DHANALAXMI NAGAR is a plotted development with open plots in Medak, MEDAK Mandal, Medak District. The registered promoter developing the project is DHANALAXMI NAGAR. The project covers 16,234.99 sq.m and comprises 51 plots; plot sizes are 52.89 sq.m to 277.54 sq.m, with no building or floor configuration disclosed. Its TG-RERA registration is P01000008819, and its proposed completion date is 30/11/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
11 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | DHANALAXMI NAGAR RERA record |
| Project type | Plotted development / layout with open plots RERA record |
| Phase / registered portion | No separate phase name is disclosed; the registration is for the listed project land RERA record |
| TG-RERA registration | P01000008819 RERA record |
| Registration validity | 27 March 2024 to 27 March 2026; the certificate states a two-year validity unless extended by the Authority RERA record |
| Registered promoter | DHANALAXMI NAGAR RERA record Corporate record |
| RERA status | New Project; the record gives the registration validity above. A later extension or current portal status is not supplied RERA record Approvals record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality | Medak RERA record |
| Revenue village | Medak Revenue Village; the approval also describes the site as MEDAK MUNICIPALITY (VILLAGE) RERA record |
| Mandal / district / PIN | MEDAK Mandal / Medak District / 502110 RERA record |
| All project survey numbers and subdivisions | 1530/A4/2, 1527/E1/1, 1530/A4/1/2/2, 1529/A1/2/1/1/2/2, 1529/A1/2/1/2, 1527/AA1/2, 1530/A1/1/1/2, 1531/A2/2, 1527/E1/2, 1530/A1/3, 1530/A4/3, 1529/A1/1/1/2, 1530/A4/1/2/1/1/2, 1530/A4/4, 1530/A1/4, 1529/A1/1/2, 1530/A1/2, 1530/A4/5, 1530/A1/5, 1530/A4/1/3, 1531/A1/2, 1530/A5, 1527/AA1/1, 1529/A1/2/2, 1530/A1/1/2, 1530/A4/1/1/2 |
| Registered site extent | Total land area 16,234.99 sq.m; net layout area 16,069.33 sq.m. The RERA land record also identifies 165.66 sq.m as affected by road widening/FTL of tanks/nala widening RERA filing |
| Boundaries | East: Neighbours Land; West: Road; North: Neighbours Land; South: Neighbours Land RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Medak Municipality / Municipal Corporation; the RERA filing identifies DTCP as the authority name Approvals record |
| Principal layout approval | Tentative Layout Plan 0016/LO/3053/2024, approved 27 March 2024 |
| Drawing / permit reference | TS/038111/2023, dated 01-06-2023 on the layout drawing Approvals record |
| Approved development | Layout with open plots; 51 plots |
| Approved built-up area | 9,287.48 sq.m is recorded as approved built-up area in the project filing; it is not a building configuration or a count of homes RERA filing |
| Buildings / floors | Building count, floor configuration and parking levels are not disclosed for this plotted layout |
| Parking | The layout approval records 0 proposed number of parkings and 0.00 common parking area |
Offering and status
| Field | Record |
|---|---|
| Offering | 51 open plots |
| Plot sizes | Drawing-derived schedule: 51 plots with sizes from 52.89 sq.m to 277.54 sq.m; software-read from the approved layout drawing and subject to drawing verification Layout record |
| Booked / available | Counts are not supplied RERA unit table |
| Construction / infrastructure stage | RERA filing reports internal roads and footpaths at 80%, water supply at 100%, and several other layout services at 50%; these are filed progress figures, not independent site verification RERA amenities |
| Completion dates | Form B contains a promoter undertaking to complete by 27 March 2026; the registered project record gives proposed completion 30/11/2026 RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied; the project is a plotted layout Document index |
2. The project story
Dhanalaxmi Nagar is a 51-plot residential layout in Medak Revenue Village, Medak Mandal, Medak District. Its approved plan allocates land to individual plots, internal and adjoining roads, open space/park, social infrastructure and utilities. The approval specifies that only detached single-family dwelling houses may be built on a site and excludes shops, business premises and industrial units except at sites specifically reserved for such proposals in the draft layout. The supplied plan identifies no amenity-area allocation and no common parking area.
