavit, signed by authorized signatory Hari Krishna Rao Gandra, declares the land is free from encumbrances and undertakes completion by 11/02/2026. These are promoter declarations. The supplied records do not provide a verified construction-progress percentage or establish that layout works are complete. RERA amenities
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C for HITECH CITY, registration P02900006463, issued 07/07/2023, stated valid through 11/02/2026. |
| Principal layout approval | Tentative residential layout plan 0020/LO/3015/2023, issued by Ramagundam Municipal Corporation; application 011980/LO/DTCP/3015/0034/2022. |
| Form-B declaration | Promoter affidavit recording the completion undertaking and other promoter declarations. |
| Layout drawing | Software-extracted land-use information; the drawing extraction states plot counts and sizes should be verified against the drawing and notes an incomplete plot schedule. Layout record |
| Completion / occupancy certificate | Not supplied. The available municipal record is a tentative layout approval. |
| Other layout-approval identifiers | Receipts TS/30767/2022 and TS/30768/2022 dated 16 November, 2022; receipt TS/32893/2022 dated 10 January, 2023; mortgage deed 645/2023 dated 24 January, 2023. |
1. Project at a glance
Project identity
Registered project name: HITECH CITY
Project type and phase: Plotted development / residential layout; registered phase or separately defined portion: not disclosed
TG-RERA registration: P02900006463; Form C issued 07/07/2023; validity stated as 07/07/2023 to 11/02/2026. The certificate says validity may be extended by the Authority; an extension is not recorded in the supplied certificate.
RERA-record status: Listed as “New Project”; the supplied registration record does not establish current completion or occupancy status.
Registered promoter: SHATHAMANYU INFRA DEVELOPERS, a partnership firm; firm registration number 370 OF 2021.
Land and geographic identity
Locality / recorded project location: LAXMIPUR / LAXMIPURAM Revenue Village; the registration certificate gives the locality as LAXMIPUR.
Mandal: Ramagundam; the layout approval describes Ramagundam Municipal Corporation Mandal.
District: Peddapalli; the layout approval spells this “Peddapally.”
PIN: 505210 in the project record and registration certificate.
Project survey numbers and subdivisions: 257/3, 258/3, 259, 260/2, 263A, 263/AA/2, 264A, 264E, 266AA, 267AA, 267E, 320A.
Site extent: RERA land record: 130041.21 sq. m total and net area. Layout approval: 32 Acer 5.33 Gts 155528 Sq. Yds layout extent.
Boundaries in RERA land record: East: LAND OF OTHERS; West: LAND OF OTHERS; North: LAND OF OTHERS; South: LAND OF OTHERS RAILWAY TRACK.
Development identity
Sanctioning authority: Ramagundam Municipal Corporation.
Principal layout approval: Tentative layout plan approval 0020/LO/3015/2023; approval date recorded as 11/02/2023. Application number: 011980/LO/DTCP/3015/0034/2022.
Approval status and scope: The filed document is an approval for a tentative layout plan for residential plots—not evidence of final layout release.
Plots: The approval extraction states 361 No's; it does not provide an approved built-up area, building count or floor configuration for this plotted layout.
Approved built-up area / buildings: Not disclosed for this plotted development. The RERA record lists 65970.44 sq. m as approved built-up area, but its scope is not explained in the supplied fields; it is not treated here as an individual plot or home-area figure.
Road, park and other land allocation in the approval: Plotted area: 50.9%; road area: 36.36%; open-space park: 9.05%; social infrastructure: 2.68%; utilities: 1%.
Offering and status
Offering: Residential plots. The supplied RERA approval extraction identifies 361 plots; no RERA unit-type schedule, plot-by-plot inventory, booked/available count or RERA-filed plot-size range is supplied.
Promoter-declared completion date: 11/02/2026, as stated in the Form-B declaration and project record.
Construction / development stage: Current physical development stage is not established by the supplied records. RERA amenity entries show 0 progress for the listed items; no independent site verification is supplied.
Occupancy / completion certificate: Not supplied. The available municipal approval is tentative layout approval, not an occupancy or completion certificate.
2. The project story
HITECH CITY is registered as a residential plotted development in LAXMIPURAM Revenue Village, Ramagundam Mandal, Peddapalli District. The municipal approval on file is for a tentative residential layout and records 361 plots. The approval describes a layout with internal roads, park/open space, social-infrastructure land and utility land; it also places responsibility for layout development works on the applicant.