The project’s filed progress figures describe infrastructure work rather than the completion of houses: water supply is reported at 100%, internal roads and footpaths at 80%, and sewerage, storm-water drains, park/green strip, street lighting, water conservation/rainwater harvesting and the electrical meter room/substation at 50%. These are RERA-filed percentages; no independent site inspection or verification is supplied. RERA amenities
The RERA registration runs from 27 March 2024 to 27 March 2026 unless extended. That is distinct from the completion dates recorded in the project materials: the Form B undertaking says 27 March 2026, while the project record states proposed completion as 30 November 2026. The supplied evidence does not establish whether a registration extension was granted or whether a completion/occupancy certificate has since been issued. RERA record Document index
3. Master plan, architecture & building design
The approved layout drawing records a total site extent of 16,234.99 sq.m and a net layout area of 16,069.33 sq.m. Its land-use table allocates the net layout area as follows:
| Layout use | Area | Share shown on drawing |
|---|---|---|
| Plotted area | 9,287.48 sq.m | 57.80% |
| Road area | 4,761.73 sq.m | 29.63% |
| Organized open space / park area | 1,452.75 sq.m | 9.04% |
| Social infrastructure area | 405.37 sq.m | 2.52% |
| Utility area | 162.00 sq.m | 1.01% |
| Amenity area | 0.00 sq.m | 0.00% |
| Total net layout | 16,069.33 sq.m | 100.00% |
The drawing identifies road widths including 50' WIDE PUMP HOUSE ROAD, 60' WIDE ROAD, 15.24 MT WIDE EXISTING, 18.00 MT WIDE PROPOSED ROAD, 9.14mt wide Internal Road and 9.00mt wide Internal Road. It also labels a pump house, water tank, buffer/tot-lot and social-infrastructure and utility areas. These are layout-plan features; the supplied material does not describe building footprints, floor plans, building height or residential building design.
4. Homes, configurations & floor plans
This is a plotted project, not an apartment configuration schedule. The RERA record identifies 51 plots, but does not provide plot-by-plot booked or available counts. RERA unit table
The drawing’s plot schedule was read by software; the resulting plot sizes and bands are not RERA-filed unit measurements and should be checked against the approved drawing. Layout record
| Plot-size band | Plot count |
|---|---|
| 0–100 sq.yd (0–84 sq.m) | 1 |
| 100–150 sq.yd (84–125 sq.m) | 5 |
| 150–200 sq.yd (125–167 sq.m) | 16 |
| 200–250 sq.yd (167–209 sq.m) | 12 |
| 250–300 sq.yd (209–251 sq.m) | 14 |
| 300–400 sq.yd (251–334 sq.m) | 3 |
The smallest, median and largest software-measured plot areas are 52.89 sq.m, 189.63 sq.m and 277.54 sq.m, respectively. No apartment carpet-area, saleable-area or loading data applies in the supplied records. Layout record
5. Parking & vehicle circulation
The layout approval records 0 proposed number of parkings and 0.00 common parking area. It does not disclose visitor, accessible or allocated plot parking, or parking arrangements within individual future homes.
The layout drawing shows internal roads of 9.14mt and 9.00mt wide, along with the listed wider road connections. These describe the approved road network; the supplied evidence does not establish separate pedestrian routes, vehicle-entry controls or parking allotments to individual plot buyers.
6. Amenities, recreation & open spaces
| Facility | Organized open space / park |
|---|---|
| Description / size | 1,452.75 sq.m (9.04%) of net layout area |
| Declared progress / verified status | RERA filing reports Green Strip/TOT LOT/Park at 50%; no independent completion verification supplied RERA amenities |
| Facility | Buffer tot-lot |
|---|---|
| Description / size | Named on the layout drawing; no size supplied |
| Declared progress / verified status | No separate completion status supplied |
| Facility | Social infrastructure area |
|---|---|
| Description / size | 405.37 sq.m (2.52%) |
| Declared progress / verified status | RERA filing records community buildings at 0%; no independent verification supplied RERA amenities |
| Facility | Amenity area |
|---|---|
| Description / size | 0.00 sq.m (0.00%) in the layout land-use table |
| Declared progress / verified status | Not applicable as a designated area in that table |
The layout approval also names a pump house and water tank; these are site utilities, described in the next section.
7. Utilities, building services & safety
The layout approval lists a water reservoir, septic tank, sewerage treatment plant, electric transformer, solid-waste management, storm-water drains, underground drainage lines, internal water-supply pipelines, overhead tank, street lights, avenue plantation, park development and rainwater-harvesting pits. It requires the developer to provide infrastructure and amenities and to hand over the specified open space, utility and road areas to the Municipality by registered gift deed before release of the tentative layout. The supplied evidence does not establish that these works or handovers have been completed.
RERA-filed progress figures are: water supply 100%; sewerage (chamber, lines, septic tank, STP) 50%; storm-water drains 50%; street lighting 50%; water conservation/rainwater harvesting 50%; and electrical meter room/substation/receiving station 50%. Solid-waste management, treatment and disposal of sewage and sullage water, energy management and fire protection/safety are recorded at 0% in the supplied amenity progress data. These are declared progress figures, not an independent inspection or certification. RERA amenities
No capacities, electrical-backup details, fire-system specifications, accessibility features, security systems or lift information are supplied. Document index RERA amenities
8. Location, access & connectivity
The registered location is Medak, Medak Mandal, Medak District, PIN 502110, within Medak Revenue Village. The site boundaries recorded in the project filing are neighbours’ land to the east, north and south, and a road to the west. RERA record RERA filing
The layout drawing identifies the Pump House Road, a 60-foot road, a 15.24-metre existing road, an 18.00-metre proposed road and internal roads of 9.14 metres and 9.00 metres.
A supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 44.5 km. No other measured distances, public-transport details or local landmark distances are supplied. Location record
9. Developer & development status
The registered promoter is DHANALAXMI NAGAR, identified in the filing as a partnership. Its GSTIN is 36AASFD7434K1ZV; no other corporate identifier is supplied here. The promoter address recorded in the RERA project fields is 5-3-455, Vidya Nagar Colony, Medak Revenue Village, Medak, MEDAK, Medak, 502110. The project’s authorized signatory is listed as SRINIVAS EPPHA. Corporate record Parties record
The promoter’s Form B declaration, signed by EPPHA SRINIVAAS as authorized signatory in July 2024, states that the promoter has legal title, declares the land free from encumbrances and undertakes completion by 27 March 2026. These are promoter declarations in the filed affidavit.
The record reports plotted-layout infrastructure progress, not construction progress for individual homes. The RERA project record’s proposed completion date is 30/11/2026; no extension order or completion/occupancy certificate is supplied. RERA amenities RERA record Document index
10. Approvals, official records & documents
| Record | Evidence and scope |
|---|---|
| TG-RERA registration | Form C registration certificate P01000008819, for DHANALAXMI NAGAR, project type plotted, covering the listed Medak survey numbers; certificate states validity from 27/03/2024 to 27/03/2026, unless extended |
| Layout drawing / permit reference | Approved layout drawing carries TS/038111/2023, dated 01-06-2023 |
| Tentative layout approval | Medak Municipality / Municipal Corporation approval 0016/LO/3053/2024, dated 27 March 2024, for a tentative layout of 51 plots |
| Mortgage / reserved plots in approval | The approval identifies Plots 30, 29, 28, 41, 40, 38, 37, 36, 32, 31 as mortgaged to Medak Municipality / Municipal Corporation; Mortgage Deed No. 4284, dated 23 December 2023 |
| Form B declaration | Promoter affidavit dated July 2024, including title, encumbrance and completion declarations |
| Occupancy / completion certificate | None supplied Document index |
The supplied approval states a two-year infrastructure-and-amenities completion period from 27 March 2024, identifies the municipality handover requirements, and describes the approval as tentative.