The promoter’s Form-B declaration undertakes completion by 11/02/2026. That is a promoter declaration, not an independently verified construction-completion finding. The supplied record does not establish current on-site progress, final layout release, or an occupancy/completion certificate.
3. Master plan, architecture & building design
This is a plotted layout, so the available design evidence concerns land division and layout infrastructure rather than apartment blocks or building plans. The tentative layout approval allocates the layout area as follows:
Plotted area: 16 Acer 12.05 Gts 78900 Sq. Yds; 50.9%
Roads: 11 Acer 25.69 Gts 56350 Sq. Yds; 36.36%
Open space (park): 2 Acer 35.98 Gts 14034 Sq. Yds; 9.05%
Social infrastructure: 0 Acer 34.39 Gts 4161 Sq. Yds; 2.68%
Utilities: 0 Acer 12.81 Gts 1551 Sq. Yds; 1%
Layout extent stated in approval: 32 Acer 5.33 Gts 155528 Sq. Yds
A separate software extraction from the approved layout drawing reports the land-use areas as 65968.64 sq. m for plots, 47114.04 sq. m for roads, 11733.94 sq. m for parks/open space, 1296.45 sq. m for utilities and 3479.21 sq. m for social infrastructure, over a stated base of 129592.28 sq. m. These are drawing-derived figures and should be checked against the drawing; the extraction also notes the plot schedule is incomplete and contains no plot sizes.
The approval describes tentative layout infrastructure and directs that roads be made accessible to neighbouring sites, with no compound wall or fencing around the site. It does not provide evidence of apartment towers, floor levels, parking floors, or a building-wise residential/commercial arrangement.
4. Homes, configurations & floor plans
The RERA-filed approval describes 361 residential plots. A plot-by-plot schedule, RERA-filed plot-size range, and booked or available inventory are not present in the supplied data.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading |
|---|---|---|---|---|---|---|
| Residential plots | 361 (as stated in tentative layout approval) | Not disclosed | Not disclosed | Not disclosed | Not applicable / not supplied | Not supplied |
The vendor section lists plot sizes of 1158 Sq. Ft. and 5339 Sq. Ft., but these are vendor-attributed figures, not a RERA-filed plot schedule. The two available drawing sheets are layout sheets; the floor-plan extraction reports no flats and no measured home areas.
5. Parking & vehicle circulation
The supplied records do not state parking-space counts, visitor or accessible parking, parking allotments, or EV charging. The tentative layout approval identifies roads and requires road accessibility, but does not establish parking provision or exclusive parking rights for any plot.
6. Amenities, recreation & open spaces
The tentative layout approval describes planned layout works and allocated public/open-space areas. Its amenity record marks progress as 0 for listed items, and no independent completion verification is supplied.
| Description / size | Approval reserves 2 Acer 35.98 Gts 14034 Sq. Yds (9.05%) for open space (park). |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Planned / reserved in tentative approval; completion not verified. |
| Description / size | 0 Acer 34.39 Gts 4161 Sq. Yds (2.68%). |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Land reserved; facility details and completion status not supplied. |
| Description / size | No size or facility description supplied. |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | Progress shown as 0; completion not verified. |
| Description / size | Internal roads are listed; the approval calls for road formation with black top. |
|---|---|
| Evidence source | RERA amenity record; tentative layout approval |
| Declared progress / verified status | Progress shown as 0; completion not verified. |
| Description / size | Listed in the RERA amenity record; no separate dimensions supplied. |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | Progress shown as 0; completion not verified. |
7. Utilities, building services & safety
The tentative layout approval describes proposed infrastructure works, including an assured water supply source, internal water-supply pipelines, overhead tank, water reservoir, underground drainage, common septic tank/STP, storm-water drains, electrical supply lines, transformer, street lighting, solid-waste management, avenue planting and rainwater-harvesting pits. These are approval-described works, not proof that the facilities have been completed or are operating.