1. Project at a glance
Project identity
Registered project name: DHANALAXMI NAGAR
Project type: Plotted development / layout with open plots
Phase / registered portion: No separate phase name is disclosed; the registration is for the listed project land
TG-RERA registration: P01000008819
Registration validity: 27 March 2024 to 27 March 2026; the certificate states a two-year validity unless extended by the Authority
Registered promoter: DHANALAXMI NAGAR
RERA status: New Project; the record gives the registration validity above. A later extension or current portal status is not supplied
Land and geographic identity
Locality: Medak
Revenue village: Medak Revenue Village; the approval also describes the site as MEDAK MUNICIPALITY (VILLAGE)
Mandal / district / PIN: MEDAK Mandal / Medak District / 502110
All project survey numbers and subdivisions: 1530/A4/2, 1527/E1/1, 1530/A4/1/2/2, 1529/A1/2/1/1/2/2, 1529/A1/2/1/2, 1527/AA1/2, 1530/A1/1/1/2, 1531/A2/2, 1527/E1/2, 1530/A1/3, 1530/A4/3, 1529/A1/1/1/2, 1530/A4/1/2/1/1/2, 1530/A4/4, 1530/A1/4, 1529/A1/1/2, 1530/A1/2, 1530/A4/5, 1530/A1/5, 1530/A4/1/3, 1531/A1/2, 1530/A5, 1527/AA1/1, 1529/A1/2/2, 1530/A1/1/2, 1530/A4/1/1/2
Registered site extent: Total land area 16,234.99 sq.m; net layout area 16,069.33 sq.m. The RERA land record also identifies 165.66 sq.m as affected by road widening/FTL of tanks/nala widening
Boundaries: East: Neighbours Land; West: Road; North: Neighbours Land; South: Neighbours Land
Development identity
Sanctioning authority: Medak Municipality / Municipal Corporation; the RERA filing identifies DTCP as the authority name
Principal layout approval: Tentative Layout Plan 0016/LO/3053/2024, approved 27 March 2024
Drawing / permit reference: TS/038111/2023, dated 01-06-2023 on the layout drawing
Approved development: Layout with open plots; 51 plots
Approved built-up area: 9,287.48 sq.m is recorded as approved built-up area in the project filing; it is not a building configuration or a count of homes
Buildings / floors: Building count, floor configuration and parking levels are not disclosed for this plotted layout
Parking: The layout approval records 0 proposed number of parkings and 0.00 common parking area
Offering and status
Offering: 51 open plots
Plot sizes: Drawing-derived schedule: 51 plots with sizes from 52.89 sq.m to 277.54 sq.m; software-read from the approved layout drawing and subject to drawing verification
Booked / available: Counts are not supplied
Construction / infrastructure stage: RERA filing reports internal roads and footpaths at 80%, water supply at 100%, and several other layout services at 50%; these are filed progress figures, not independent site verification
Completion dates: Form B contains a promoter undertaking to complete by 27 March 2026; the registered project record gives proposed completion 30/11/2026
Occupancy / completion certificate: No occupancy or completion certificate is supplied; the project is a plotted layout
2. The project story
Dhanalaxmi Nagar is a 51-plot residential layout in Medak Revenue Village, Medak Mandal, Medak District. Its approved plan allocates land to individual plots, internal and adjoining roads, open space/park, social infrastructure and utilities. The approval specifies that only detached single-family dwelling houses may be built on a site and excludes shops, business premises and industrial units except at sites specifically reserved for such proposals in the draft layout. The supplied plan identifies no amenity-area allocation and no common parking area.
The project’s filed progress figures describe infrastructure work rather than the completion of houses: water supply is reported at 100%, internal roads and footpaths at 80%, and sewerage, storm-water drains, park/green strip, street lighting, water conservation/rainwater harvesting and the electrical meter room/substation at 50%. These are RERA-filed percentages; no independent site inspection or verification is supplied.
The RERA registration runs from 27 March 2024 to 27 March 2026 unless extended. That is distinct from the completion dates recorded in the project materials: the Form B undertaking says 27 March 2026, while the project record states proposed completion as 30 November 2026. The supplied evidence does not establish whether a registration extension was granted or whether a completion/occupancy certificate has since been issued.
3. Master plan, architecture & building design
The approved layout drawing records a total site extent of 16,234.99 sq.m and a net layout area of 16,069.33 sq.m. Its land-use table allocates the net layout area as follows:
| Layout use | Area | Share shown on drawing |
|---|---|---|
| Plotted area | 9,287.48 sq.m | 57.80% |
| Road area | 4,761.73 sq.m | 29.63% |
| Organized open space / park area | 1,452.75 sq.m | 9.04% |
| Social infrastructure area | 405.37 sq.m | 2.52% |
| Utility area | 162.00 sq.m | 1.01% |
| Amenity area | 0.00 sq.m | 0.00% |
| Total net layout | 16,069.33 sq.m | 100.00% |
The drawing identifies road widths including 50' WIDE PUMP HOUSE ROAD, 60' WIDE ROAD, 15.24 MT WIDE EXISTING, 18.00 MT WIDE PROPOSED ROAD, 9.14mt wide Internal Road and 9.00mt wide Internal Road. It also labels a pump house, water tank, buffer/tot-lot and social-infrastructure and utility areas. These are layout-plan features; the supplied material does not describe building footprints, floor plans, building height or residential building design.
4. Homes, configurations & floor plans
This is a plotted project, not an apartment configuration schedule. The RERA record identifies 51 plots, but does not provide plot-by-plot booked or available counts.
The drawing’s plot schedule was read by software; the resulting plot sizes and bands are not RERA-filed unit measurements and should be checked against the approved drawing.
0–100 sq.yd (0–84 sq.m): 1
100–150 sq.yd (84–125 sq.m): 5
150–200 sq.yd (125–167 sq.m): 16
200–250 sq.yd (167–209 sq.m): 12
250–300 sq.yd (209–251 sq.m): 14
300–400 sq.yd (251–334 sq.m): 3
The smallest, median and largest software-measured plot areas are 52.89 sq.m, 189.63 sq.m and 277.54 sq.m, respectively. No apartment carpet-area, saleable-area or loading data applies in the supplied records.
5. Parking & vehicle circulation
The layout approval records 0 proposed number of parkings and 0.00 common parking area. It does not disclose visitor, accessible or allocated plot parking, or parking arrangements within individual future homes.
The layout drawing shows internal roads of 9.14mt and 9.00mt wide, along with the listed wider road connections. These describe the approved road network; the supplied evidence does not establish separate pedestrian routes, vehicle-entry controls or parking allotments to individual plot buyers.
6. Amenities, recreation & open spaces
| Facility | Organized open space / park |
|---|---|
| Description / size | 1,452.75 sq.m (9.04%) of net layout area |
| Declared progress / verified status | RERA filing reports Green Strip/TOT LOT/Park at 50%; no independent completion verification supplied |
| Facility | Buffer tot-lot |
|---|---|
| Description / size | Named on the layout drawing; no size supplied |
| Declared progress / verified status | No separate completion status supplied |
| Facility | Social infrastructure area |
|---|---|
| Description / size | 405.37 sq.m (2.52%) |
| Declared progress / verified status | RERA filing records community buildings at 0%; no independent verification supplied |
| Facility | Amenity area |
|---|---|
| Description / size | 0.00 sq.m (0.00%) in the layout land-use table |
| Declared progress / verified status | Not applicable as a designated area in that table |
The layout approval also names a pump house and water tank; these are site utilities, described in the next section.