| Evidence in supplied records | Water reservoir, internal supply pipelines, overhead tank and an assured water-supply source are described in the approval. |
|---|---|
| Status / limitation | Proposed layout works; source, storage capacity and completion are not supplied. |
| Evidence in supplied records | Underground drainage lines and common septic tank/STP are described; sewerage, storm-water drainage and sewage/sullage treatment are listed in the RERA amenity record. |
|---|---|
| Status / limitation | Progress shown as 0 in the amenity record; capacity and operating status are not supplied. |
| Evidence in supplied records | Electrical supply lines, street lights and transformer are described; an electrical meter room/sub-station/receiving station is listed in the RERA amenity record. |
|---|---|
| Status / limitation | Proposed/listed; no capacity or completion verification supplied. |
| Evidence in supplied records | Solid-waste management is described in the approval and listed in the RERA amenity record. |
|---|---|
| Status / limitation | Progress shown as 0 in the amenity record; operational details are not supplied. |
| Evidence in supplied records | Rainwater-harvesting pits are described in the approval and water conservation/rainwater harvesting is listed in the RERA amenity record. |
|---|---|
| Status / limitation | Proposed/listed; completion is not verified. |
| Evidence in supplied records | Fire protection and fire-safety requirements appear in the RERA amenity record. |
|---|---|
| Status / limitation | No system specifications, clearances or completion evidence supplied. |
| Evidence in supplied records | Not disclosed in the supplied records. |
|---|---|
| Status / limitation | No capacities or completion status can be stated. |
8. Location, access & connectivity
The registered location is LAXMIPUR / LAXMIPURAM Revenue Village, Ramagundam Mandal, Peddapalli District, PIN 505210. The project record lists land boundaries as land of others to the east, west and north, and land of others plus a railway track to the south.
A supplied location record gives a geocode at 18.7161424, 79.4973417, identified as Urban Health Centre, Laxmipur, Ring Road, Sarada Nagar, Ramagundam. The sampled connectivity record lists the nearest sampled Outer Ring Road interchange at 161.7 km (approx.). This is a recorded sampled distance, not a travel-time estimate.
9. Developer & development status
The registered promoter is SHATHAMANYU INFRA DEVELOPERS, a partnership firm, GSTIN 36AELFS7821N1ZA, with firm registration number 370 OF 2021. The project record gives the promoter address as B, G M COLONY, LAXMIPURAM, RAMAGUNDAM MUNICIPAL CORPORATION, Ramagundam, Peddapalli, 505210. The RERA certificate separately records the promoter office as Village G.M COLONY, Mandal Ramagundam, District Peddapalli, PIN 505209.
The Form-B affidavit, signed by authorized signatory Hari Krishna Rao Gandra, declares the land is free from encumbrances and undertakes completion by 11/02/2026. These are promoter declarations. The supplied records do not provide a verified construction-progress percentage or establish that layout works are complete.
10. Approvals, official records & documents
TG-RERA registration: Form C for HITECH CITY, registration P02900006463, issued 07/07/2023, stated valid through 11/02/2026.
Principal layout approval: Tentative residential layout plan 0020/LO/3015/2023, issued by Ramagundam Municipal Corporation; application 011980/LO/DTCP/3015/0034/2022.
Form-B declaration: Promoter affidavit recording the completion undertaking and other promoter declarations.
Layout drawing: Software-extracted land-use information; the drawing extraction states plot counts and sizes should be verified against the drawing and notes an incomplete plot schedule.
Completion / occupancy certificate: Not supplied. The available municipal record is a tentative layout approval.
Other layout-approval identifiers: Receipts TS/30767/2022 and TS/30768/2022 dated 16 November, 2022; receipt TS/32893/2022 dated 10 January, 2023; mortgage deed 645/2023 dated 24 January, 2023.
Frequently asked questions
Is HITECH CITY registered with Telangana RERA?
Yes. HITECH CITY is registered with the Telangana Real Estate Regulatory Authority as P02900006463; the registration status is New Project.
Who is the developer of HITECH CITY?
The promoter named in the RERA registration is SHATHAMANYU INFRA DEVELOPERS.
Where is HITECH CITY located?
HITECH CITY is in RAMAGUNDAM MUNICIPAL CORPORATION, LAXMIPUR, Ramagundam, Peddapalli, Telangana (505210).
When will HITECH CITY be completed?
The promoter's proposed date of completion filed with RERA is 11/02/2026. This is the promoter's declaration, not a guarantee.