7. Utilities, building services & safety
The layout approval lists a water reservoir, septic tank, sewerage treatment plant, electric transformer, solid-waste management, storm-water drains, underground drainage lines, internal water-supply pipelines, overhead tank, street lights, avenue plantation, park development and rainwater-harvesting pits. It requires the developer to provide infrastructure and amenities and to hand over the specified open space, utility and road areas to the Municipality by registered gift deed before release of the tentative layout. The supplied evidence does not establish that these works or handovers have been completed.
RERA-filed progress figures are: water supply 100%; sewerage (chamber, lines, septic tank, STP) 50%; storm-water drains 50%; street lighting 50%; water conservation/rainwater harvesting 50%; and electrical meter room/substation/receiving station 50%. Solid-waste management, treatment and disposal of sewage and sullage water, energy management and fire protection/safety are recorded at 0% in the supplied amenity progress data. These are declared progress figures, not an independent inspection or certification.
No capacities, electrical-backup details, fire-system specifications, accessibility features, security systems or lift information are supplied.
8. Location, access & connectivity
The registered location is Medak, Medak Mandal, Medak District, PIN 502110, within Medak Revenue Village. The site boundaries recorded in the project filing are neighbours’ land to the east, north and south, and a road to the west.
The layout drawing identifies the Pump House Road, a 60-foot road, a 15.24-metre existing road, an 18.00-metre proposed road and internal roads of 9.14 metres and 9.00 metres.
A supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 44.5 km. No other measured distances, public-transport details or local landmark distances are supplied.
9. Developer & development status
The registered promoter is DHANALAXMI NAGAR, identified in the filing as a partnership. Its GSTIN is 36AASFD7434K1ZV; no other corporate identifier is supplied here. The promoter address recorded in the RERA project fields is 5-3-455, Vidya Nagar Colony, Medak Revenue Village, Medak, MEDAK, Medak, 502110. The project’s authorized signatory is listed as SRINIVAS EPPHA.
The promoter’s Form B declaration, signed by EPPHA SRINIVAAS as authorized signatory in July 2024, states that the promoter has legal title, declares the land free from encumbrances and undertakes completion by 27 March 2026. These are promoter declarations in the filed affidavit.
The record reports plotted-layout infrastructure progress, not construction progress for individual homes. The RERA project record’s proposed completion date is 30/11/2026; no extension order or completion/occupancy certificate is supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C registration certificate P01000008819, for DHANALAXMI NAGAR, project type plotted, covering the listed Medak survey numbers; certificate states validity from 27/03/2024 to 27/03/2026, unless extended
Layout drawing / permit reference: Approved layout drawing carries TS/038111/2023, dated 01-06-2023
Tentative layout approval: Medak Municipality / Municipal Corporation approval 0016/LO/3053/2024, dated 27 March 2024, for a tentative layout of 51 plots
Mortgage / reserved plots in approval: The approval identifies Plots 30, 29, 28, 41, 40, 38, 37, 36, 32, 31 as mortgaged to Medak Municipality / Municipal Corporation; Mortgage Deed No. 4284, dated 23 December 2023
Form B declaration: Promoter affidavit dated July 2024, including title, encumbrance and completion declarations
Occupancy / completion certificate: None supplied
The supplied approval states a two-year infrastructure-and-amenities completion period from 27 March 2024, identifies the municipality handover requirements, and describes the approval as tentative.
Frequently asked questions
Is DHANALAXMI NAGAR registered with Telangana RERA?
Yes. DHANALAXMI NAGAR is registered with the Telangana Real Estate Regulatory Authority as P01000008819; the registration status is New Project.
Who is the developer of DHANALAXMI NAGAR?
The promoter named in the RERA registration is DHANALAXMI NAGAR.
Where is DHANALAXMI NAGAR located?
DHANALAXMI NAGAR is in Medak, Telangana (502110).
When will DHANALAXMI NAGAR be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.